Storm Damage Repair Work
Storm Damage Repair Work
Project Number: F2023-01
During the last major storm event several roads were impacted by the heavy rains. The staff have been taking an inventory of the major areas that need to be addressed to preform dig outs of various sections of streets. The work will consist of "dig-outs". A dig-out refers to the process of removing existing asphalt pavement, or sections of it, to remove and replacing the underlying base and sub-base materials. It's used when the pavement has failed in certain areas, such as when the support materials have disintegrated or lost their ability to carry a load. Proper excavation and replacement are crucial to ensuring the longevity and safety of the repaired asphalt surface.
Appian Way between Michael Drive to Allview Avenue
San Pablo Avenue between Appian Way to Oak Ridge Road (Update 9/10/2024: Area has been canceled due to budget constraints)
Project Need
Various segments of streets have been identified as needing dig out repairs. The Public Works Department has allocated funds to make repairs on Appian Way, San Pablo Avenue, and several other streets.
Project Goals
The Storm Damage Repair Work project seeks to achieve the following goals:
- Provide Adequate Transportation Facilities and Services.
- Provide adequate transportation facilities while maintaining neighborhood integrity.
- Provide timely input and effective means of programming street and highway improvements to maintain the objective peak hour level of service without detrimentally impacting community character or commercial activity.
- Provide safe, efficient roadway infrastructure to support multiple modes of transportation and to meet existing and future circulation needs.
Contact
KARL JASON "KJ" MADAYAG
PROJECT MANAGER| City of Pinole
(510) 741-2065 Direct
(510) 724-2065 Main
Bidding and Award
Bid Date:
Tuesday, June 11, 2024 at 2:00 PM
2131 Pear Street
Pinole, CA 94564
Awarded to:
A & A Paving Co. Inc.
Bay Point, CA
In Construction
Construction Period:
Summer 2024 - Summer 2024
*Note: Barring Weather or Other Unforseen Delays
Construction Completion
Estimated Completion:
Summer 2024
Actual Completion Date:
September 25, 2024