Oakley Place (Lyon to Crescent)

Construction is expected to start early March depending on the weather.

This is a reconstruction project. Contractors will replace the road and upgrade what is listed below:

  • Driveway approaches and sidewalks

  • Water

  • Parkways and street trees

  • Storm sewer 

Check out our Road Construction Guide to learn more.

Have a question?

Contact Us 

communityengagement@grcity.us

311 or 616-456-3000

Timeline

planned
planned
Thursday, February 26: Construction Preparation Meeting

At this meeting we will share the work to be completed, project schedule, and access during construction. Register for the meeting here.

 

planned
planned
Early March 2026 Construction Begins

We recommend parking on Crescent or Lyon overnight to avoid early morning conflicts with the construction working.

 

planned
planned
May 2026: Construction ends

Construction is expected to end in May 2026.