Chefornak: DOT&PF Emergency Repair Work
Chefornak: DOT&PF Emergency Repair Work
DOT&PF is providing updates for each community and has built tools to report damages and request assistance. This page will help you see real-time updates in your community for infrastructure repairs & road access, water & sanitation status, and local recovery progress & resources.
Reporting Damage: If your home, property, or infrastructure was damaged, please report it using our Damage Assessment Hub at: https://damage-assessment-2-akdot.hub.arcgis.com
Need materials or assistance: If your community hasn’t connected with DOT&PF yet, reach out to dot.ask@alaska.gov - we’ll help coordinate approvals and connect you to supplies quickly.
DOT&PF Emergency Response Manager: Amber Shumpert, amber.shumpert@alaska.gov, 907-322-0603.
Water and sewer updates: check Alaska DEC West Coast Storm.
Chefornak Operations Summary
12/3/25
Daily Activities
- UICC crews were mobilized but did not arrive in Chefornak due to bad weather. They are now expected to arrive on Wednesday, 12/3.
12/2/25
Daily Activities
- UICC crews were mobilized but did not arrive in Chefornak due to bad weather. They are now expected to arrive on Wednesday, 12/3.
11/29/25
Daily Activities
- UICC crews are scheduled to be in Chefornak on 12/1 and will start repairs for the LKSD buildings. Repairs include sewer line, foundation repair and insulation replacement at teacher housing as well as roof repairs at the pre-school. Asbestos is an identified hazard to deal with in these repairs.
- Working on material list/procurement for LKSD repairs.
- It is intended that once UICC crews are on-site, residential repairs will be completed as needed or requested.
11/21/2025
Daily Activities
- UICC crews are scheduled to be in Chefornak on 12/1 and will start repairs for the LKSD buildings. Repairs include sewer line, foundation repair and insulation replacement at teacher housing as well as roof repairs at the pre-school. Asbestos is an identified hazard to deal with in these repairs.
- Working on a material list/procurement for LKSD repairs.
- It's intended that once UICC crews are on-site, residential repairs will be completed as needed or requested.
11/18/2025
- Horizontal Work Complete.
11/15/2025
- Knik Construction is onsite working on boardwalk repairs, anticipating completion on COB Sunday.
- Working on timeline for UICC to be on-site to start repairs.
- Priority is school/teacher housing repairs. Need to coordinate with LKSD.
11/14/2025
- No Change: Knik Construction is onsite working on boardwalk repairs, anticipating end of week completion.
11/13/2025
- No Change: Knik Construction is onsite working on boardwalk repairs, anticipating end of week completion.
11/11/2025
- (no change) UICC is onsite in Chefornak for assessments. Contractor has been notified of high-priority school sewer line replacement.
- Knik Construction is onsite working on boardwalk repairs, anticipating end of week completion.
11/10/2025
- Knik Construction is onsite working on boardwalk repairs, anticipating end of week completion.
- No Change: UICC is onsite for assessments; contractor has been notified of high-priority school sewer line replacement.
11/09/2025
- Knik Construction is onsite working on boardwalk repairs, anticipating 4 more days to completion.
11/08/2025
- Boardwalk restoration ~50% complete; ~6 days of work remaining as of Nov 6.
- Tasks: replace planks, re-set helical piles, reinforce undermined spans.
- All materials on hand; progress steady with no new issues.
- Completion anticipated by mid-next week; mobility to be fully restored.
- Knik Construction onsite working on boardwalk repairs.
- Repairing sections towards sewer lagoon.
11/06/2025
- UICC scheduled to travel to Chefornak for November 06 for assessments. Contractor has been notified of priority school sewer line replacement.
- Knik Construction is onsite working on boardwalk repairs, anticipating 6 more days to completion.
11/5/2025
- Knik Construction is onsite working on boardwalk repairs.
11/4/2025
- Knik Construction is onsite working on boardwalk repairs.
11/3/2025
- Knik Construction is onsite working on boardwalk repairs.
- Constructability issues due to access across private property.
11/1/2025
- Knik Construction has hired a local crew for boardwalk repairs and is making steady progress.
10/30/2025
- Contractor supplies are in Bethel and on route to Akiak.
- UICC is mobilizing crews to Napakiak to assess and begin mechanical, electrical, and structural work on the school and associated structures.
- DOT&PF personnel have been made aware of possible humanitarian issues in Napaskiak and Oscarville that are currently being assessed.
10/22/2025 - Infrastructure Damage Assessment.
10/19/2025 - Infrastructure Damage Assessment.
10/14/2025 - Infrastructure Damage Assessment.
11/15/2025
11/14/2025
11/13/2025
11/11/2025
11/10/2025
11/09/2025
11/08/2025
11/4/2025
Knik Construction is onsite working on boardwalk repairs.
11/3/2025
Crews making progress on boardwalks
11/1/2025
Boardwalk progress