Kwigillingok Operations Summary

3/03/26

  • Cruz: Continued support for other contractors. Continued boardwalk installation: one excavator drove piles; 2nd drive unit is broken down with plans in the works to get the other helical head driver operational. Continued installation of boardwalk deck and support brackets. Removed snow. Installed boardwalk deck out to freshwater source. Installed piles out to sewage lagoon. 
  • Helical Piles to date: 1,016/ Linear feet of boardwalk: 1,080. 
  • Brice/STG: Local and non-local hires on. Critical infrastructure checks still being performed. Two plumbers currently troubleshooting and monitoring school's sewer line. 
  • Delta Backhaul: Removed and hauled debris. Assisted with snow removal. Supported other contractors. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K13: Stripped insulation, removed skirting, and began drying out. 
  • #K14: Began interior wall painting. 
  • #K20: Repaired damaged wall, removed deteriorated plywood, and completed floor repairs. 
  • #K33: Stripped insulation, removed skirting, and began drying out.
  • #K43: Attempted to thaw sewer tank.
  • #K46: Serviced boiler. 
  • General: Installed hot water heater in rental unit, prefabricated components for heater installations. 
  • Total of 24 team members onsite. 

3/02/26

  • Cruz: Continued support for other contractors. Continued boardwalk installation. Day shift installed 12 helicals/night shift installed 12 helicals. Continued installation of boardwalk deck and support brackets. Removed snow. Installed boardwalk deck out to freshwater source. Installed piles out to sewage lagoon. 
  • Helical Piles to date: 837/ Linear feet of boardwalk: 1,080. 
  • Brice/STG: Local and non-local hires on. Critical infrastructure checks still being performed. Two plumbers currently troubleshooting and monitoring school's sewer line. 
  • Delta Backhaul: Removed and hauled debris. Assisted with snow removal. Supported other contractors. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K13: Cleared snow around the house and gathered cribbing. 
  • #K14: Completed interior wall sheeting with AC plywood and began painting.
  • #K16: Installed new beams, raised the house to elevation, and set posts and pads on the south side of the house. 
  • #K20: Finished interior insulation and began interior sheeting. 
  • #K65: Performed lift operations on the structure. 
  • Total of 25 team members onsite. 

3/01/26

  • Cruz: Continued support for other contractors. Continued boardwalk installation. Day shift installed 12 helicals/night shift installed 10 helicals. Continued installation of boardwalk deck and support brackets. Removed snow. Installed boardwalk deck out to freshwater source. Installed piles out to sewage lagoon. 
  • Helical Piles to date: 813/ Linear feet of boardwalk: 990. 
  • Brice/STG: Local and non-local hires on standby including three electricians, two wiremen, and one plumber. Critical infrastructure checks still being performed. 
  • Delta Backhaul: Removed/hauled debris. Assisted with snow removal and supported other contractors. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

2/28/26

  • Cruz: Continued support for other contractors. Continued boardwalk installation. Day shift installed eight helicals/night shift installed eight helicals. Continued installation of boardwalk deck and support brackets. Removed snow. Installed boardwalk deck out to freshwater source. Installed piles out to sewage lagoon. 
  • Helical Piles to date: 791/ Linear feet of boardwalk: 880. 
  • Brice/STG: Local and non-local hires on standby including three electricians, two wiremen, and one plumber. Critical infrastructure checks still being performed. 
  • Delta Backhaul: Removed/hauled debris. Assisted with snow removal and supported other contractors. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K13: Cleared snow around the house and gathered cribbing materials. 
  • #K14: Sheeted interior walls with plywood. 
  • #K16: Installed new beams and completed preparation to raise and set the structure. 
  • #K18: Removed floor insulation and skirting for drying and constructed stairs; prepared the unit for closeout.
  • #K19: Completed interior painting and prepared for closeout. 
  • #K20L Finished cleaning the house; completed underlayment installation to 100%. 
  • #K78: Completed fur-out work and installed insulation; prepared for electrical service. 
  • Total of 33 team members onsite. 

