Mecklenburg County Park and Recreation is renovating and improving Naomi Drenan Recreation Center as well as completing improvements to Grayson Park and the existing Grayson Skatepark. Naomi Drenan Recreation Center is located at 750 Beal Street, Charlotte, NC 28211 and is an existing 13,265 square foot recreation center. The Center has a gymnasium, multipurpose rooms, and kitchen. Renovations may include improvements to the building systems (HVAC, Electrical, Security, etc.), main entry lobby, restrooms/lockers, new multi-purpose room and offices.    
Outside you can also find the Grayson Skatepark, basketball court, tennis courts, playground, and baseball/multipurpose field. Grayson Skatepark is one of two current skatepark facilities within the Mecklenburg County park system. 

See below for the current proposed skatepark improvement plans for Grayson Skatepark. Substantial Construction Completion punch list items for the recreation center are underway with an anticipated opening April 2026. Grayson Skatepark will open with the recreation center. 

Provide your contact information below to receive project updates.

 

Learn more about existing Park and Recreation locations and amenities: https://gis.mecklenburgcountync.gov/MecklenburgCountyParkExplorer/

 

What do you like about the concept design?

How could the concept design be improved?

Any additional comments or questions on the skatepark design?

Existing Naomi Drenan Recreation Center:

Proposed Grayson Skatepark Improvements:

Our goal was to give the Grayson Skatepark a much needed facelift. The design focuses on the entry way into the park by reprogramming the unused space that currently exists. This includes a skateable archway and a series of bank ramps, which are both functional and aesthetically pleasing. In addition, we propose enhancements to the lower section that includes modern street elements and new flatwork. 

 

Project Timeline

complete
complete

Schematic Design/Design Developmentent

Spring 2023-Summer 2023

complete
complete

Construction Documents

Summer 2023-Fall 2023

complete
complete

Permitting/Bidding

January 2024-March 2024

complete
complete

Construction

2024

Do you have any comments or questions about the project?

Contact Information

(required) Would you like to provide your contact information for future project updates?

Project Schedule: 

Additional questions? Contact:

James Williams, Planner

James.Williams@MecklenburgCountyNC.gov or 704-534-8258