U-5780 & W-5601: N.C. 150/Wiggins & Western Intersection N.C. 150/N.C. 152
U-5780 & W-5601: N.C. 150/Wiggins & Western Intersection N.C. 150/N.C. 152
Project Overview
The N.C. Department of Transportation is proposing to realign the intersections of Wiggins Road and N.C. 150 and the western intersection of N.C. 150 and N.C. 152 in Mooresville. The proposed project is the combination of two separate projects but because of their proximity to each other they are being planned, designed, and constructed as one project.
- U-5780 proposes to realign the intersection of Wiggins Road and N.C. 150. This realignment will include left turn lanes from N.C. 150 onto Wiggins Road, a right turn lane from eastbound N.C. 150 onto Wiggins Road and signalization.
- W-5601U proposes to realign N.C. 152 to intersect N.C. 150 at a better angle. The intersection will be signalized with a left turn lane from N.C. 150 onto N.C. 152.
The purpose of this project is to increase safety and traffic capacity along this segment of N.C. 150 and N.C. 150/ N.C. 152.
Project Map
Step 1
Title VI Feedback
To ensure we’re hearing from a broad set of voices, would you be willing to share (completely anonymously) some information about yourself?
If so, please click here: https://publicinput.com/ncdot-title-vi-form
RESOURCES FOR PROPERTY OWNERS
Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road
project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right
of way acquisition and answers questions about the process.
Right-of-Way Brochure Single Page Layout Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions
Right of Way Acquisition Process Videos
Page Last Updated- May 6 2026
Project Schedule
Based on currently adopted State Transportation Improvement Program (STIP) and subject to change
April 2019 - Environmental Document Signed
June 2019 - Right of Way Plans Complete
August 2021 - Right of Way Acquisition
Summer 2023 - Final Plans Complete
December 2024 - Construction Begins