This site is a self-guided tour through a series of tabs highlighting options under consideration. Opportunities are provided throughout for you to provide feedback and share your comments. This virtual Open House will be open 24 hours a day for 30 days, closing on April 14. A preferred alternative will be chosen based in part on the input received from the public. All questions and comments must be received by April 14, 2024 to be included in the environmental document and will be compiled and posted on the website. 

  

To advance between tabs, click on the green CONTINUE button located at the bottom of the page. You can also move between pages by clicking the tabs located at the top of the discussion section. If you would like to view larger versions of any of the graphics, simply click on the image.

 

Project Timeline

live
live
Begin Feasibility Study

June 2023

live
live
Gather Public Input

Public Comment Period:

March 13th to April 14th, 2024

planned
planned
Complete Feasibility Study

May 2024

planned
planned
Environmental Engineering

2025-2026*

(Pending Funding)

planned
planned
Develop Detailed Designs

2027-2028*

(Pending funding)

planned
planned
Right-of-Way Acquisition

2027-2028*

(Pending funding)

planned
planned
Utility Relocation

2027-2028*

(Pending funding)

planned
planned
Project Sale/Award

2028-2029*

(Pending Funding)

planned
planned
Construction

2029-2031*

(Pending Funding)

* Funding for these phases has not been allocated. Dates shown are tentative based on the earliest possible potential funding timeline.

 

 

PROJECT CONTACT 

Dan Corey 

Project Program Coordinator 

Warren County Transportation Improvement District 

210 West Main St., Lebanon, Ohio 45036 

(513) 431-1229