Questions or concerns? Reach out to the England Street Streetscape Project Manager, Kathleen Bison, at: kbison@ashlandva.gov or 804-752-6875, ext. 237.

UPDATE 12/08/25:

  • Work is becoming increasingly weather dependent as the temperatures drop.
  • The contractor is working toward the end of the northern side in the coming weeks.

UPDATE 10/20/25:

  • Water line work is almost finished. A final water line connection at Henry Street will be completed in the next week or two.
  • New sidewalk on Maple Street (between England Street and Robinson Street) was completed.
  • A new American with Disabilities Act (ADA) compliant ramp has been started by the post office.
  • This week, we will finish the ramp and restore the sidewalk between the ramp and the crossing at Henry Street.
  • This week, we may begin demolishing the sidewalk in front of the old St. Ann’s Church building at the northwest corner of England Street and Henry Street, if time allows.
  • We learned that Verizon had not finished its underground work, although they finished the critical phase of it.  They do expect to complete the underground work this week.  In the next week or so, Verizon will remove the overhead lines and the poles.
live
live
Phase I: 100-200 Block

Fully funded and currently under construction.

  • Step 1: Dominion Energy relocates utility lines and poles
    • Status: Completed
  • Step 2: Town contractors complete sidewalk and roadway enhancements
    • Status: Underway
    • Anticipated Completion: Winter 2025 - Spring 2026
  • Step 3: Installation of light poles and landscaping
    • Status: To be done concurrently with sidewalk roadway enhancements
    • Anticipated Completion: Soon after Step 2 

planned
planned
Phase II: 300-400 Block

Partially funded. Construction and completion timeline TBD.

planned
planned
Phase III: 500-600 Block

Unfunded. Construction and completion timeline TBD.