Mekoryuk Operations Summary

4/03/2026

Facilities Daily Report

  • Performed general site coordination and preliminary review activities across the Mekoryuk School, gym addition, and teacher housing. 
  • Conducted roof inspections at the gym addition, identifying storm related damage, locating an active leak and determining that fail exhaust-fan shroud and deteriorated fasteners require removal and patching of the opening. 
  • Identified siding damage at the teacher housing and noted the likely presence of spare materials onsite but inaccessible due to the amount of snow. 
  • Coordinated with school administration and maintenance staff to confirm issues and aligned on necessary corrective actions. 

2/16/2026

Facilities Daily Report

  • Work is on hold until completion of either Chefornak or Napaskiak; the first available crew will mobilize to Mekoryuk, where less than one week of work is anticipated. 

2/12/2026

Facilities Daily Report

  • Work is on hold until completion of either Chefornak or Napaskiak; the first available crew will mobilize to Mekoryuk, where less than one week of work is anticipated. 

1/16/2026

Facilities Daily Report

    • Work is on hold until completion of either Chefornak or Napaskiak; the first available crew will mobilize to Mekoryuk, where less than one week of work is anticipated. 

    1/14/2026

    Facilities Daily Report

      • A sample of the existing roofing of the Nuniwarmiut School that was damaged has been received. Working on procurement of matching profile/color. 
        • May provide initial repair with flat stock metal and circle back to more "permanent repair" once material can be sourced - Nonmatching metal may require re-roof of the entire side damaged.