CONSTRUCTION UPDATE:

2/2024:  Reedy Creek Greenway construction started in February 2024 and is projected to be completed by Summer 2025.

December 9th, 2021 Public Meeting:

Reedy Creek Greenway:  Rocky River Road to Plaza Road Extension

Reedy Creek Greenway alignment map

Question title

From where will you likely access Reedy Creek Greenway?

Click to view results

Question title

How will you primarily get to Reedy Creek Greenway?

Question title

How many times have you visited Reedy Creek Park & Nature Preserve in the past 6 months?

Click to view results

Question title

What are your favorite Reedy Creek park and recreation amenities?

Reedy Creek Natural Surface Trails

Question title

Do you have any concerns with existing Reedy Creek Park and Nature Preserve you would like to share with Mecklenburg County Park and Recreation?

Project Schedule

complete
complete
Master Planning

complete
complete
Virtual Public Meeting

December 9, 2021 at 6pm.

complete
complete
Design

Fall 2021 - Summer 2023

complete
complete
Bidding

Summer 2023

planned
planned
Construction

February 2024 - Summer 2025

Toby Crk Gwy boadwalk

Question title

Do you have any additional comments and/or questions about this greenway project?

Greenway Master Plan:

Map of the Mecklenburg County Greenway Master Plan

Little Sugar Creek Greenway

Additional questions? 

Contact:

Joyce Figueroa, Planner

Joyce.Figueroa@MecklenburgCountyNC.gov or 980-314-1055