2017-2022 Bond Project: South Alamo Street (Market Street to East Cesar E. Chavez Blvd.)
2017-2022 Bond Project: South Alamo Street (Market Street to East Cesar E. Chavez Blvd.)
This Bond Project will reconstruct Alamo St. from Market to Cesar E. Chavez. Includes pedestrian amenities and enhancements as appropriate and within available funding.
Project Type: Streets
Phase: Construction
Project Contact: Joey Doctor, (210) 207-8415
Estimated Construction Timeline: Fall 2022 - Summer 2025
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)
Project Budget: |
| |
2017 General Obligation Bond (Street) | $20,561,541.00 | |
2022 CO TIRZ #34 Hemisfair $8,000,000.00 | ||
AT&T Contribution | $1,500,556.00 | |
CPS Energy | $1,668,760.15 | |
San Antonio Water System | $16,029,110.35 | |
Tree Preservation Fund | $750,000.00 | |
Total | $48,509,967.50 |
Project Limits:
Know Before You Go Downtown! Plan ahead for traffic, detours and parking at this link: https://saspeakup.com/downtown
SUPPORT YOUR LOCAL SMALL BUSINESSES: https://www.sanantonio.gov/EDD/Programs-Grants/Paving-The-Way
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Business Outreach Specialist: Gabby Tello, 210-207-4688
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.
Project Update 11/21/24:
South Alamo and East Nueva Street - Intersection Closure
The east half of the E. Nueva Street and S. Alamo intersection will be closed for construction of drainage improvements. The closure will begin on December 9, 2024 and is anticipated to be complete by mid-February 2025 (Updates will be provided as necessary). There will be access to Magik Theatre and the Hemisfair Park from Hemisfair Blvd and E. Nueva Street. This closure will not impact the western half of the intersection, and there will continue to be two open lanes on Nueva heading west to S. Presa. The closure will have an impact in the area, but detour and alternate routes will allow for access to businesses in the area. All construction areas will be marked by barricades and road closure signs. Detours around the road closure will be clearly marked and posted and be in effect for the duration of the closure. All work is weather permitting. We apologize for any inconvenience. Please see the map and detour route provided for more information. We appreciate your patience.
Project Update:
Market Street Southern Lane Closure – Gas Installation
UPDATE: Through the end of September 2024, Market St. will be reduced to 1 lane at the S. Alamo intersection. After that, it will return to a two-lane configuration through November 2024.
The two southern lanes on Market St. at the S. Alamo St. intersection will be closed starting as early as Monday, August 12, 2024, and will remain closed for approximately 3-4 months. Two lanes will stay open traveling eastbound on Market. The gas installation work within this closure will be completed in 2 phases. Please see the maps and descriptions provided.
- Phase 1 (approx. 3 weeks) – Workzone in SW corner of Market/Alamo. Pedestrian access closed on west north-south crossing.
- Phase 2 (approx. 2-3 months) - Workzone in SE corner of Market/Alamo. The one-way southbound lane along S. Alamo will shift west. Pedestrian access closed on east north-south crossing.
Phase 1 Gas Installation – SW corner of Market/Alamo
Phase 2 Gas Installation - SE corner of Market/Alamo
Current and planned work:
- Continue excavation and installation of chilled water on S. Alamo between Nueva and Market St.
- CPS Gas installation on the east side of South Alamo, to be preceded by storm drain installation and followed by SAWS water main and sanitary sewer installation.
- South Alamo & Market SE Intersection: This area is being converted for permanent pedestrian and traffic signal improvements, which closes one small traffic lane.
- South Alamo & Cesar Chavez NE Intersection: Drill shaft planned for traffic signal mast arm.
- Arciniega Street continues to be closed for underground utility work.
- Scheduled completion Summer 2025.
Nueva Street & South Alamo - Crosswalk Closure
- The contractor will close the Nueva Street north-south crosswalk on the west side of South Alamo Street from Thursday 8.1.24 until Monday 8.5.24. This closure is necessary to rehabilitate the sanitary sewer along the South Alamo corridor. The contractor will be detouring pedestrians west to the nearest crosswalk at Presa & Nueva intersection. All work is weather permitting. Please see the map provided.
Nueva & South Alamo Intersection
- The Nueva intersection is now open to two-way traffic
South Alamo One-Way Southbound Traffic
- South Alamo has been converted to one single southbound traffic lane from March 18, 2024 thru end of project.
- Pedestrian access on S. Alamo east side from Market to Cesar Chavez, and South Alamo west side from Nueva to La Villita St.
- 4-way Stop at Nueva intersection has been implemented.
- Business access provided.
South Alamo One-Way Southbound Traffic Map
Businesses remain open and accessible!
BUY LOCAL!
Project Presentation Documents