The roadway between University Avenue and 500 West will be reconstructed in a similar layout as previous projects on U.S. 89 in Provo have done. This will improve the roadway and underground infrastructure while providing better transportation options for all kinds of road users.

 

Project Activities*:

 

300 South will be CLOSED to through traffic between Freedom Boulevard (200 West) and University Avenue from Monday, July 1 through Wednesday, July 3 at 6 a.m. while crews install new storm drain crossings underneath 300 South.

  • Through traffic should use alternate routes. (see map below). Pedestrian access will be maintained.
  • During this closure, crews will also work at night from 10 p.m. to 6 a.m. to shorten the duration of this closure. Residential access will be maintained. Residents can expect open trenching and intermittent access limitations during this work, as well as increased nighttime noise, light, and work vehicles. Impacted properties have been notified.

 

*schedule is subject to change due to weather, material availability, etc.

 

Impacts:

Homeowners can expect open trenching and intermittent access limitations during this work. One lane in each direction will be open on 300 South. Work will take place Monday through Friday from 7 a.m. to 5 p.m. unless noted.

 

 

The Utah Department of Transportation (UDOT)has designed improvements for US-89 (300 South) in Provo between University Avenue and 500 West. The project's goals are to improve the road and underground infrastructure while providing better transportation options for all kinds of road users. The project will begin in early February.
 
The project plans to reconstruct the road between University Avenue and 500 West in a similar layout as previous projects on U.S. 89 in Provo (500 West and 300 South) have done.
 
The project team plans to improve the corridor by:
  • Replacing 300 South asphalt with concrete pavement
  • Upgrading the roadway drainage system with storm drain, curb and gutter
  • Replacing aged underground utilities including sewer and culinary water
  • Adding new pedestrian/bicycle crosswalks in several locations
  • Widening the sidewalk on both sides of 300 South
  • Reconstructing driveway approaches
  • Adding on-street bicycle lanes
  • Installing "bump-outs" on 400 West to reduce the crossing distance at intersections without painted crosswalks
  • Installing raised medians between blocks to improve safety
  • *In locations with existing buildings at the back of sidewalk, widening may be required if or when those properties are redeveloped.
 
The map below shows the project area.

 

Cross-section of 300 South

complete
complete
Design

Summer 2023

complete
complete
Project Advertisement

A contractor has been selected

live
live
Construction

February 14, 2024