Installation of a Roundabout at Madison (U.S. 701 Business), Lee and Franklin Street in Columbus County.
Interactive Study Area Map:
Project Overview
The N.C. Department of Transportation proposes to construct a roundabout at the intersection of Franklin St., Lee St., and Madison St. (U.S. 701 Business) in Whiteville. Roundabouts improve safety and traffic flow. NCDOT was awarded a federal grant through the Carbon Reduction Program to help fund this project, which will eliminate the traffic signal at this location and result in less idling and reduced carbon emissions.
Project Highlights
The roundabout will consist of:
- one 18-foot circulatory travel lane
- a 14-foot concrete apron to accommodate tractor-trailers, buses and other large vehicles
- 12-foot approach lanes with concrete traffic islands
- a grass median in the center
Project History
In January of 2021 the city of Whiteville adopted a Downtown Development Plan which recommended a roundabout at this location. In 2023 this project was approved and funded under the Carbon Reduction Program. Right of Way acquisition is scheduled to begin in the winter of 2025 and Construction will begin in winter of 2026.
Aerial View of Proposed Design
For information on how to navigate roundabouts, see video below.
Typical Drawings
North and Southbound approach from U.S. 701 (Madison St.)
Roundabout at U.S. 701 (Madison St.), Lee St., and S. Franklin St.
Project Funding:
Activity | Cost* |
Right-of-Way Acquisition | $ 100,000 |
Construction | $ 3.0 Million |
Total | $ 3.1 Million |
Project Timeline:
Milestone | Date |
Right-of-Way Acquisition Begins | February 2025 |
Construction Begins | February 2026 |
Project Comments:
NCDOT accepts comments throughout all phases of project development.
All comments will be taken into consideration, and carry equal weight, regardless of submittal method.
Comments for consideration during the current phase of project development
were to be submitted before November 16, 2024.
The public is encouraged to leave comments using this webpage, email, or phone number:
Email: us701roundabout-whiteville@publicinput.com
Phone Number: 984-205-6615 enter project code 7366 to leave a message.
Project Contact Information
Craig A. Freeman Jr., P.E.
Division Project Engineer
NCDOT Highway Division 6
PO Box 1150
Fayetteville, NC 28302
Title VI Feedback
To ensure we’re hearing from a broad set of voices, would you be willing to share (completely anonymously) some information about yourself?
If so, please click here: https://publicinput.com/NCDOT-Title-VI-Form
RESOURCES FOR PROPERTY OWNERS
Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road
project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right
of way acquisition and answers questions about the process.
Right-of-Way Brochure Single Page Layout Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions
Right of Way Acquisition Process Videos