Project Area

 

 

Streetscape concepts being considered. This illustrates what is being considered between E Street and D Street. In the Docments section below, you can download the concept plans for the entire project corridor from E Street to A Street.

Project Status and Schedule

The concept level design for signal and lighting upgrades was completed in the spring of 2020, followed by completion of the concept level landscape plans this fall. The public involvement phase of the project is just getting started as we share these concept level plans with interested stakeholders. Final plans are anticipated to be completed late Summer/early Fall 2021, with construction shortly thereafter so that long lead material items can be ordered in 2021 and installed Summer 2022. 

Question title

What would you like us to know about the area as we move forward with the design?

Closed for Comments

Question title

What concerns do you have that you'd like to share?

Closed for Comments

Question title

What should we pay attention to during construction?

Closed for Comments

Project Background

The Downtown Signals and Lighting Upgrade project began with a Reconnaissance Study that was completed in August of 2018. The study involved inventorying and assessing the conditions of traffic signals and street lights located within the project area, which is the area bounded by 10th Avenue on the south, 1st Avenue on the north, L Street on the west, and Ingra Street on the east. Lighting systems were evaluated to determine if they met current standards. Deficiencies that were found included significant corrosion of pole base plates and anchor bolts (particularly along 4th Avenue), poor bonding/grounding, and electrical components that are too old to maintain or repair because replacement parts are unavailable. Moreover, the lighting levels failed to meet current standards in about half of the project area. To correct these deficiencies, the report recommended lighting and signalization improvements throughout the project area. (In the Documents section at the bottom, you can click to download photos of some of deficiencies that were found.)

The first upgrade project was 4th Avenue, A Street to Cordova Street which began in the summer of 2020. The traffic signals at A Street and Cordova Street were removed and replaced, and the street and pedestrian lighting were upgraded. Sidewalk and curb ramps were also replaced. While nearly complete, this project will be finished once the above ground traffic signal and light pole components arrive from the factory and are installed and operational.

Funding for the projects is coming from a variety of sources including federal highway funding and municipal bonds. DOT&PF is currently planning upgrades along 4th Avenue from Cordova Street to Ingra Street, using federal funds. MOA will continue upgrades, working westward along 4th Avenue. That work, as well as other future upgrade projects, will be implemented as funding allows. 

The map below demonstrates the extent of conduit bonding/grounding and junction boxes that are in poor condition.

Question title

* Sign up to recieve project update emails.

Contact Information

Joann Mitchell, PE
Public Involvement Coordinator
Kinney Engineering
(907) 344-7590

JoannMitchell@KinneyEng.com

OR

Julie Makela, PE
Project Administrator
Municipality of Anchorage
(907) 343-7598

julie.makela@anchorageak.gov