Sanitary Sewer Rehabilitation Project (Phase 1)
Sanitary Sewer Rehabilitation Project (Phase 1)
Capital improvement Project Number: SS2201
This Sanitary Sewer Rehabilitation Project (Phase 1) will replace aging Sanitary Sewer pipes as identified in the Sanitary Sewer Master Plan. This project will upsize the sanitary sewer mains on Orleans Drive between Zoe Court and Tennent Ave.
Project Need
The Sanitary Sewer Rehabilitation Project (Phase 1) project will benefit present and future community needs. This project, once completed, will provide and maintain a level of public infrastructure facilities and services community by increasing the amount of sewer collection into our system benefitting the health and safety of our community. It is the City goal to continue to make capital improvements to the wastewater collection and treatment system to maintain system capability and reliability.
Project Goals
The Sanitary Sewer Rehabilitation Project (Phase 1) project seeks to achieve the following goals:
- Provide increased level of adequate services to the community.
- Provide dependable wastewater collection service to the community.
History, Status, Or Impact if Delayed
On October 4, 2022, City staff released an RFP for preliminary engineering design services for phase 1 of the Pinon project described in the City’s recently adopted Sanitary Sewer Master Plan. On January 18, 2023, a one‐year contract was executed with West Valley Construction Company, Inc. for the work.
Project Funding
This project is currently supported and funded by the City Sewer Enterprise Fund and Growth Impact Fees. City Sewer Enterprise Fund is collected through yearly Pinole sewer taxes, while Growth Impact Fees are colleted through building impact fees from new development within the City.
Project Budget Total: $1,500,000
Related Projects
Sanitary Sewer Rehabilitation Project (Phase 2) - TBD
Project Timeline
Design
Bidding and Award
Bid Date:
Wednesday, November 8, 2023, at 2:00 PM
Awarded to:
APB General Engineering
San Pablo, CA
In Construction
Estimated Construction Period*:
Summer 2024 - Fall 2024
*Note: Barring Weather or Other Unforseen Delays
Construction Completion
Estimated Completion:
Fall 2024
Actual Completion Date:
TBD
Contact
Nazmieh "Mia" Huebner, EIT
Public Works Specialist | City of Pinole
510-724-9835 Direct
510-724-9000 Main