Davis Lane Park Improvements

Davis Lane Park Improvements

Following direction from City Council and feedback we received from the community, the City is moving forward with the design and replacement of a pickleball and/or tennis court(s) in the park. As part of this process, preserving the park’s mature trees will be a priority to maintain the natural beauty and shade they provide.

As a reminder, any park improvement project will not begin construction until after the two-year warranty period for the sewer line ends, no sooner than 2027. However, project planning and design will be happening during the two-year warranty period.

In the meantime, the trail at Davis Lane Park has reopened, and site amenities, including the picnic table and bike repair station, have been reinstalled for community use. Thank you for your continued support as we work to enhance Davis Lane Park for the future!

 
Learn more about the background on this project and the impetus for the park improvements on the Davis Lane Sewer Line Replacement project page

Round 2 - CLOSED

Logo for Davis Lane Park Improvements - Round 2

Davis Lane Park Improvements - Round 2

In this round of engagement, we are asking the community to weigh various criteria and how they would apply to each potential park improvement option. Please take a few moments to fill out the survey...

Project Timeline

complete
complete

March - May 2024

Round 1: understanding values

Community meeting and survey open to the public for feedback.

complete
complete

Summer 2024

Survey feedback analysis and planning next steps.

complete
complete

September - October 2024

Round 2: understanding priorities and feasibility

Community meeting and survey open to the public for feedback.

complete
complete

Fall - Winter 2024

Survey feedback analysis and next steps.

live
live

2025 and beyond

Final decision to replace a pickleball and/or tennis court(s) at the park

Planning and design during the two-year warranty period for the sewer line