Project Steps

complete
complete
School Board to surplus the properties

Completed October 2024

complete
complete
Board of Supervisors to accept surplus properties and begin maintaining the structures and ballfields

Completed November 2024

complete
complete
Open-House Community Meetings

Completed January 21 and February 5, 2025

complete
complete
Community Development Committee

Completed March 5, 2025; feedback provided and posted; preliminary conversations only

planned
planned
Community Development Committee

May 20, 2025 (All public will be notified of this meeting through social media posts and any email address that was provided.)