Project Overview

Current Status

The design team is continuing work on the final plans, specifications, and estimate. Preliminary design and the Environmental Document are complete.

Schedule

Final Design – Now through Summer 2021

Construction – Summer of 2022

For more information contact:

Chris Bentz, P.E., Project Manager, DOT&PF

(907) 269-0652

Chris.bentz@alaska.gov

Question title

What concerns do you have about temporary detours for Nash Road, Bear Lake Avenue, and Stoney Creek Avenue while the railroad crossings are replaced?

Question title

What concerns do you have about construction?