Project Overview

Current Status

The project is progressing through the right-of-way acquisition and design stages.

  • Right-of-way is a slow process and will likely require the rest of the year to finish.
  • Design is now at 95% completion.
  • Construction is anticipated to start in 2022.

What’s Next

  • Complete design work
  • Complete utility permitting & relocation agreements
  • Complete right-of-way work
  • Construction (possibly broken into multiple projects pending funding availability)

Funding

This project is being completed using a combination of state and federal funds and is being developed in accordance with FHWA guidelines.

For more information contact:

Kelly Summers, P.E., DOT&PF Project Manager, (907) 269-0546

Alexa Greene, DOWL Project Administrator, (907) 562-2000

Question title

What concerns do you have about construction?