Chefornak Operations Summary

12/3/25

Daily Activities

  • UICC crews were mobilized but did not arrive in Chefornak due to bad weather. They are now expected to arrive on Wednesday, 12/3. 

12/2/25

Daily Activities

  • UICC crews were mobilized but did not arrive in Chefornak due to bad weather. They are now expected to arrive on Wednesday, 12/3. 

11/29/25

Daily Activities

  • UICC crews are scheduled to be in Chefornak on 12/1 and will start repairs for the LKSD buildings. Repairs include sewer line, foundation repair and insulation replacement at teacher housing as well as roof repairs at the pre-school. Asbestos is an identified hazard to deal with in these repairs. 
  • Working on material list/procurement for LKSD repairs. 
  • It is intended that once UICC crews are on-site, residential repairs will be completed as needed or requested. 

11/21/2025

Daily Activities

  • UICC crews are scheduled to be in Chefornak on 12/1 and will start repairs for the LKSD buildings. Repairs include sewer line, foundation repair and insulation replacement at teacher housing as well as roof repairs at the pre-school. Asbestos is an identified hazard to deal with in these repairs. 
  • Working on a material list/procurement for LKSD repairs. 
  • It's intended that once UICC crews are on-site, residential repairs will be completed as needed or requested. 

11/18/2025

  • Horizontal Work Complete. 

11/15/2025

  • Knik Construction is onsite working on boardwalk repairs, anticipating completion on COB Sunday. 
Daily Activities 
  • Working on timeline for UICC to be on-site to start repairs. 
  • Priority is school/teacher housing repairs. Need to coordinate with LKSD. 

11/14/2025

  • No Change: Knik Construction is onsite working on boardwalk repairs, anticipating end of week completion. 

11/13/2025

  • No Change: Knik Construction is onsite working on boardwalk repairs, anticipating end of week completion. 

11/11/2025

  • (no change) UICC is onsite in Chefornak for assessments.  Contractor has been notified of high-priority school sewer line replacement.
  • Knik Construction is onsite working on boardwalk repairs, anticipating end of week completion. 

11/10/2025

  • Knik Construction is onsite working on boardwalk repairs, anticipating end of week completion.
  • No Change: UICC is onsite for assessments; contractor has been notified of high-priority school sewer line replacement.

11/09/2025

  • Knik Construction is onsite working on boardwalk repairs, anticipating 4 more days to completion.

11/08/2025

  • Boardwalk restoration ~50% complete; ~6 days of work remaining as of Nov 6.
  • Tasks: replace planks, re-set helical piles, reinforce undermined spans.
  • All materials on hand; progress steady with no new issues.
  • Completion anticipated by mid-next week; mobility to be fully restored.
  • Knik Construction onsite working on boardwalk repairs.
  • Repairing sections towards sewer lagoon.

11/06/2025

 

  • UICC scheduled to travel to Chefornak for November 06 for assessments.  Contractor has been notified of priority school sewer line replacement.
  • Knik Construction is onsite working on boardwalk repairs, anticipating 6 more days to completion.

11/5/2025

  • Knik Construction is onsite working on boardwalk repairs.

11/4/2025

  • Knik Construction is onsite working on boardwalk repairs.

11/3/2025

  • Knik Construction is onsite working on boardwalk repairs.
  • Constructability issues due to access across private property.

11/1/2025 

  • Knik Construction has hired a local crew for boardwalk repairs and is making steady progress.

10/30/2025

  • Contractor supplies are in Bethel and on route to Akiak.
  • UICC is mobilizing crews to Napakiak to assess and begin mechanical, electrical, and structural work on the school and associated structures.
  • DOT&PF personnel have been made aware of possible humanitarian issues in Napaskiak and Oscarville that are currently being assessed.

10/22/2025 - Infrastructure Damage Assessment.


10/19/2025 - Infrastructure Damage Assessment.


10/14/2025 - Infrastructure Damage Assessment.

11/15/2025


11/14/2025


11/13/2025


11/11/2025


11/10/2025


11/09/2025


11/08/2025


11/4/2025

Knik Construction is onsite working on boardwalk repairs.

Chefornak 11.05.2025


11/3/2025

Crews making progress on boardwalks


11/1/2025

Boardwalk progress