2/27/26

  • Cruz: Continued support for other contractors. Continued boardwalk installation. Day shift installed eight helicals/night shift installed seven helicals. Continued installation of boardwalk deck and support brackets. Removed snow. Installed boardwalk deck out to freshwater source. Installed piles out to sewage lagoon. 
  • Helical Piles to date: 785/ Linear feet of boardwalk: 880. 
  • Brice/STG: Local and non-local hires on standby including three electricians, two wiremen, and one plumber. Critical infrastructure checks still being performed. 
  • Delta Backhaul: Removed/hauled debris. Assisted with snow removal and supported other contractors. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K13: Prepared to elevate the structure and remove existing insulation. 
  • #K14: Completed walls sheathing installation. 
  • #K18: Completed installation of posts and pads with bracing; began removal of existing materials; completed final sheathing installation and painting.
  • #K19: Installed trim at base and corner locations. 
  • #K20: Removed insulation and allowed the area to dry; performed general cleaning and completed underlayment sheathing installation on one side. 
  • #K78: Completed fur-out work and installed insulation. 
  • Total of 31 team members onsite. 

2/26/26

  • Cruz: Continued support for other contractors. Continued boardwalk installation. Day shift installed six helicals/night shift installed four helicals. Continued installation of boardwalk deck and support brackets. Removed snow. Installed boardwalk deck out to freshwater source. Installed piles out to sewage lagoon. 
  • Helical Piles to date: 761/ Linear feet of boardwalk: 880. 
  • Brice/STG: Local and non-local hires on standby including three electricians, two wiremen, and one plumber. Critical infrastructure checks still being performed. 
  • Delta Backhaul: Removed/hauled debris. Assisted with snow removal and supported other contractors. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K14: Finished vapor barrier and began sheeting. 
  • #K18: Finished posts and pads; installed vapor barrier and sheeting on walls.
  • #K19: Applied second coat of paint for walls and floor; finished floor insulation and underlayment. 
  • #K20: Insulated floor and began sheeting. 
  • #K65: Prepared house for relocation from across the river.
  • Total of 31 team members onsite.   

2/25/26

  • Cruz: Continued support for other contractors. Continued boardwalk installation. Day shift installed 106 helicals/night shift installed 61 helicals. Continued installation of boardwalk deck and support brackets. Removed snow. Installed boardwalk deck out to freshwater source. Installed piles out to sewage lagoon. 
  • Helical Piles to date: 751/ Linear feet of boardwalk: 760. 
  • Brice/STG: Local and non-local hires on standby including three electricians, two wiremen, and one plumber. Critical infrastructure checks still being performed. 
  • Delta Backhaul: Removed/hauled debris. Assisted with snow removal and supported other contractors. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K14: Installed insulation and vapor barrier. 
  • #K18: Installed posts and pads; prepared the structure for insulation and vapor barrier installation. 
  • #K19: Painted interior walls and flooring surfaces. 
  • #K20: Constructed stairs and completed removal of interior materials and wet insulation to allow for drying. 
  • #K41: Relocated the structure to the designated site; relocated the steam bath adjacent to the structure. 
  • Total of 29 team members onsite. 

2/24/26

  • Cruz: Continued support for other contractors. Continued boardwalk installation. Day shift installed 68 helicals/ night shift installed 80 helicals. Continued installation of boardwalk deck and support brackets. Removed snow. Installed boardwalk deck out to freshwater source. Installed piles out to sewage lagoon. 
  • Helical Piles to date: 751/ Linear feet of boardwalk: 680. 
  • Brice/STG: Local and non-local hires on standby including three electricians, two wiremen, and one plumber. Critical infrastructure checks still being performed. 
  • Delta Backhaul: Removed/hauled debris. Assisted with snow removal and supported other contractors. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K14: Finished foam board installation. Reinsulated walls and installed vapor barrier. 
  • #K15: Installed foam board underlayment. 
  • #K18: Lifted house to elevation for new post and pad. Set post and pads. 
  • #K19: Installed insulation, vapor barrier, and sheeting. Installed insulation, vapor barrier, and sheeting. Installed stairs.
  • #K20: Finished post and pad along with bracing. 
  • #K28: General cleaning of the house for inspection. 
  • #K31: Stripped interior and wet insulation for dry out. 
  • #K42: Moved house to new location 1/2 mile, raised and removed skid. 
  • Total of 31 team members onsite. 

