Skip Navigation

*closed* Long Branch Outfall Repair

*closed* Long Branch Outfall Repair

The outfall at S Kensington Street and 5th Road South leads to a small stream in the Upper Long Branch watershed, near Long Branch Nature Center. The outfall has been identified as a high priority for a repair project due to severe active erosion and the broken and damaged stormwater pipes. If left unchecked, an eroding 8 foot drop in the stream channel (or headcut) will continue to erode and advance upstream. 

The project approach will aim to:

  • Create a stable outfall at the connection from the storm system to the stream,
  • Repair broken storm infrastructure and improve capacity, 
  • Repair and stabilize stream erosion, particularly at the 8-foot drop in the stream channel,
  • Remove invasive plants and plant native trees, shrubs and plants,
  • Protect habitat value of water resources for salamanders and other wildlife,
  • Redesign and recreate the connection from Moses Ball Spring to the stream,
  • Minimize impacts to the stream corridor and limit tree impacts,
  • Keep a natural look and feel in the stream work.

In order to identify and minimize impacts, the project team has:

  • Conducted a detail tree inventory of condition, species, size, and location to inform the design process,
  • Walked the site with DPR Natural Resources and Nature Center staff to collaborate and hear key insights,
  • Met onsite with community leaders early (pre-design) in the process to identify existing problems, key priorities, and shared goals,
  • Narrowed the scope after identifying high-quality habitat value trees that are stable and in good condition,
  • Concentrated disturbance in areas with pervasive invasive plants,
  • Worked with the existing grade in the stream to limit earthwork and root disturbance.

The team will also conduct native plant/wildlife rescue in fall 2025, focusing efforts on salamanders living in this section of the creek. Salamanders will be moved downstream of the project area. 

In fall 2025, the project team is asking community members for feedback on the project and on options regarding the fence on the site. See below for more details.

The project is planned to go to construction in early 2026.  View the Long Branch outfall repair project webpage.

 

Fall 2025 Feedback Form

See below for key updates, feedback questions and concept designs for the Long Branch Outfall Repair. 

Key Updates

During the design process, the project team has considered locating the construction access from either 5th Road S or through Carlin Springs Road. There are several considerations that make 5th Road South a preferable option:

  • The replacement of the storm drain pipe will extend out to the manhole adjacent to the sidewalk on 5th Rd S. (In a previous design iteration, the replacement extended only to the storm drain structure, but additional pipe replacement was needed to improve stormwater capacity.)
  • There are high levels of invasive plants at the 5th Road S location that could be removed and remediated through the project. 
  • The access through 5th Road South limits any potential impacts to the Moses Ball Spring. 
  • There are several large mature trees near Moses Ball Spring that would likely be impacted if access was through that area.
  • This option also avoids potential conflicts with construction at the Carlin Springs Road site. 

Minimizing Impacts to Neighbors: Fence, Safety and Parking

  • We have heard specific feedback about minimizing impacts to neighbors on and near 5th Rd S. This includes questions on the fence, keeping neighborhood kids safe during construction, and parking on 5th Rd S.
  • Fence and Safety: Sections of the existing wooden fence near 5th Rd S & S Kensington will be removed temporarily to access stormwater pipes. During construction, 6-foot chain link perimeter fencing will prevent access and ensure safe conditions.​ At the close of the project, the contractor will rebuild these fence sections. Is the community interested in any modifications to the fence design? Please provide your input below. 
  • Parking: The staging areas are sized so large equipment can be kept inside the construction area overnight. For contractor personal vehicles, County staff will work with the community and the contractor to identify parking locations that minimize inconveniences.  

Landscaping at the 5th Rd S & S Kensington street end

  • Currently, the area is covered with invasive plants and vines, including English Ivy and Porcelainberry. 
  • Community members have expressed an interest in removing invasive plants and changing the current plant cover. Please provide any input below. 

How do you use the area near 5th Rd S & S Kensington St? What do you value about that area now?

Closed for Comments

How would you like to see the area near 5th Rd S & S Kensington St change? (Please note that there are specific questions about the fence location and landscaping below.)

Closed for Comments

How do you use the area near Moses Ball Spring? What do you value about that area now?

Closed for Comments

How would you like to see the area near Moses Ball Spring change?

Closed for Comments

Please see the following draft design views, including potential fence relocation. 

Long Branch outfall - aerial

Long Branch outfall

Fence Feedback

During construction, portions of the fence will need to be removed to access the outfall and stream. Temporary chain link fencing will keep the area secure during construction.

Questions for community members on the replacement fence

1. Would you prefer adjusting the fence location to improve safety?

Background: Currently the fence follows the steep slope down to just above the outfall. After the project is completed, the area will be more open, and the steep slope and yard inlet may pose a safety risk for kids and other area residents. At the August 11, 2025 streetside meeting, community members expressed interest in realigning the fence to exclude the yard inlet and steep slope from the 5th Rd S side. ​If you have thoughts about the fence location, please add them below.

2. Feedback on gate or door in fence. There was also a question posed by a community member: Would the community like to have a gate or door in the fence that could be kept locked?

At 2025 meetings, Glencarlyn community members have shown an overall strong preference against providing a gate or door. If you have thoughts on this topic, please provide them below.

Closed for Comments

Minimizing Impacts to Neighbors

We have heard specific feedback about minimizing impacts to neighbors on and near 5th Rd S. This includes questions on temporary construction fencing, keeping neighborhood kids safe during construction, and parking on 5th Rd S.

County staff understand these concerns, and will take back the feedback to the design team to work on minimizing impacts to neighbors.

Please provide any additional specific comments or concerns below so we can communicate them to the design team.

Closed for Comments

Visualization of 5th Rd S & S Kensington area

Long Branch perspective from 5th Rd S & S Kensington

Landscaping in the 5th Rd S & S Kensington Area

Currently, the area is covered with invasive plants and vines, including English Ivy and Porcelainberry. As part of the tree replacement requirements, there will be tree replanting in this section (and throughout the project area).

Please provide any additional input or thoughts you have on planting in the 5th Rd S and S Kensington street end area below.

Closed for Comments

Do you have any additional comments or feedback on the design?

Closed for Comments
Contact Information

If you would like to receive updates on this topic, please share your name and email address below: