Preliminary Engineering Activities for this project
have been suspended.

The N.C. Department of Transportation proposes to improve the intersection of U.S. 17 and Oak Stump Road (S.R. 1145) in Pasquotank County.  

Alternative 1A

U.S. 17 Business will be realigned to create a signalized, four-legged intersection at U.S. 17 and the northern Elizabeth City Crossings entrance. A roundabout is proposed at the Port Elizabeth Centre entrance on U.S. 17 Business.

Alternative 1B

U.S. 17 Business will be realigned to create a signalized, four-legged intersection at U.S. 17 and the northern Elizabeth City Crossings entrance.

Alternative 2

U.S. 17 Business will be realigned to create a signalized, three-legged intersection at U.S. 17.

Vicinity Map:

 

Purpose and Need:

STIP Project U-5939 is located at the intersection of U.S. 17 and Oak Stump Road (S.R. 1145) in Pasquotank County, NC.  The primary purpose of this project is to improve traffic flow and safety at the intersection.

Public Involvement

Public Meetings

A public meeting was held on August 6, 2019 in Elizabeth City to obtain stakeholder and public input regarding the project's design.  

                                                   

Public Meeting Map for U.S. 17 and Oak Stump Road

Map 1:   

Alternatives 1A & 1B (Intersection of U.S. 17 & Old Stump Road)

Map 2:    

Alternative 2 (Intersection of U.S. 17 & Old Stump Road)

Project Funding

 This project is listed as Project U-5939 in the N.C. Department of Transportation’s State Transportation Improvement Program (STIP) and is funded for $2.028 million.

 

 

Estimated Amount*

   Project Development & Design  $      500,000
   Property Acquisition  $      280,000
   Construction  $    1,248,000
   Total Cost  $    2,028,000

* Estimated costs are subject to change. Based on NCDOT STIP.

 

Project Timeline

 Milestone

    Date*

  Environmental Document February 2020
  Right of Way Acquisition  Spring 2020
  Construction Begins Fall 2021

* Future dates are preliminary and subject to change

PROJECT CONTACT INFORMATION 

Roham Lahiji

Division Project Manager

NCDOT Division Highway 1

113 Airport Drive, Suite 100

Edenton, NC  27932

         252-482-1882

Would you like to be added to the project email list for updates?

RESOURCES FOR PROPERTY OWNERS 


Although the N.C. Department of Transportation works to minimize the number of homes and businesses displaced by a road project, it is inevitable, in many cases, that a certain amount of private property is needed. The following information explains right of way acquisition and answers questions about the process.  

 

Relocation Assistance Brochure                                       Asistencia para Reubicación      
Right-of-Way Acquisition Process Brochure             Folleto del Proceso de Adquisición de Bienes Raíces
Right-of-Way Frequently Asked Questions