Welcome to the Far East - Harrisburg SIA construction information page. This is your source for the latest information on what is being built, how it may affect your travel, and how long the work will last.
As Charlotte grows, the city is investing in safer, smoother ways to move through this corridor. Multiple projects underway will add wide sidewalks, new signalized pedestrian crossings, and intersection improvements, giving the community more ways to get around the area, regardless of their mode of transportation.
While construction is occurring, you may notice temporary changes to your usual routes, including shoulder and lane closures, and traffic shifts. Much of the work happens off the roadway, and some takes place at night to reduce daytime disruption.
We know this can be inconvenient, and we are committed to keeping you informed every step of the way. Below, you will find each work location along the corridor. Check back often, as this page is updated as the projects move forward.
Want updates sent directly to your phone or inbox? Subscribe below to receive email and text alerts about road impacts, construction schedules, and traffic changes.
Traffic Impacts
Active Now
Traffic Impact Alert for November 30
Daytime Paving Activity on Robinson Church Road between Brawley Lane and Jones Creek Lane
___________________________________________________________________________________________
Harrisburg Road: Winterwood Place to Sam Dee Road
What's being built: A shared-use path (a wide paved path for pedestrians and bicyclists).
How it affects travel: Expect lane closures and shoulder closures.
Timeline: June through December.
Harrisburg Road: Ponderosa to Colwick
What's being built: A sidewalk and shared-use path (a wide paved path for walking, biking, and rolling).
How it affects travel: This section will have night-time lane closures.
Timeline: August through December.
Questions?
Have questions about this program?
Contact Tiffany Blackwell at tiffany.blackwell@charlottenc.gov, 704-574-5365.
Completed Projects:
(Celebrated during the Nov. 23 Ribbon Cutting)
Harrisburg Road-Robinson Church Rd Intelligent Transportation System Install
Before
During
Harrisburg Road Shared Use Path
Before
After
Harrisburg Road Shared Use Path (Camp Stewart Road to Winterwood Place)
Before
After
Robinson Church Rd Sidewalk (Brawley Lane-Jones Creek Lane)
Before
After
Cambridge Commons Sidewalk Gap
Before