The East 131st Avenue Improvements will evaluate potential improvements along East 131st Avenue from Nebraska Avenue to Bruce B. Downs Boulevard. These potential improvements include pedestrian features, access management, and raised crosswalks and intersections. They will help reduce traffic congestion and improve safety for drivers, pedestrians, and bicyclists, as well as provide better accommodation for buses. 

The following improvements have been proposed along 131st Avenue.

Quick Facts (CIP # 69642000)  

  • Community Area: USF 

  • Project Type: Roadway Corridor Improvements 

  • Commissioner District: District 3 

  • Current Project Phase: Design  

 

Project Objectives: 

  • Reduce traffic congestion and improve safety for drivers, pedestrians, and bicyclists 

  • Speed management and improved safety among multiple modes of transportation, such as bike and car 

 

Estimated Project Schedule: 

  • Project Development (Planning) Completion – Late 2024   

  • Design/Land Acquisition Completion – Mid 2026  

  • Procurement Completion – Late 2026  

  • Construction Completion – Late 2027 

 

Project Cost Estimate: 

  • Total: $3,308,658

  • Planning: $1,347,283 

  • Design and Land: $380,306 

  • Construction:  $1,581,068
     

Note: The cost and schedule data shown here are the County's current best estimates and are subject to change.