W-5706L - N.C. 27 / Old Stage Rd / Leslie Campbell Road and N.C. 27 at Sheriff Johnson Road
W-5706L - N.C. 27 / Old Stage Rd / Leslie Campbell Road and N.C. 27 at Sheriff Johnson Road
The North Carolina Department of Transportation proposes to construct a roundabout at the intersection of N.C. 27 / Old Stage Rd / Leslie Campbell Ave. and dead end Sheriff Johnson Rd at N.C. 27.
Vicinity Map:
Interactive Study Area Map:
Map is for informational purposes only and reflects the approximate boundaries of the area in which environmental studies for the project will be conducted.
Project Overview
The N.C. Department of Transportation proposes to construct a roundabout at the N.C. 27 / Old Stage Rd (S.R. 1006) / Leslie Campbell Ave (S.R. 2084) intersection. Pavement removal is proposed at the NC 27 / Sheriff Johnson Rd (SR 1516) intersection.
Public Involvement
Information will be provided to the public in a virtual format on this website. The public is encouraged to provide comments or share their thoughts regarding the proposed map below.
Comments may be submitted below, via email to OldStageRd-Harnett@PublicInput.com or by calling 512-580-8850 and entering project code 8739.
The comment period for this project closes on October 24, 2022.
Public Meeting Map:
Click on this link or the map map below to view the project map Updated public meeting map Roundabout at Old Stage Rd / Leslie Campbell Ave intersection.
A video explaining how to read a public hearing or meeting map can be viewed below. The video contains information on colors used and symbology.
Roundabouts in North Carolina
Project Funding:
This project is listed as Project W-5706L in the N.C. Department of Transportation’s State Transportation Improvement Program (STIP) and is funded for $ 5.175 million.
Activity | Estimated Costs* |
Project Development & Design | $ 900,000 |
Property Acquisition & Utilities | $ 1,775,000 |
Construction Cost | $ 3,150,000 |
Total Cost | $ 5,825,000 |
Estimated costs are subject to change. Based on currently adopted NCDOT STIP.
Project Timeline:
Milestone | Date* |
Public Outreach | September 2022 |
Final Environmental Consultation | January 2023 |
Right-of-Way Acquisition Begins | September 2022 |
Construction Begins | April 2024 |
* Future dates subject to change.
PROJECT CONTACT INFORMATION
Alex Henderson
Division Project Engineer
NCDOT Highway Division 6
PO Box 1150
Fayetteville, NC 28302
PROJECT CONTACT INFORMATION
Michael Wray
Consultant Project Manager
Stantec
801 Jones Franklin Road Suite 300
Raleigh, NC 27606-3394
RESOURCES FOR PROPERTY OWNERS
Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.
Right-of-Way Brochure Single Page Layout Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions
Right of way Acquisition Process Videos
Title VI Feedback
To ensure we’re hearing from a broad set of voices, would you be willing to share (completely anonymously) some information about yourself?
If so, please click here https://publicinput.com/NCDOT-Title-VI