Schedule

Project Timeline

complete
complete

Draft Inventory/Forecasts - December 2020

complete
complete

Draft Environmental Overview - December 2020

complete
complete

Conditions and Needs Public Meeting - January 2021

complete
complete

Draft Facility Requirements - April 2021

complete
complete

Draft Preliminary Alternatives - July 2021

live
live

Alternatives Public Meeting - August 2021

planned
planned

Refined Alternatives - October 2021

planned
planned

Draft Airport Layout Plan - October 2021

planned
planned

Final Airport Layout Plan - November 2021

planned
planned

Draft Implementation and Master Plan - December 2021

planned
planned

Final Master Plan - February 2022

Contact Us

Email the team at 17915@PublicInput.com

Project voicemail hotline: 855-925-2801, code: 9926

 

Jennifer Keller, Project Manager, Alaska Department of Transportation & Public Facilities, Phone: 907-451-2385

RaeAnne Hebnes, PE, Project Manager, Michael Baker International, Phone: 907-273-1618

Camden Yehle, Public Involvement Lead, Yehle and Associates, Phone: 907-346-0506

Karin McGillivray, Stakeholder Support, Michael Baker International, Phone 907-273-1614