Happening Now

Construction began in July 2025 after City Council approved a contract with Appalachian Sitework.

Lane closures associated with this project will only occur at night in order to avoid congestion.
 

Next Milestone: Project estimated to be complete in late 2025.
 

w patton sidewalk

 

Background

The Patton Avenue sidewalk is one of several transportation projects prioritized by City residents during public outreach for the 2016 bond referendum. This project enhances the City’s sidewalk network by constructing a new sidewalk and connecting to existing sidewalk along the eastbound lanes of Patton Avenue from Druid Avenue to Louisiana Avenue, a total length of approximately 0.45 miles. The project also includes curb ramps, crosswalks, and bus stop pad upgrades to meet standards of Americans with Disibilities Act.

The purpose of this project is to improve mobility, safety, and continuity for pedestrians on City streets and provide pedestrian connections to important commercial and public amenities. 

Supporting Documents

Living Asheville Comprehensive Plan

Close the GAP Plan

 
 
 

live
live
Construction

planned
planned
Project Completion

complete
complete
Advertise and Select Construction Firm - 2025

complete
complete
Advertise for Construction - 2023

In 2023 this project was advertised for construction but did not receive adequate bids.

complete
complete
Design Phase

See Process for more information.

complete
complete
2016 Bond Referendum approved by voters

The Patton Avenue sidewalk project was identified for bond funding under “Streets, Sidewalks & Bike Lanes”.