Project Overview

Runway 7-25 is a 5000 foot long x 132 foot wide paved runway with 12 foot wide paved shoulders. This project will repave the runway to 130 feet wide with 12 foot paved shoulders. At the east end of the runway, where the grade is proposed to be lowered, the lateral safety areas (150 feet each side of centerline) will also require grade adjustment. The three taxiways, each 50 feet wide with 12 foot paved shoulders, will each have approximately 250 linear feet repaved. Work required for the temporary runway will consist of modifications to the surface markings, existing edge lighting and existing sign legends.

The project is expected to start in May 2021 and last approximately six months.

Existing conditions.

Work areas shown below. For a larger version, see the Document section on this page.

Project Team

Owner: City of Soldotna

Kyle Kornelis, P.E., Public Works Director, Airport Manager

907-262-9107, kkornelis@soldotna.org

 

Design/Project Management: Wince-Corthell-Bryson

Mark Blanning, P.E., 907-283-4672, mblanning@wcbalaska.com

 

Contractor: Knik Construction

Pete Hoogenboom, 907-262-9140, peteh@lynden.com

Frequently Asked Questions

No, lease lots and tie downs are not expected to be affected.

Aircraft movement areas will reconfigure during construction. Some larger aircraft that require the full 5,000 foot runway may have to use an alternate airport.

No. The gravel runway will remain open, and the parallel taxiway will become the temporary paved runway.

Question title

What concerns do you have about construction?