Project Overview

The N.C. Department of Transportation proposes to construct a roundabout at the intersection of Franklin St., Lee St., and Madison St. (U.S. 701 Business) in Whiteville.  Roundabouts improve safety and traffic flow. NCDOT was awarded a federal grant through the Carbon Reduction Program to help fund this project, which will eliminate the traffic signal at this location and result in less idling and reduced carbon emissions.

 

 

 

Project Highlights

The roundabout will consist of: 

  • one 18-foot circulatory travel lane
  • a 14-foot concrete apron to accommodate tractor-trailers, buses and other large vehicles
  • 12-foot approach lanes with concrete traffic islands
  • a grass median in the center

 

Project History

In January of 2021 the city of Whiteville adopted a Downtown Development Plan which recommended a roundabout at this location.  In 2023 this project was approved and funded under the Carbon Reduction Program.  Right of Way acquisition is scheduled to begin in the winter of 2025 and Construction will begin in winter of 2026.  

 

Aerial View of Proposed Design          

  

           

For information on how to navigate roundabouts, see video below. 

 

Typical Drawings

North and Southbound approach from U.S. 701 (Madison St.)

Roundabout at U.S. 701 (Madison St.), Lee St., and S. Franklin St.

 

 

Project Funding:

Activity

   Cost*

Right-of-Way Acquisition

   $   100,000

Construction 

   $ 3.0 Million

Total

   $ 3.1 Million

 

Project Timeline:

Milestone

Date  

Right-of-Way Acquisition Begins

February 2025  

Construction Begins

February 2026  

 

Project Comments:

NCDOT accepts comments throughout all phases of project development.  

All comments will be taken into consideration, and carry equal weight, regardless of submittal method.

Comments for consideration during the current phase of project development

were to be submitted before November 16, 2024.


The public is encouraged to leave comments using this webpage, email, or phone number:

Email: us701roundabout-whiteville@publicinput.com

Phone Number: 984-205-6615 enter project code 7366 to leave a message.

Question title

Would you like to be added to the project email list?

Project Contact Information 

Craig A. Freeman Jr., P.E.

Division Project Engineer 

NCDOT Highway Division 6

PO Box 1150

Fayetteville, NC 28302

Title VI Feedback

To ensure we’re hearing from a broad set of voices, would you be willing to share (completely anonymously) some information about yourself?

If so, please click here: https://publicinput.com/NCDOT-Title-VI-Form

 

RESOURCES FOR PROPERTY OWNERS 
Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road

project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right

of way acquisition and answers questions about the process.  

     
Right-of-Way Brochure Single Page Layout      Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions

Right of Way Acquisition Process Videos

English                                                                     Spanish