South Section
Koenig Lane to US 183
Under Construction- March 2026 Construction began
- Work underway Construction advances in phases
- Date to be confirmed Anticipated completion
Mobility, safety and connectivity improvements are coming to Burnet Road from Koenig Lane to MoPac Expressway. The improvements are funded by the 2016 Austin Mobility Bond.
August 3, 2026 Project Update: The Burnet Road corridor project is under construction in three active segments: White Horse Trail to US 183, US 183 to Bright Verde Way, and Bright Verde Way to MoPac Expressway. Over the coming months, crews will continue installing utilities, upgrading intersections, adding new pedestrian and bicycle facilities, and preparing the corridor for future enhancements. As construction activity increases, residents, businesses, and commuters will likely notice lane shifts, temporary detours, and intermittent closures. While teams are making every effort to minimize disruptions, some travel delays should be anticipated throughout the work.
Construction started in March 2026 on approximately 2.7 linear miles of rescoped corridor mobility improvements for Burnet Road from Koenig Lane (RM 2222) to US 183, including construction of sidewalks, shared-use paths, curb and gutter, minimal driveway reconstruction and upgraded traffic signal infrastructure and improvements at priority intersections.
Construction is underway on safety and mobility improvements, including:
Construction began in June 2026 on approximately 1.5 linear miles of corridor mobility improvements for Burnet Road from Bright Verde Way to MoPac Expressway, including:
August 3, 2026 Project Update
Construction is underway in three sections of Burnet Road:
Crews are installing utilities, upgrading intersections and adding walking and biking facilities. Work is happening in phases along the corridor.
As construction progresses, expect lane shifts, temporary detours and intermittent closures. Follow posted signs and allow extra travel time.
The City of Austin is improving Burnet Road from Koenig Lane to MoPac Expressway to make traveling along and across the corridor safer and easier for people walking, biking, driving and riding transit.
Funded by the voter-approved 2016 Austin Mobility Bond, the project includes sidewalks and shared-use paths, accessible crossings, bus stop improvements, intersection and traffic signal upgrades, roadway repairs and drainage improvements. Features vary by section.
The project is divided into three sections:
Construction is happening in phases, with a separate schedule for each section. Explore the sections below for improvements, construction progress and anticipated completion dates.
Burnet Road improvements are being built in three sections, each with its own construction schedule.
2016 — Funding approved
Austin voters approved the Mobility Bond that funds these corridor improvements.
Koenig Lane to US 183
Under ConstructionUS 183 to Bright Verde Way
Under ConstructionBright Verde Way to MoPac Expressway
Under ConstructionCentral and North completion forecasts reflect September 2026 construction notes. Anticipated dates are subject to change.
Koenig Lane to US 183
South section project limits map coming soon.
Construction began in March 2026. Work is happening in phases on walking and biking facilities and priority intersection improvements.
Expect lane shifts, temporary detours and changes to access as work moves through the section. Follow posted signs and allow extra travel time.
US 183 to Bright Verde Way
Central section project limits map coming soon.
Construction update: September 30, 2026
Crews continued drainage and water-line construction, concrete work and shared-use path preparation. Traffic signal work progressed at Longhorn Boulevard and Waterford Center Boulevard, with additional foundation work remaining at Rutland Drive.
Anticipated completion: August 2027.
Expect lane shifts, temporary detours and changes to access as work moves through the section. Follow posted signs and allow extra travel time.
Bright Verde Way to MoPac Expressway
North section project limits map coming soon.
Construction update: September 29, 2026
Construction began in June 2026. Crews continued curb and gutter construction, shared-use path preparation, storm-drain installation and traffic signal conduit work at Esperanza Crossing.
Anticipated completion: October 2028.
Expect lane shifts, temporary detours and changes to access as work moves through the section. Follow posted signs and allow extra travel time.