Status and Schedule

The project is just getting started! Crews have been out in the field collecting data and the traffic analysis of the ramps has begun. By fall of 2021 the Design Study Report (DSR) will be completed and we will know the extent of the improvements and then development of detailed plans can begin. The project may be broken into phases to match available funding with the first phase anticipated to be to construction in 2024. 

Question title

What would you like us to know about this corridor as we move forward with the project?

Question title

* Sign up to receive emails about the project status:

Contact Information:

Joann Mitchell, PE
Public Involvement Coordinator
Kinney Engineering

JoannMitchell@KinneyEng.com
(907) 344-7590

OR:

Chris Bentz, PE
DOT&PF Project Manager

Chris.bentz@alaska.gov
(907) 269-0652