Exterior view of entrance pavilion of Joan Means Khabele Bathhouse.

 

Joan Means Khabele Bathhouse at Barton Springs Pool Rehabilitation Project Update

October 2024

 

Please see the information below for the latest updates on progress, photos, and announcements. Construction is expected to be substantially completed in the Spring of 2025.

 

Please note that as with any construction project, schedules are projected as accurately as possible. All dates are subject to change due to the nature of construction and the weather conditions.

 

Announcements

  • The bathhouse closed for construction on June 6, 2024. As of June 21, 2024, the north entrance to Barton Springs Pool is relocated to the west end of the bathhouse, near the temporary restroom and shower trailers.
  • The south side entrance to Barton Springs Pool and parking lot at Azie Morton Drive will remain unchanged throughout the construction phase.
  • Pool tickets may be purchased online, on-site with credit cards from ticket kiosks located near the Zilker Café, or with cash directly at the Zilker Café. 
  • Entry for Early Swim (swim at your own risk) is available at the south entrance on Azie Morton Drive, from 5 to 8 a.m., and at the north entrance from 7:30 to 8 a.m.

 

Illustration of project site plan for renovation of Joan Means Khabele Bathhouse.Ilustración del plano del proyecto para la renovación del Casa de Baños Joan Means Khabele.

Current Project Phase: Construction

Completed Tasks

  • Demolition inside women's shower and dressing court complete.
  • Subgrade and rebar prep for concrete slab in Rotunda and West Exhibit area complete.
  • Concrete foundation installation inside Rotunda and West Exhibit area complete.

Work In Progress

  • Roof replacement in center area of building
  • Installation of underground plumbing inside women's shower and dressing court
  • Installation of plumbing in the south side women's restrooms
  • Subgrade and rebar prep for concrete slab in East Exhibit area
  • Masonry structural reinforcing and cleaning

Planned Work

  • Installation of electrical throughout women's shower and dressing court
  • Roof replacement over Spectator's Gallery
  • East Exhibit area concrete slab placement
  • Framing walls in exhibit area

 

Figure 1 – Subgrade and rebar prep for concrete slab for West Exhibit area.

 

Figure 2 – Subgrade and rebar prep for concrete slab in center Rotunda area.

 

Figure 3 – Concrete foundation installation inside Rotunda and West Exhibit area undergoing completion.


Figure 4 – Ongoing electrical and plumbing installation underground women's shower and dressing court.

 

Figure 5 - Bathhouse prepped for roof replacement with roofing materials wrapped and stored in front of the Rotunda.

 

Illustration map of construction project area with red highlight denoting construction impact zones and green highlights denoting public parking areas.

 

Reminder:

During the Bathhouse Rehabilitation project, Barton Springs Pool will maintain its regular schedule and remain open to swimmers. However, William Barton Drive, leading to the parking lot adjacent to the Bathhouse, will be closed to public parking and drop-offs during construction. Parking in the other lots at Zilker Park will remain open, with wayfinding signage guiding pedestrians to the north side pool entrance. Pedestrian access routes through the construction site will be adjusted as work progresses. Public ADA-accessible parking and emergency vehicle access will be available throughout the construction period. The south side pool entry gate and parking lot at Azie Morton will remain unchanged throughout this time.

 

Zilker Park Electrical Maintenance Work:

Austin Energy will begin maintenance work to update the power line running from Barton Springs Road to near the Zilker playground and train station. Phase 1 work (from October 22 to November 19) shouldn't impact operations at Zilker Park but may require reserving a few parking spaces in the parking lots near the Pecan Grove and playground.

Bathhouse Renamed:

On April 4, 2024, an Austin City Council resolution renamed the Bathhouse at Barton Springs Pool in honor of Joan Means Khabele for her contributions and activism which led to the integration of the pool. 

 

To learn more about Joan Means Khabele, please visit the Parks and Recreation Department's blogpost.

 

For more information on the renaming of the bathhouse, please visit the Barton Springs Renaming Proposal webpage.

 

Stay informed on the rehabilitation project on our project webpage.

 

Questions or concerns should be directed to:

 

Paul Mendoza, AIA, Project Manager

Capital Delivery Services

Paul.Mendoza@austintexas.gov

512-974-1272

 

Ali Petersen, RID, Project Manager

Capital Delivery Services

Alison.Petersen@austintexas.gov

512-974-7830

 

Ellen Colfax, RA, Project Manager

Parks and Recreation Department

Ellen.Colfax@austintexas.gov

512-974-9472

For more information, email CapitalDelivery@AustinTexas.gov

Visit us online at AustinTexas.gov/Bathhouse-Rehab

Building Austin Learn More
Austin is growing! Learn what's coming. Click the banner above for details on our upcoming info session.

Share this news on social media
    
Capital Delivery Services logo 300 dpi
Unsubscribe | My Subscriptions
View this email in a browser