U-5826: Falls Of Neuse

U-5826: Falls Of Neuse

 

Falls Of Neuse Widening 

I-540 to Durant Road

Raleigh

 

PROJECT DESCRIPTION

The N.C. Department of Transportation is proposing to Widen Falls of Neuse Road between I-540 and Durant Road in Raleigh.  The proposal would improve Falls of Neuse Road from the current five-lane undivided roadway to a six-lane median-divided roadway. The purpose of the project is to improve traffic operations along Falls of Neuse Road.  

Two alternatives were presented at the open house public meeting held in August of 2017:  

  • Alternative 1

Widen Falls of Neuse primarily on the west side of the existing roadway.

  • Alternative 2

Widen Falls of Neuse primarily on the east side of the existing roadway.

 

RECOMMENDED ALTERNATIVE SELECTED

After review of all comments received at the public meetings and throughout the comment period which concluded on September 27, 2017, a recommended alternative was selected for more detailed design work.  Alternative 2 was selected as the recommended alternative.

Alternative 2 selected as Recommended Alternative

  • minimizes the potential impacts on residential properties on the west side of Falls of Neuse including potential impacts to septic drain fields;

  • avoids major relocation of the Duke Energy power distribution line along the west side of Falls of Neuse;

  • has similar impacts to Alternative 1 with respect to business parking along the east side of Falls of Neuse; and

  • meets the congestion and safety improvement goals of the project.

 

MODIFICATION OF RECOMMENDED ALTERNATIVE

Following discussions with the City of Raleigh, additional modifications to the recommended alternative were made.  A 'best-fit' widening alternative was developed.  

A map of the Recommended Alternative is available here:  https://www.ncdot.gov/news/public-meetings/Documents/U-5826_rdy_phm_09_28_18.pdf 

 

Contact Information

Would you like to be added to our email list for future updates?

 

MilestoneAlternative 1Alternative 2Best Fit Alternative

Utilities

  $         1,500,000  

$                       0  

$                       0  

Property Acquisition

  $         3,200,000  

$          4,300,000  

$          3,116,000  

Construction Costs

  $         7,700,000  

$          7,700,000  

$          6,500,000  

Total Cost

  $       12,400,000  

$        12,000,000  

$          9,616,000  

* Estimated Costs are subject to change

 

 

Milestone       Date*

Public meeting

       August 24, 2017 

NCDOT Recommended Alternative      

       November 2017 

Right of Way Plans Complete

           January 2019 

Right-of-way Acquisition Complete

       December 2021 

Construction

                   Summer 2022 

* Future Dates are subject to change 

 
 

PUBLIC INVOLVEMENT

PUBLIC MEETING 

NCDOT conducted a public meeting to inform the public of the proposed project and to receive feedback. The meeting was held on August 24, 2017 and comments were received and reviewed following the close of the comment period on September 27, 2017.  

Information on the project was also presented at the Raleigh Area Projects Meeting held at the McKimmon Center in Raleigh on November 8, 2017.

 


PUBLIC MEETING MAPS

The Map presented at the October 16, 2018 meeting can be viewed using the link below: 

https://www.ncdot.gov/news/public-meetings/Documents/U-5826_rdy_phm_09_28_18.pdf

PROJECT CONTACT INFORMATION

John Braxton
Project Delivery - Project Manager
NCDOT Division 5
1020 Birch Ridge Drive

Raleigh, NC  27610

Email:   

FallsOfNeuse-Raleigh@publicinput.com

Title VI Feedback

To ensure we’re hearing from a broad set of voices, would you be willing to share (completely anonymously) some information about yourself?

If so, please click here: https://publicinput.com/ncdot-title-vi-form

 

RESOURCES FOR PROPERTY OWNERS 


Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.  

     
Right-of-Way Brochure Single Page Layout      Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions

Right of way Acquisition Process Videos

English                                                                     Spanish

 

Page Last Updated- May 4 2026

ADA Compliant