[ UPDATED: Friday, September 10th, 2022 ]

 

On behalf of UDOT leadership, Nielson Construction, Staker Parson Material & Construction, Sunrise Engineering, Wall Contractors and all sub-contractors involved in this work since April, we want to thank the following public/private stakeholders for their patience during construction of this project…  -  Jeffrey Putzke, Public Involvement
 
Bryce Canyon City, Tropic City, Cannonville, Henrieville, Panguitch Municipal Leadership, Businesses and Residents
Bryce Canyon Natl. Park Leadership and Staff
Garfield & Wayne County Emergency Services, Public Works, and Transportation Staff
Ruby’s Inn Management and Staff
Utah Trucking Association
 

SCHEDULE:

Approx. Completion Date:  Primary construction activity to be completed by next Friday, Sept. 17th

Work Hours:   6am – Sunset (Mon-Fri)

 

Labor Day Weekend:  In observance of the holiday, crews will be offsite with all lanes open starting today through Labor Day 

 

UPCOMING WORK:

Monday, Sept. 13th – Friday, Sept. 17th

  • Roundabout roadway messaging, delineators, directional and safety signage installations ongoing
  • Miscellaneous electrical work ongoing near roundabout
  • Bridge barrier concrete work near Henrieville

 

Image: Roundabout Lunimaires lifted into Foundations 9/9/21

 

SAFETY NOTICE:

For your safety and the safety of those working in the area, please use extra caution, reduce your speeds, and follow posted signs and signals when driving through construction zones. Traffic control devices are placed to guide motorists safely through the work zone, and to protect the project team.