Project Overview
This proposed Virginia Department of Transportation (VDOT) project, funded by Stafford County, would install a modular roundabout at the intersection of Banks Ford Parkway and Celebrate Virginia Parkway in Stafford.
Modular roundabouts are prefabricated units made from recycled material that make installation easy and quick. VDOT crews are able to bolt down pieces over a period of weeks for each roundabout when compared to a lengthier timeline for typical roundabout construction. They are also a lower-cost alternative compared with traditional roundabout construction.
New pavement markings and posted signs also direct traffic through the roundabout.
VDOT installed modular roundabouts at several Chesterfield County intersections in 2020. Click here to learn more.
Photo below from completed VDOT modular roundabout at Otterdale Road and Hampton Park Drive in Chesterfield County:
Design Public Hearing: November 6, 2023
Stop by the in-person design public hearing between 5:30-7:30 p.m. on Monday, November 6, 2023, to review proposed project plans and materials, ask questions, and offer comment.
A brief presentation will be delivered at 5:45 p.m.
VDOT representatives will be present to answer questions about the project in an open house format between 5:30-7:30 p.m.
The public hearing is being held at:
Central Rappahannock Regional Library, Howell Branch
806 Lyons Boulevard
Fredericksburg, VA 22406 (Stafford County)
Give your comments at the hearing or submit them by November 16, 2023, to Mr. Richard Spurlock, VDOT Project Manager, 87 Deacon Road, Fredericksburg, VA 22405. Comments may also be submitted through the online comment form on this page or emailed to fred.comments@vdot.virginia.gov. Please reference “Celebrate Virginia Parkway and Banks Ford Parkway PH Comment” in the email subject line.
The inclement weather date for the public hearing is Monday, November 13, 2023. If the hearing on November 6 is canceled for inclement weather, the hearing will be rescheduled for this date and will be held at the same time and in the same location.
Project Benefits
- Reduces the risk of crashes, especially angle crashes. Angle crashes often occur between vehicles traveling straight through an intersection and vehicles making a turn, when the front of a vehicle collides at a right angle with the side of a vehicle.
- Rapid installation at a lower cost than a traditional roundabout
Project Cost
- $700,000 in locality funds
Major Milestones
Design Public Hearing: November 6, 2023
Construction Begins: Spring 2024
Construction Complete: Summer 2024
Project Documents
Public Hearing Display: Proposed Roundabout Design
Design Public Hearing Newspaper Advertisement
Project contacts
Mr. Richard Spurlock
(540) 899-4302
Richard.Spurlock@VDOT.Virginia.Gov
and
Ms. Kelly Hannon
VDOT Communications Manager
(540) 656-0321 cell
Kelly.Hannon@VDOT.Virginia.Gov
Phase: Proposed
Locality: Stafford County
Special assistance for persons with disabilities or limited English proficiency: VDOT ensures nondiscrimination and equal employment in all programs and activities in accordance with Title VI and Title VII of the Civil Rights Act of 1964. If you need special assistance for persons with disabilities or limited English proficiency, contact the project manager at (540) 899-4302, the VDOT Fredericksburg District office at (540) 899-4288, or TTY/TDD 711.