PROJECT UPDATES

 

Construction Activities May 8 - May 16

Ongoing Activities 

State Street to 700 West

A contractor for Dominion Energy will be working in this area through June. Please be aware of shifting work zones, lane closures, and night work. 

700 West to 900 West

Work continues on the outside lanes for the new bridge over the Jordan River with the concrete for the new bridge walls being poured this week into next. 

Work on the storm drain service lines may require short-term driveway access interruptions. 

Patrons to the River Oaks Driving Range may only enter and leave eastbound on 9000 South. See the detour map below.

River Oaks Golf Course Driving Range Detour Map

900 West to 1300 West

As early as Thursday, May 9, West Jordan City will conduct fire hydrant and water line relocation work between 7:00 p.m. and 11:00 p.m. near 1075 West requiring water service interruptions affecting a few properties. These properties have been notified of the upcoming work. Motorists can expect lane closures on 9000 South in this area during this work. 

Water meter relocations continue on the south side of 9000 South requiring short-term water service interruption. Crews will notify individual property owners prior to any work taking place as these connections take approximately 30 minutes. 

As early as Monday, May 20, work on storm drain and water service line installation will require the closure of the south leg of 1075 West. This closure will last up to one week and residents should use the detour shown. 

1075 West closure detour map

Work on block walls on the south side of 9000 South continues in this section. 

Work on the storm drain and water service lines may require short-term driveway access interruptions. Alternate business accesses are open and posted.

 

1300 West to Redwood Road

As early as Monday, May 13, crews will close the south leg of 1510 West at 9000 South for up to two weeks. Additionally, overnight lane closures on 9000 South are planned as part of this work. 

Overnight water service interruptions are anticipated overnight Tuesday, May 14 from 11:00 p.m. through 5:00 a.m. Wednesday morning May 15 as crews relocate existing water service lines. Affected property owners will be notified of upcoming impacts. 

Residents and businesses south of 9000 South should use the detour shown below. 

1510 West closure detour map

Work on the storm drain and water service lines may require short-term driveway access interruptions. Alternate business accesses are open and posted.

*Schedule is subject to change due to weather, equipment, or material delays.

 

Bridge Girder Placement

See the time lapse video of the crews placing the girders on 9000 South over the Jordan River. 

Bridge Deck Concrete Pour

See the time lapse video of crews pouring concrete for the southern deck of the bridge over the Jordan River. 

 

Infographic as of February 29, 2024. 

9000 South work completed to date infographic

 

Closures

Eastbound 9000 South left turn closed at 700 West

The left turning lane to 700 West from eastbound 9000 South will be closed. This closure is expected to last through Summer 2024. Traffic should use Sandy Parkway (450 West) as the detour route. Click here to see the recommended detour map.

This closure is necessary to ensure safety as there is insufficient room to install a left-turning lane.

 

Transit and Traffic Information

UTA LogoUTA Bus Route F590 - Due to construction activities, the bus stops within work areas may have temporary closures and stop adjustments. Visit UTA's website for specific stop information

 

Know before you go! Check UDOT Traffic before hitting the road. 

Question title

Receive Project Updates

If you would like to receive project updates, please enter your information below:

By entering your information, you will be signed up to receive project updates as they are released.

Contact Information

Hotline: 855-925-2801 Project #5626
Email: widen9000south@utah.gov

Schedule

complete
complete
Project Design:

complete
complete
Environmental Evaluation: Spring 2019 to Summer 2020

complete
complete
Right of Way Acquisition: 2020 to 2021

complete
complete
Advertise: January 2023 to March 2023

Receive bids from potential contractors

Dry Creek was selected as the contractor for the project. 

complete
complete
9000 S Open House Meet the Contractor

June 28, 2023

5:30 PM - 7:30 PM

Riveside Elementary School

8737 South 1220 West, West Jordan

live
live
Start Construction: July 5, 2023

Work Hours: 7 a.m. - 5:30 p.m.

Workdays: Monday - Friday 

Schedules are subject to change due to weather conditions and material availability. 

There will be some night work and weekend work as part of this project. 

planned
planned
End Construction: July 1, 2025

 

Contact Information

To contact the Public information team with questions or concerns:

Hotline: 855-925-2801 Project #5626
Email: widen9000south@utah.gov

 

Stay Informed

To receive weekly construction updates, please contact the public information team at the email address above and enter "Weekly Updates" in the subject line

Area Projects

To learn more about the 1300 West widening project by West Jordan City, click here

To learn more about the Redwood Road Renewed (9000 South - 6600 South) project by UDOT, click here.

To learn more about the Dominion Energy Gas Feeder Line 34 (1300 West from 7800 South to 11400 South), click here.