W-5706L - N.C. 27 / Old Stage Rd / Leslie Campbell Road and N.C. 27 at Sheriff Johnson Road
W-5706L - N.C. 27 / Old Stage Rd / Leslie Campbell Road and N.C. 27 at Sheriff Johnson Road
The North Carolina Department of Transportation proposes to construct a roundabout at the intersection of N.C. 27 / Old Stage Rd / Leslie Campbell Ave. and dead end Sheriff Johnson Rd at N.C. 27.
Vicinity Map:
Interactive Study Area Map:
Map is for informational purposes only and reflects the approximate boundaries of the area in which environmental studies for the project will be conducted.
Step 1
Project Overview
The N.C. Department of Transportation proposes to construct a roundabout at the N.C. 27 / Old Stage Rd (S.R. 1006) / Leslie Campbell Ave (S.R. 2084) intersection. Pavement removal is proposed at the NC 27 / Sheriff Johnson Rd (SR 1516) intersection.
Public Involvement
Information will be provided to the public in a virtual format on this website. The public is encouraged to provide comments or share their thoughts regarding the proposed map below.
Comments may be submitted below, via email to OldStageRd-Harnett@PublicInput.com or by calling 512-580-8850 and entering project code 8739.
The comment period for this project closes on October 24, 2022.
Public Meeting Map:
Click on this link or the map map below to view the project map Updated public meeting map Roundabout at Old Stage Rd / Leslie Campbell Ave intersection.
A video explaining how to read a public hearing or meeting map can be viewed below. The video contains information on colors used and symbology.
Roundabouts in North Carolina
Project Funding:
This project is listed as Project W-5706L in the N.C. Department of Transportation’s State Transportation Improvement Program (STIP) and is funded for $ 5.175 million.
Activity | Estimated Costs* |
Project Development & Design | $ 900,000 |
Property Acquisition & Utilities | $ 1,775,000 |
Construction Cost | $ 3,150,000 |
| Total Cost | $ 5,825,000 |
Estimated costs are subject to change. Based on currently adopted NCDOT STIP.
Project Timeline:
Milestone | Date* |
Public Outreach | September 2022 |
Final Environmental Consultation | January 2023 |
Right-of-Way Acquisition Begins | September 2022 |
Construction Begins | April 2024 |
* Future dates subject to change.
PROJECT CONTACT INFORMATION
Alex Henderson
Division Project Engineer
NCDOT Highway Division 6
PO Box 1150
Fayetteville, NC 28302
PROJECT CONTACT INFORMATION
Michael Wray
Consultant Project Manager
Stantec
801 Jones Franklin Road Suite 300
Raleigh, NC 27606-3394
Title VI Feedback
To ensure we’re hearing from a broad set of voices, would you be willing to share (completely anonymously) some information about yourself?
If so, please click here https://publicinput.com/NCDOT-Title-VI
RESOURCES FOR PROPERTY OWNERS
Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.
Right-of-Way Brochure Single Page Layout Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions
Right of way Acquisition Process Videos