The Utah Department of Transportation (UDOT) will begin road construction on US-89 (300 South) between University Avenue and 500 West in February 2024. Reconstruction is expected to continue through the end of the year. 

 

The roadway between University Avenue and 500 West will be reconstructed in a similar layout as previous projects on U.S. 89 in Provo have done. This will improve the roadway and underground infrastructure while providing better transportation options for all kinds of road users.

 

Project Activities*: 300 South

  • Crews continue to work on sewer line installation along the south side of 300 South heading west. This work requires crews to trench through driveways, and homeowners will see intermittent access limitations. Traffic has been shifted to the north and motorists are advised to slow down and pay attention to traffic control.
  • Crews have begun removing trees along 300 South that conflict with utilities. The trees to be removed were called out in design and properties will be notified before the removal.
  • Beginning next week crews will begin demolition of existing curb, gutter and sidewalk along the south side.

 

Impacts:

Homeowners can expect open trenching and intermittent access limitations during this work. One lane in each direction will be open on 300 South. Work will take place Monday through Friday from 7 a.m. to 5 p.m. unless noted.

 

 

Project Activities: Dominion Gas

Dominion Gas is finishing up their work along 300 South. This work is outside of the project and is not being directed by UDOT. Questions should be directed to Tempest Enterprises, Inc. by calling 801-262-4165 or emailing office@thetempestco.com. Dominion is anticipating finishing their work in approximately two weeks.

The Utah Department of Transportation (UDOT)has designed improvements for US-89 (300 South) in Provo between University Avenue and 500 West. The project's goals are to improve the road and underground infrastructure while providing better transportation options for all kinds of road users. The project will begin in early February.
 
The project plans to reconstruct the road between University Avenue and 500 West in a similar layout as previous projects on U.S. 89 in Provo (500 West and 300 South) have done.
 
The project team plans to improve the corridor by:
  • Replacing 300 South asphalt with concrete pavement
  • Upgrading the roadway drainage system with storm drain, curb and gutter
  • Replacing aged underground utilities including sewer and culinary water
  • Adding new pedestrian/bicycle crosswalks in several locations
  • Widening the sidewalk on both sides of 300 South
  • Reconstructing driveway approaches
  • Adding on-street bicycle lanes
  • Installing "bump-outs" on 400 West to reduce the crossing distance at intersections without painted crosswalks
  • Installing raised medians between blocks to improve safety
  • *In locations with existing buildings at the back of sidewalk, widening may be required if or when those properties are redeveloped.
 
The map below shows the project area.

 

Cross-section of 300 South

complete
complete
Design

Summer 2023

complete
complete
Project Advertisement

A contractor has been selected

live
live
Construction

February 14, 2024

FOR IMMEDIATE PUBLIC INQUIRIES

Project Hotline: 888-556-0232

Email: provo300s@utah.gov