Happening Now

Construction began in early November in the Beacon Village Neighborhood in Swannanoa and on Joyner Avenue in West Asheville. Both areas will be under construction simultaneously.  

 

Background

This project was identified as a critical need due to the amount of leaks and breaks in the two communities. 

Repairs and upgrades will involve the installation of approximately 11,200 feet of waterline in Beacon Village and 3,000 feet on Joyner Avenue. These lines are replacing existing infrastructure.

Once the water line installation is complete, all roads disturbed by this project will be milled and repaved.

The project advertised for bids on Nov. 5, 2024. The city began evaluating bids on Dec. 5, 2024. Council approved the contract for the  project on January 14, 2025, in the amount of $10,175,349. Thomas Construction is performing the work. 

 

Timeline

Thomas Construction began work on Sevier Street & Barnard Ave at the end of April, with all water line work in those areas completed as of November 1, 2025. The project now shifts to Beacon Village and West Asheville.

 

Supporting Documents

Map of Joyner Avenue Project Area

Map of Beacon Village Project Area

 

Contact Information

Clay Chandler, Water Resources Public Information Officer

828-259-5419

cchandler@ashevillenc.gov