FORTAG California Avenue Segment
FORTAG California Avenue Segment
FORTAG California Avenue
This phase of the Fort Ord Regional Trail & Greenway stretches 1.4 miles from Patton Parkway in the City of Marina to 8th Avenue, adjacent to California Avenue. From 8th Avenue, the trail heads north through former Fort Ord open space and crosses Imjin Road via at an-grade crossing to connect to the new roundabout at the Imjin Parkway and Imjin Road intersection as part of the Imjin Parkway Widening and Roundabout Project. This phase was awarded $8.4M in funding from the State Active Transportation Program Cycle 5 and utilizes $2.2M of Measure X funds for a total project cost of $10.6M. The project is at 60% design with a target to begin construction in Fall 2025.