South Lamar Boulevard Corridor
South Lamar Boulevard Corridor
Project Overview
The South Lamar Boulevard Corridor Project will bring mobility, safety and connectivity improvements to South Lamar Boulevard, within the broader corridor from Riverside Drive to Ben White Boulevard. Funded by the 2016 Austin Mobility Bond, the project’s construction limits extend from Barton Springs Road to U.S. 290 (Ben White Boulevard).
Planned work includes accessible shared-use paths, sidewalks, bike lanes and ramps; updated curbs and driveways; roadway resurfacing; traffic signal and bus stop improvements; and upgrades to storm drains and water and wastewater lines. Streetscape enhancements will include landscaping, tree plantings, rain gardens, irrigation, signs and pavement markings, along with intermittent medians.
Community Open House – December 2, 2026
Join us to learn more about planned improvements to the South Lamar Boulevard Corridor, explore the latest project plans and connect with the project team.
Event details
Wednesday, December 2, 2026
5–7 p.m.
Wheatsville Co-op, 4001 South Lamar Boulevard, Bluewillow Lounge
This is a drop-in event, so you can stop by anytime to ask questions, speak with project representatives and share your feedback.
South Lamar Corridor Improvements
The overall South Lamar Corridor project is approaching final design. Planned changes include:
- Traffic signal upgrades
- New signalized intersections
- New and upgraded pedestrian hybrid beacons (PHBs)
- Shared-use paths
- Raised medians
- Drainage and storm sewer improvements
- Rain gardens
- Water and wastewater upgrades
- Improved pedestrian crossings at US 290
- A northbound transit-priority lane
To help deliver improvements more efficiently, the City is dividing the corridor into two segments at Montclaire Street.
South Lamar corridor project map
Project Map Key
- Southern Segment · Montclaire Street to US 290
Bid solicitations began in July 2026. Construction is anticipated to start in early 2027.
- Northern Segment · Barton Springs Road to Montclaire Street
This segment is expected to go to bid closer to 2029, as the southern segment nears completion.
- Mary Street Roundabout · Complete
Work was completed in spring 2026. Other improvements include a new shared-use path and a new signalized intersection. See photos of the completed roundabout.
- Del Curto / Bluebonnet Roundabout · Pre-Construction
The City has selected a contractor—the same contractor currently working on the storm drain project. Construction is expected to begin in fall 2026. Other improvements include turn-lane upgrades, a shared-use path, and a new signal at Del Curto Road and Lamar Boulevard.
Stormwater Improvements
Status: Under Construction
Construction is underway on the storm drain project, which will improve drainage and support long-term roadway conditions along the corridor. This work is expected to continue through the next several years, with completion anticipated in 2027.
Treadwell Connection Update
Status: Removed from Project Scope
As part of preliminary engineering, the City requested approval from Union Pacific Railroad to connect Treadwell Street to South Lamar via either an overpass or underpass. Union Pacific denied both requests, so this connection has been removed from the current project scope.
While it is not included in the corridor program due to feasibility and funding constraints, it could be considered in the future if prioritized through local mobility programs.
Project Documentation
- South Lamar Boulevard Final Report
- Appendix A - Public Involvement Plan
- Appendix B - Drainage
- Appendix C - Travel Demand
- Appendix D - Traffic Analysis
- Appendix E - Health Assessment Impact Study
- Appendix F - Relevant Plans and Policies
- Appendix G - Walk Audit and Workshop Workbook
- Appendix H - Cost Estimates
- Appendix I - Recommendations
Contact
For questions about the project, please email Corridors@AustinTexas.gov, call (512) 974-2300, or sign up below for project updates.
Project Timeline
- April 2016 Preliminary Engineering Report Complete
- July 2020 NEPA Virtual Public Hearing
Riverside Drive to Barton Springs Road
Complete - August 2020 30% Design Complete
- December 2020 60% Design Complete
- March 2021 90% Design Complete
- May 2026 Final Design Complete
- September 2026 Southern Segment Bid Solicitation
Montclaire Street to U.S. 290 · Solicitation closed September 24, 2026
Complete - Anticipated early 2027 Southern Segment Construction
Montclaire Street to U.S. 290
Upcoming - Closer to 2029 Northern Segment Bid Solicitation
Barton Springs Road to Montclaire Street · Expected as the southern segment nears completion
Upcoming - To be determined Northern Segment Construction
Barton Springs Road to Montclaire Street
Upcoming