Schedule

Phase 1, reconstructing Old Seward from Alaska Cycle Center to Tudor Road, has been bid and construction will occur in early summer of 2021.

Phase 2, reconstructing the storm drain between Phase 1 and Campbell Creek, is dependent on funding but is anticipated in 2022.

Examples of some of the problems this project will solve: ponding.

 

This is a photo taken inside the old storm drain that needs to be replaced:

Examples of some of the problems this project will solve: rutted, failing pavement; cracked sidewalks; poor drainage.