2/23/26

  • Cruz: Continued support for other contractors. Continued boardwalk installation. Day shift installed 57 helicals/ night shift installed 74 helicals. Continued installation of boardwalk deck and support brackets. Removed snow. Installed boardwalk deck out to freshwater source. Installed piles out to sewage lagoon. 
  • Helical Piles to date: 472/ Linear feet of boardwalk: 540. 
  • Brice/STG: Local and non-local hires on standby including three electricians, two wiremen, and one plumber. Critical infrastructure checks still being performed. 
  • Delta Backhaul: Removed/hauled debris. Assisted with snow removal and supported other contractors. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K14: Completed underlayment and started installation of foam board.
  • #K15: Wrapped up underlayment and initiated placement of foam board underlayment. 
  • #K18: Removed insulation for drying and performed general cleaning.
  • #K19: Installed insulation, vapor barrier, and sheeting. 
  • #K20: Set posts and pads, 75% completed. 
  • #K42: Prepared house for relocation. 
  • Total of 27 team members onsite. 

2/22/26

  • Cruz: Continued support for other contractors. Continued boardwalk installation. Day shift installed 16 helicals/night shift installed 47 helicals. Continued installation of boardwalk deck and support brackets. Removed snow. Received approval from council member Gavin Phillip to offset boardwalk out to sewage lagoon and begin driving piles. 
  • Helical piles to date: 472/ linear feet of boardwalk: 540. 
  • Brice/STG: Non-local hires on standby including three electricians, two wiremen, and one plumber. Local hires continued fuel haul, airfield operations, infrastructure checks and other daily operations. 
  • Delta Backhaul: Assisted with snow removal and support other contractors. 
  • Hog River: Moving/leveling houses. Setting dog houses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K14 and #K15: Installed floor insulation and underlayment. 
  • #K18: Removed wet insulation to facilitate drying. 
  • #K19: Repaired rim joist and wall. Reinstalled insulation in walls and applied vapor barrier. 
  • #K20: Raised house to final elevation and set posts and pads on east side. 
  • #K42: Raised house in preparation for relocation. 
  • Total of 27 team members onsite. 

2/21/26

  • Cruz: Continued support for other contractors. Continued boardwalk installation. Day shift installed 16 helicals/night shift installed 40 helicals. Continued installation of boardwalk deck and support brackets. Removed snow. Received approval from council member Gavin Phillip to offset boardwalk out to sewage lagoon and begin driving piles. 
  • Helical piles to date: 416/ linear feet of boardwalk: 540. 
  • Brice/STG: Non-local hires on standby including three electricians, two wiremen, and one plumber. Local hires continued fuel haul, airfield operations, infrastructure checks and other daily operations. 
  • Delta Backhaul: Assisted with snow removal and support other contractors. 
  • Hog River: Moving/leveling houses. Setting dog houses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 

2/20/26

  • Cruz: Continued support for other contractors. Continued boardwalk installation. Night shift installed 6 helicals. Continued installation of boardwalk deck and support brackets. Removed snow. Received approval from council member Gavin Phillip, to offset boardwalk out to sewage lagoon and begin driving piles. 
  • Helical Pules to Date: 354/Linear feet of boardwalk: 240. 
  • Brice/STG: Non-local hires on standby including three electricians, two wiremen, and one plumber. Local hires continued fuel haul and airfield and other daily operations. 
  • Delta Backhaul: Assisted with snow removal. Supported other contractors. 
  • Hog River: Moving/leveling houses. Setting dog houses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K02: Conducted dog house repairs. 
  • #K14 & #K15: Removed wet insulation beneath flooring and skirting. Continued drying out floors. 
  • #K18: Removed water - damaged wall materials. 
  • #K19: Repaired rim joist and wall. Removed remaining insulation and dry interior. Conducted dog houses repair. 
  • #K20: Elevated structure by 3.5 feet. 
  • #K42: Removed ice accumulation from building base. 
  • #K43 and #K49: Performed water and sewer system repairs. 
  • #K77: Elevated structure off beams. 
  • Total of 30 team members onsite. 

2/19/26

  • Cruz: Continued support for other contractors. Continued boardwalk installation. Continued installation of boardwalk deck and support brackets. Continued snow removal. 
  • Helical Piles to Date: 354/linear feet of boardwalk: 240. 
  • Brice/STG: Pulled majority of crew out of Kwig. A few guys stayed behind for equipment watch. Local hires continued fuel haul and airfield operations. 
  • Delta Backhaul: Assisted with snow removal and supported other contractors. 
  • Hog River: Moving/leveling houses. Setting dog houses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K14: Remove wet insulation under flooring and skirting. Initiate drying process. 
  • #K15: Continued drying process underneath the unit. 
  • #K18: Remove water-damaged wall materials. 
  • #K19: Completed post and pad installation with bracing. Repaired damaged rim joist and wall. Removed remaining insulation. 
  • #K43 and #K49: Continued water and sewer system repairs. 
  • #K78: Constructed stairs. Framed interior walls and door openings. 
  • Total of 32 team members on-site. 

