W-5706X - U.S. 74 and Peacock Rd. - Chadbourn
W-5706X - U.S. 74 and Peacock Rd. - Chadbourn
Update: Proposed roundabout at Columbus Co. intersection will not move forward
PROPSED ROUNDABOUT AT U.S. 74 / 76 BUSINESS / N.C. 130 AND PEACOCK ROAD.
Vicinity Map:
Project Overview
The N.C. Department of Transportation proposes to construct a roundabout at the intersection of U.S. 74 / U.S. 76 Business / N.C. 130 and Peacock Road.
Project Highlights
NCDOT proposes to improve safety at the intersection. Crash data showed a total of 16 crashes, including one fatal crash, within a five-year timeframe (2014-2018).
Public Involvement
Public Meetings
Information will be provided to the public in a virtual format on this website. The public is encouraged to provide comments or share their thoughts regarding the proposal.
Public Meeting Map:
Proposed preliminary design map of Roundabout at U.S. 74 / 76 Business / N.C. 130 at Peascock Road.
A video explaining how to read a public hearing or meeting map can be viewed below. The video contains information on colors used and symbology.
Roundabouts in North Carolina
Project Funding:
This project is listed as Project W-5706X and is funded for $ 1.6 million. Cost estimates have been prepared and are shown below.
Activity | Estimated Costs* |
Project Development & Design | $ 350,000 |
Property Acquisition & Utilities | $ 300,000 |
Construction Cost | $ 975,000 |
Total Cost | $ 1,625,000 |
*Estimated costs are subject to change. Based on currently adopted NCDOT STIP.
Project Timeline:
Milestone | Date* |
Public Outreach | Oct. 2021 |
Final Environmental Document | Oct. 2021 |
Right-of-Way Acquisition Begins | Dec. 2021 |
Construction Begins | Dec. 2022 |
* Future dates subject to change.
PROJECT CONTACT INFORMATION
Alex Henderson
Division Project Engineer
NCDOT Highway Division 6
PO Box 1150
Fayetteville, NC 28302
PROJECT CONTACT INFORMATION
Steve Smallwood
Consultant Project Manager
Stantec
801 Jones Franklin Road Suite 300
Raleigh, NC 27606-3394
RESOURCES FOR PROPERTY OWNERS
Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.
Right-of-Way Brochure Single Page Layout Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions
Right of way Acquisition Process Videos