Project Update: 9/11/2024

 

Floyd Curl Update:

 

Floyd Curl Drive (Hueber Road to Charles Katz) Closure --- Beginning Sunday, September 15, 2024, from 9:00 P.M. to Monday, September 16, 2024, the contractor will close Floyd Curl between Huebner and Fawn Meadow to conduct a concrete pour. Beginning at 6:00 A.M., off-duty police officers will be on-site to facilitate traffic. The roadway will reopen by 2:00 P.M. Electronic signage was put in place to alert drivers of the upcoming closure. For ease of reference, below is a map showing the closure and detour routes. 

 

 

DETOUR MAP

 

 

__________________________________________________________________________________________________________________________________________________________________________________________________________________________________

 

Project Update: 8/23/2024

 

Floyd Curl Update:

The contactor is working on: Roadway reconstruction (southbound lanes).

Planned activities: Roadway excavation.

Lane closures: Floyd Curl Southbound lanes – barricaded work zone.  Two-way traffice will be maintained. See map provided.

Hamilton Wolfe (from Babcock to Cinnamon Hill Drive) is reduced to two lanes -- one in each direction -- through mid-October

 

Hamilton Wolfe Update:

The contactor is working on: Pedestrian bridge rip rap excavation, storm drain, and irrigation main. 

Planned activities: Bridge rap rap, sidewalk and cycle track construction, driveways, and curb ramps.

Lane closures: Hamilton Wolfe Eastbound lanes – barricaded work zone. Two-way traffice will be maintained. See map provided

DETOUR MAP

 

Floyd Curl Roadway Construction

 

 

Hamilton Wolfe Progress

_____________________________________________________________________________________________________________________________________________________________________________________________

Project Update: 7/23/2024

 

The contractor will perform a closure of Hamilton Wolfe on the eastside of Floyd Curl for approximately 3 weeks (no through traffic on Hamilton Wolfe at the intersection). This closure is necessary to construct the concrete paving through the intersection (constructing Floyd Curl NB direction). Traffic on Hamilton Wolfe will be detoured through Floyd Curl, Wurzbach, and Ewing Hassell. The traffic along Floyd Curl will not be affected. Detours to be implemented on Wednesday, July 31, 2024 weather permitting. Businesses will continue to have vehicular access.

 

 

 

Detour Map

____________________________________________________________________________________________________________________________


NOTE TO BUSINESS OWNERS:

If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.


Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.


 

Question title

To receive project updates and details on future public meetings, please provide the following information.

Question title

Please share any feedback or questions about this project.

Project Presentation Documents