Stevens Street Reconstruction

Stevens Street Reconstruction

In 2014, Grand Rapids voters established the Vital Streets fund. This fund dedicates its focus to improving our street conditions. The Stevens Street project is funded by Vital Streets. Construction will begin in July and is expected to be complete in September 2026.

About the project

Stevens Street (Steele to Randolph)

Construction is expected to start July 6, 2026. 

This is a reconstruction project. Contractors will replace the road and upgrade what is listed below:

  • Driveway approaches and sidewalks

  • Water

  • Parkways and street trees

  • Storm sewer

Check out our Road Construction Guide to learn more.

Project Limits and Detour

 

 

Have a question?

Contact Us 

communityengagement@grcity.us

311 or 616-456-3000

Timeline

Project Timeline

planned
planned

June 25, 2026: Construction Preparation Meeting

At this meeting we will share the work to be completed, project schedule, and access during construction.

 

REGISTER HERE

 

planned
planned

July 6, 2026 Construction Begins

Construction begins

 

planned
planned

late September 2026: Construction ends

Construction is expected to end in September 2026.