2022-2027 Bond Project: Floyd Curl Drive (Huebner Road to Charles Katz)
2022-2027 Bond Project: Floyd Curl Drive (Huebner Road to Charles Katz)
The Project will construct roadway improvements to include curbs, driveway approaches, drainage, and other improvements as applicable and within available funding.
Project Type: Streets, Bridges, & Sidewalks
Phase: Design Phase
Project Contact: LaShondra Gladney - (210) 207-0620
Estimated Construction Timeline: Winter 2024-Spring 2025
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
| |||||||||
Associated Projects:
Project Limits:
Project Update: 11.26.2024
FLOYD CYRL UPDATE: Beginning December 10 until December 11, 2024, from 9:00 am until 5:00pm each day, EZ Bel will be closing the eastern approach of the Floyd Curl & Hamilton Wolfe intersection. The closure is to deliver and install materials at the SE corner of Hamilton Wolfe and Floyd Curl. Delivery and Installation should last two (2) days. The intersection closure will be in place until December 12, 2024. Barricades will be removed at the close of business each day. The closure dates and times are weather permitting.
A detour will be in place during the closure time. Please see attached closure and detour map.
__________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Project Update: 11.4.2024
Hamilton Wolfe Update: Starting 11.5.2024 at 9PM E-Z Bel will be pouring concrete causing a closure of Hamilton Wolfe on the East and West sides of the intersection. Northbound and Southbound traffic on Floyd Curl will still have access during the closure. This closure will be needed until the following morning on 11/6.
CLOSURE AREA
DETOUR MAP
___________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Project Update: 10/18/2024
Floyd Curl Update:
Floyd Curl Drive (Huebner Roald to Charles Katz) Closure: Beginning Monday October 21, 2024 starting at 9 PM, the intersection of Hamilton Wolfe and Floyd Curl and the intersection of Charles Katz and Floyd Curl will be closed. Closure will end at 2 PM Tuesday, October 22, 2024. Please see attached maps provided
CLOSURE MAP
DETOUR MAP
___________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
Project Update: 10/1/2024
Floyd Curl Update:
Hamilton Wolfe Traffic Switch: Beginning Thursday October 3, 2024, the contractor will be switching traffic on Hamilton Wolfe moving traffic from the westbound lanes to the eastbound lanes. Please see the map provided.
Hamilton Wolfe Traffic Switch
Floyd Curl Drive (Huebner Roald to Charles Katz) Closure - Beginning Tuesday, October 8, 2024, from 12:00 A.M. to Wednesday, October 9, 2024, at 2:00 P.M., the contractor will close Floyd Curl between Oakland Drive and Hamilton Wolfe for concrete pours. Beginning at 6:00 A.M., the contractor will have 1-lane, two-way traffic with off-duty police officers on-site to facilitate traffic. Electronic signage is in place to alert drivers of the upcoming closure. For ease of reference, below is a map showing the closure and available traffic route.
Closure Area
Detour Route
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.