2/18/26

  • Cruz: Continued support for other contractors. Continued boardwalk installation: night shift installed 13 helicals. Continued installation of boardwalk deck and support brackets and continued snow removal. 
  • Helical Piles to Date: 354/linear feet of boardwalk: 240. 
  • Brice/STG: Maintained critical infrastructure. Conducted daily checks on WTP/washeteria, health clinic, and powerplant. Continued fuel haul, and assisted airfield operations. Installed new meter and 15' hose to LKSD fuel tank. 
  • Delta Backhaul: Assisted with snow removal and supported other contractors. 
  • Hog River: Moving/leveling houses. Setting dog houses for installation. Drying/thawing houses and removing wet/damaged material in houses. Continuing to install new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K02: Perform painting and general interior cleaning. 
  • #K14: Remove damaged insulation, installed stairs, and completed fuel system adjustments. 
  • #K15: Position doghouse structure on foundation supports, installed skirting, and initiated drying process underneath the unit. 
  • #K19: Elevated structure, set foundation supports, and removed ceiling insulation. 
  • #K43 and #K49: Conducted water and sewer system repairs. 
  • #K78: Cleared addition area and framed walls to prepare for insulation installation. 
  • Water Plant: Perform routine operational checks. 
  • Total of 29 team members on-site. 

2/17/26

  • Cruz: Continued support for other contractors. Continued boardwalk installation: day shift installed six helicals. Continue installation of boardwalk deck and support brackets. Continued snow removal. 
  • Helical Piles to Date: 331/Linear feet of boardwalk: 80. 
  • Brice/STG: Maintained critical infrastructure. Conducted daily checks on WTP/washeteria, health clinic, and powerplant. Continued fuel haul, and assisted airfield operations. 
  • Delta Backhaul: Assisted with snow removal and supported other contractors. 
  • Hog River: Moving/leveling houses. Setting dog houses for installation. Drying/thawing houses and removing wet/damaged material in houses. Continuing to install new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K14: Complete post and pad foundation installation with bracing. 
  • #K15: Install second fuel tank on stand. 
  • #K19: Frame out wall and repair deteriorated section of flooring. 
  • #K20: Remove interior finishes and continue cleaning. 
  • #K32: Clear debris around the house. 
  • #K43 & #K49: Performed water and sewer system repairs. 
  • #K78: Frame out wall and prepare structure for storm conditions. 
  • Total of 30 team members are currently on-site. 

2/16/26

  • Cruz: Continued support for other contractors. Continued boardwalk installation: day shift installed 19 helicals/night shift installed two helicals. Continuing to install boardwalk materials and removed snow. 
  • Brice/STG: Maintained critical infrastructure. Conducted daily checks on WTP/washeteria, health clinic, and powerplant. Continued fuel haul and assisted airfield operations. 
  • Delta Backhaul: Assisted with snow removal and supported other contractors. 
  • Hog River: Moving/leveling hoses. Setting dog houses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K14: Install middle beam along with posts and pads. 
  • #K15: Remove wet insulation. 
  • #K19: Frame out wall and repair deteriorated section of flooring. 
  • #K20 and #K32: Remove interior finishes and general cleaning. 
  • #K43 and #K49: Conduct water and sewer system repairs. 
  • #K78: Install underlayment with CDX and apply metal roofing. 
  • Rental Units: Perform plumbing repairs. 
  • Total of 28 team members are currently onsite. 

2/15/26

  • Cruz: Continued support for other contractors. Continued boardwalk installation: day shift installed four helicals/night shift installed none. Installing boardwalk material. Continuing to remove snow. 
  • Brice/STG: Maintained critical infrastructure. Conducted daily checks on WTP/washeteria, health clinic, and powerplant. Continued thawing/drying for diagnosis of community skid steer. Offloaded fuel. Conducted sewage haul. 
  • Delta Backhaul: Assisted with snow removal and supported other contractors. 
  • Hog River: Moving/leveling hoses. Setting dog houses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K02: Interior trim installation. 
  • #K14: Complete post and pad installation. 
  • #K15: Remove wet insulation and floor sheathing. 
  • #K19: Perform interior stripping. 
  • #K32: Conduct house cleaning and interior stripping. 
  • #K77: Install ice shield. 
  • #K78: Relocate house structure. 
  • Rental Units: Perform plumbing repairs. 
  • Total of 32 team members are currently on-site. 

