2017-2022 Bond Project: North New Braunfels Ave Phase 1 (E Houston St to Burleson St)

2017-2022 Bond Project: North New Braunfels Ave Phase 1 (E Houston St to Burleson St)

 

The Bond Project will improve N. New Braunfels corridor from E. Houston to Burleson with the construction of new sidewalks and other street amenities as appropriate and within available funding. Phase 2 (E. Houston St. to Paso Hondo St.) is part of the 2022-2027 Bond Program.

Project Type: Streets, Bridges & Sidewalks 

Phase: Compelete

Project Contact: Sean Strong - (210) 207-8037

Estimated Construction Timeline: Fall 2021 - Fall 2023

Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December.)

 

Related Projects:

 


Project Budget:

 

 

2017 General Obligation Bond (Street)

           $7,400,315.10

CPS Energy

               $563,547.13

San Antonio Water System

           $3,566,247.26

Total

     $115,30,109.49



SUPPORT YOUR LOCAL SMALL BUSINESSES: https://www.sanantonio.gov/EDD/Programs-Grants/Paving-The-Way

NOTE TO BUSINESS OWNERS:

If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.

Business Outreach Specialist: Monica Cantu, 210-207-3935


Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.

Contact Information

If you would like to receive updates on the project, please submit your contact information below.

Please share any feedback or questions about this project.