THIS PROJECT IS SUBSTANTIALLY COMPLETE

2022 SCHEDULE

Est. Start Date:  Monday, April 18   Hours:  7am - 7pm (with nighttime paving/painting/restriping work)

Construction Days:  Mon-Fri; Except Holidays.  Sat. only as necessary. 

Road Resurfacing: June (Road closures expected)

Est. Completion Date:  Late June

Note: Schedules are subject to change due to weather and materials available


Updated: 06/22/22

ANTICIPATED TRAFFIC IMPACTS

  • None

 

Safety Notice:

For your safety, as well as the safety of the working in the area, please use extra caution and stay alert while driving through construction zones.  Businesses and residents in the area should anticipate increased noise, dust, and vibration associated with construction.


 

UDOT PROJECT INFORMATION PAGE


LATEST TRAFFIC CONDITIONS

udottraffic.utah.gov 

or download the latest UDOT Traffic App.