2/14/26

  • Cruz: Continued support for other contractors. Continued boardwalk installation: no helicals were installed on either shift. Both driver heads are down. Worked on snow removal. 
  • Brice/STG: Maintained critical infrastructure. Conducted daily checks on WTP/washeteria, health clinic, and powerplant. Continued thaw/dry for diagnosis of community skid steer. Offload fuel. Conducted sewage haul. 
  • Delta Backhaul: Worked indoors. Assisted with snow removal and supported other contractors.
  • Hog River: Moving/leveling houses. Setting dog houses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K02: Interior trim installation. 
  • #K14: House life. 
  • #K19: Continue interior stripping. 
  • #K32: Clean the interior and remove designated surfaces. 
  • #K49: Interior finish painting completed. 
  • Plumbing: Repair rental units. 
  • Water Plant: Continue monitor water return systems. 
  • Total of 12 team members onsite.

2/13/26

  • Cruz: Continued support for other contractors. Continued boardwalk installation: no helical piles were installed on either shift. Both driver heads are down. Continued snow removal. 
  • Brice/STG: Maintained critical infrastructure. Conducted daily checks on WTP/washeteria, health clinic, and powerplant. Troubleshoot/repair Toyo at marina store. Transported community to heated hooch to begin thaw/dry for diagnosis. Assist GCI personnel. 
  • Delta Backhaul: Worked indoors. Assisted with snow removal. Supporting other contractors. 
  • Hog River: Moving/leveling houses. Setting dog houses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K02: Interior trim installation (on hold due to inclement weather). 
  • #K14: House life (on hold due to inclement weather). 
  • #K19: Continue interior stripping. 
  • #K32: Clean the interior and remove designated surfaces. 
  • #K77: House post pad and bracing (on hold due to inclement weather). 
  • Plumbing: Repair rental units. 
  • Water Plant: Continue monitor water return systems. 
  • Total of 25 team members onsite. 

2/12/26

  • Cruz: Continued helical installation. Demo boardwalk/remove debris in helical path. Snow removal throughout village. Continue helical pile installation. 
  • Brice/STG: Maintain critical infrastructure. Conducted daily checks on WTP/washeteria, health clinic, powerplant, sewage line. Assisted with airfield operations. 
  • Delta Backhaul: Assisted with snow removal. 
  • Hog River: Moving/leveling houses. Setting doghouses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K02: Continue installation of interior trim. 
  • #K14: Elevate the structure to the required height. 
  • #K19: Continue interior stripping. 
  • #K32: Clean the interior and remove designated surfaces. 
  • #K49: Complete interior finish painting throughout the unit. 
  • #K77: Install foundation post pads and apply structural bracing to stabilize the unit. 
  • Rental Units and 20-Unit Housing: Repair plumbing systems to ensure proper functionality. 
  • Water Plant: Monitor water return systems to maintain compliance and performance. 
  • Total of 32 team members on-site. 

2/11/26

  • Cruz: Continued helical installation. Demo boardwalk/remove debris in helical path. Snow removal throughout village. 
  • Brice/STG: Maintain critical infrastructure. Assisted with airfield operations. 
  • Delta Backhaul: Assisted with snow removal. 
  • Hog River: Moving/leveling houses. Setting doghouses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K02: Completed installation of interior trim. 
  • #K19: Performed interior stripping. 
  • #K49: Continued application of interior finish paint. 
  • D.J. House: Elevated structure in preparation for relocation. 
  • J.W. House: Raised structure by three feet and installed posts and pads. 
  • Rental units and 20-unit housing: Conducted plumbing repairs. 
  • Water Plant: Monitored water return systems. 
  • Total of 29 team members currently on-site. 

