Tell us what you think about the proposed reconstruction on the U.S. 52 Causeway north of Sabula in Jackson County.
Share your feedback through March 23, 2026.
Attend open house to share your feedback
When: Tuesday March 10, 2026, anytime between 5 and 6:30 pm
Location: City of Sabula, 411 Broad Street, Sabula, IA 52070
Schedule
| Phase | Date |
|---|---|
| Construction Start | Target is Spring 2027 |
| Construction End | Target is Summer 2028 |
Location of the Project
Project Information
Changes include:
- Reconstruct the pavement
- Widen shoulders
- Embankment improvements
Traffic will be maintained using one lane of traffic during the majority of the project. During the paving stage of construction, the causeway will be closed approximately three months. Traffic will then be directed to use the IL-67, IL-136, and IL-84 detour.