Skip Navigation

Project logo Neighborhood Water Line Enhancement Projects Area 8

Project logo Neighborhood Water Line Enhancement Projects Area 8

 Asheville Water Resources has identified several areas for neighborhood water line replacements beginning in the spring of 2026.

General Information

Background

The scope of work for this project includes the installation of approximately 22,000 feet of ductile iron water line and related components, including new residential and commercial service connections.

The project is located in various neighborhoods and commercial corridors throughout the water service district. Project areas include:

  • Euclid Parkway
  • Avon Parkway
  • Saint Charles Place
  • Marlowe Drive
  • Donna Drive
  • Cross Place
  • Greenlee Drive
  • Wamboldt Ave
  • Euclid Blvd
  • Success Ave
  • Lane Ave
  • Inglewood Ave
  • Meadow Brook Ave
  • Dunn Street
  • Clinton Ave
  • Stewart Street
  • Granada Street
  • Cordova Street
  • Moreview Drive
  • Iris Street
  • Forest Street
  • Deanwood Circle
  • Arbutus Road
  • Merrimon Ave at Beaver Creek bridge. 

The project will mostly replace existing problematic water lines; which have been identified as a need through a prioritization and master planning process, due to age, pipe failures and future water capacity needs.

Following an audit of the bids by City staff and the project engineers, TP Howard’s Plumbing Co. Inc. was selected as the lowest responsible, responsive bidder.

Total contract amount is  $8,135,000.00. 

Timeline

The project experienced significant progress in October, with main and service lines fully installed on East Euclid Parkway and waterline work completed at 47 East Avon. Crews have also mobilized into Donna Dr. and Marlowe Dr., where residents may continue to see temporary traffic control and construction activity, anticipated paving operations, and potential water service impacts for meter transfers. Notifications will be sent in advance of scheduled service interruptions.

Crews will begin work in the area of Cross Pl. and Greenlee Ave. in the next month or so. This page will be updated as that process begins. The project is currently tracking approximately one month ahead of schedule, with a revised estimated completion date of February, 2028.

Map of Project Areas

aerial map showing waterline construction areas

 

Contact Information

Clay Chandler, Water Resources Public Information Officer

828-259-5419

cchandler@ashevillenc.gov