Chefornak Operations Summary

3/05/26

Facilities Daily Report

  • Work is performed by UIC Construction, LLC.
  • Sanded surfaces and completed touch ups on dents and cracks. 
  • Completed prep work and painting on many surfaces. 
  • Installed, wired, and adjusted ceiling lights. 
  • Finalized interior work and prepared areas for inspection. 
  • Developed and updated mockups and layout plans for sewer outfall locations. 
  • Fabricated, cut, and assembled metal supports and brackets. 
  • Installed sewer outfall components and continued adjustments and alignment. 
  • Continued sewer system installation and associated structural work. 
  • Completed roof installation prep and painted roof areas when available. 
  • Performed trimming, framing adjustments, and miscellaneous finish work. 
  • Finished cleaning up and organized project areas.

3/05/26

Facilities Daily Report

  • Work is performed by UIC Construction, LLC. 
  • Continued sewer repairs. 
  • Performed electrical system repairs. 
  • Completed interior repairs and remodeling. 
  • A total of seven UICC team members onsite.

2/20/26

Facilities Daily Report

  • Work is performed by UIC Construction, LLC. 
  • Continued sewer repairs. 
  • Performed electrical system repairs. 
  • Completed interior repairs and remodeling. 
  • A total of seven UICC team members onsite. 

2/16/26

Facilities Daily Report

  • Work is performed by UIC Construction, LLC. 
  • Continue installation and securing arctic piping; ensure alignment and prepare for future system integration. 
  • A total of seven UICC team members are currently on-site. 

2/12/26

Facilities Daily Report

  • Work is performed by UIC Construction, LLC. 
  • Continue installation and securing arctic piping; ensure alignment and prepare for future system integration. 
  • A total of seven UICC team members are currently on-site. 

1/31/26

Facilities Daily Report

  • Fuse pipe sections and secure them to structural components. 
  • Align and stabilize existing supports, weld and plumb structural elements. 
  • A total of seven UICC team members are currently on-site. 

1/14/26

Facilities Daily Report

  • Continue work on arctic pipe installation. 
  • A total of four UICC team members are currently on-site. 

1/6/2026

Facilities Daily Report

  • Continue work on arctic pipe installation. 
  • A total of 4 UICC team members are currently on-site. 

11/15/2025


11/14/2025


11/13/2025


11/11/2025


11/10/2025


11/09/2025


11/08/2025


11/4/2025

Knik Construction is onsite working on boardwalk repairs.

Chefornak 11.05.2025


11/3/2025

Crews making progress on boardwalks


11/1/2025

Boardwalk progress