I would like to provide you with an update on the Patton Avenue Sidewalk Improvement Project.
Completed Work
Crews have removed and replaced approximately 700 feet of sidewalk and have progressed past 109 Patton Ave, where Patton Pets is located. Crews are currently working on the last stretch of the North side replacements in front of 115 Patton Ave at Salon Dragonfly.
Traffic Impacts
Please note the current traffic control measures have been adjusted and shifted further down Patton Ave. Crews are making every effort to reopen the lane periodically in the afternoons and on weekends to minimize disruption.
Upcoming Work
There is about 40 feet of sidewalk left to replace on the North side, which crews anticipate completing by the end of next week. Following that, crews will return to the ramp at 92 Patton Ave, in front of the Thirsty Monk.
Thank you for your continued patience and support as we work to improve the public infrastructure along Patton Avenue. If you have any questions or need further information, please do not hesitate to reach out.