Project Updates: 

  • 10/2024:  Construction start October 2024.  
  • 8/2024:  The construction contract has been awarded to J.D. Goodrum Company.  
  • 7/2024:  The scope of Albemarle Road Park has been revised due to budget constraints.  Phase 1 of construction will include grading, trails, a boardwalk and site furnishings.  Phase 2 will start soon after the first phase is completed and will include a playground, fitness equipment and a small picnic shelter.  Other park amenities in the master plan, such as the community garden and the basketball court will be completed in the future pending funding availability.      
  • 3/2024:  Bidding is underway!  Notice to Bidders went out 3/14/2024 and Bid Opening is schedule for 4/16/2024.  
  • 1/2024:  Mecklenburg County has been working to finalize the design of Albemarle Road Park.  The permitting process is underway, and bidding is projected for Spring 2024.
  • 4/2023:  Mecklenburg County has been working hard to make improvements to Albemarle Road Park.  This Park Improvements Project involves the master plan, design and redevelopment of the park.  The original project budget allocated for this project was only for the Master Plan and the development of phase 1 (projected to include some trails and a community garden).  Thankfully, in an effort to improve park equity, the Board of County Commissioners allocated additional funds in FY2022 to this project allowing the project to evolved to include the development of most of the amenities in the master plan.  Over the past couple of years, the project team has completed the Master Plan, a Public Meeting, the site survey, some invasive species removal, overall park preliminary schematics and cost estimates, playground planning, design concepts studies and reviews, permitting pre-submittal meeting and the site plan.   Over the next 4-7 months, the design team will be finalizing the design and applying for the necessary permits to rebuild the park.

Albemarle Road Park:  Construction Phases

Albemarle Phase 1

Albemarle Road Park Site Plan:

Albemarle Park Site Plan upper

Albemarle Park Site Plan lower

 

 

 

The Albemarle Road Park Master Plan has been completed.  We thank you for all your comments and input.  The master plan is a vision for the future of the park that has taken into consideration an evaluation of the site and public input.

Albemarle Road Park Master Plan

 

Question title

Please provide comments and feedback about the Albemarle Road Park Master Plan.

Thank you for your participation at the virtual public meeting on Saturday, November 14, 2020.  If you missed the public meeting, you can still watch the video of the meeting via the YouTube video link below.  The PDF presentation is also available in the documents section at the bottom of this page.  We invite you to continue to provide us with your feedback and stay connected!  

postcard invite to Albemarle Park Public Meeting

Albemarle Road Park Property:

map of Albemarle Road Park and Recreation Center

Survey Questions:  

Please answer the questions below to provide us your feedback:

Question title

Do you have a memory of Albemarle Road Park and/or the surrounding community that you would like to share?

trail inside Albemarle Park

Question title

What words describe your thoughts and feelings about Albemarle Road Park today?

Image of perception words for the park

Question title

Would you be more likely to walk or drive to Albemarle Road Park?

Image of people walking to the park
Click to view results

Question title

These are some potential opportunities that may be found at Neighborhood Parks. Please select and rank the amenities you are most interested to see at the Albemarle Road Neighborhood Park.

images of amenities of neighborhood park

Question title

Would any of the following elements make you feel safer to fully use and enjoy Albemarle Road Park?

police biking with kids in a greenway
Click to view results

Question title

Many of our neighborhood parks have walk-in access only. How do you feel about removing the parking lot at Albemarle Road Park?

Entrance parking at Albemarle Park
Click to view results

Question title

What is your age and the age of family members most likely to use the park? Choose all that apply.

image of multigeneration family
Click to view results

Project Schedule

complete
complete
Master Planning

1/8/2021

complete
complete
Virtual Public Meeting

November 14, 2020 at 10AM

complete
complete
Design & Permitting

Spring 2022 - March 2024

complete
complete
Bidding

March 2024 - June 2024

planned
planned
Construction

Fall 2024 - Fall 2025

Question title

* Would you like to provide your contact information for future project updates?

Question title

Do you have any additional comments or questions about the project?

Additional questions? 

Contact:

Joyce Figueroa, Planner

Joyce.Figueroa@MecklenburgCountyNC.gov or 980-314-1055