2/10/26

  • Cruz: Continued support for other contractors. Continued boardwalk installation: Day installed five helicals/night shift installed 22 helicals. Worked on ways to improve helical installation. 
  • Brice/STG: Created parts list for gasoline fuel dispenser at fuel depot. Conducted daily checks on WTP/washeteria, health clinic, and powerplant. Finished drying out health clinic floor. 
  • Delta Backhaul: DBH worked indoors due to blizzard conditions. 
  • Hog River: Moving/leveling houses. Setting doghouses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 

Facilities Daily Report

    • Work performed by Hog River Construction.
    • #K02: Construct stair rails and complete interior trim installation.
    • #K08: Continue lifting the house off the skid. 
    • #K49: Continue interior finish painting. 
    • Water Plant: Monitor water return systems. 
    • Rental Units and 20-Unit Housing: Perform plumbing repairs. 
    • Total of 29 team members currently on-site.  

    2/08/26

    • Cruz: Continuing boardwalk out to the raw water supply, Cruz is looking into getting more crew out here late next week to start boardwalk installation, 39 helical installed the last full day and night shift. 
    • Brice: There is a family that lives at 235 Misvik Loop that wants to come back to Kwigillingok as soon as their house is ready. They have the heat on and demobed the water tank, water heater, and expansion tank yesterday. Making a list of doghouses that will need to be set by Hog River; these will also need pads built. We have provided Hog River with drawings for where the doghouses need to be set. We sent one guy out to Bethel for medical. The electrician on-site is finishing rough in wiring on unit K14. Offloading fuel planes and freight planes. 
    • Delta Backhaul: DBH has one foreman, two operators, and three laborers on site. They will be removing snow, hauling fuel, and clearing debris. Additionally, the burn unit will be operations today, using the debris separate4d from the snow for burning. 
    • Hog River: Moving/leveling houses. Setting dog houses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 

    2/07/26

    • Cruz: Continuing to install pile on the boardwalk out to the raw water supply, Cruz is looking into getting more crew out here late this next week to start boardwalk installation, the auger bit is here and being used when needed, it appears we may be able to get ~20 per shift = 40 per day. 
    • Brice: Working on plumbing and heating in houses, will be checking the post office later today, still have some work at the clinic, sewer line at school is still not functioning and maintenance is on-site treating the sewage right now, appearing to still to frozen. 
    • Delta Backhaul: Currently only one laborer, three operators and a foreman on-site. Primary focus is on removing snow and clearing debris in boardwalk locations. DBH is actively working along the walkway area that requires replacement behind the burn unit. 
    • Hog River: Moving/leveling houses. Setting dog houses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 

    2/05/26

    • Cruz: Continuing to install pile on the boardwalk out to the raw water supply, 28 so far, expecting an auger bit on a flight this afternoon, it will speed things up. Unloading planes as needed. 
    • Brice: Continuing to assist with house repairs, heating plumbing, dog houses, water tanks, etc.
    • Delta Backhaul: Continuing with debris hauling and sorting in boardwalk areas behind the burn unit, the burn unit and the appliance crusher is operational, incinerating and appliance crushing, removing snow in boardwalk sections for replacement. 
    • Hog River: Moving/leveling houses. Setting dog houses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 

    Facilities Daily Report

      • Work performed by Hog River Construction. 
      • #K14: Performing general cleanup. 
      • #K15: Installed exterior beams; lifted building four feet high; cutting cribbing and pad materials. 
      • #K38: Started prepping for house move. 
      • Lifted and relocated one steam house and one small workshop. 
      • Continued skid steer storage housework. 
      • Performing plumbing assessments. 
      • Water plant: Currently filling water tank. 
      • Total of 21 team members on-site. 

      2/03/26

      • Cruz: PB's made it in last night and delivered material over to the run out to the raw water supply staging material at the run from the bridge out to the raw water supply, had to build out some snow across the creek for the PB's to get across sounds like Cruz found an auger bit to drill through the frost layer, still only getting about one per hour, also unloading planes when they come in starting a 24 hour shift now on helical installation. 
      • Brice: The sewer line leak was repaired and numerous leaks in the water system were identified and Brice got authorization to go in and fix the damage. Continuing housing maintenance and repair is ongoing, servicing heaters, restoring heat, doghouse repair, heat trace, and fixing plumbing issue the water treatment plant has resumed water production. Brice is fabricating a tank on a trailer with a 1" pump to assist in fuel logistics. 
      • Delta Backhaul: Incinerator is back up and running continuing to remove boardwalk in front of Cruz and expect to be down with that today and moving to another portion of boardwalk to clear out and take to the burn pile. 
      • Hog River: Moving/leveling houses. Setting dog houses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 

      Facilities Daily Report

        • #K02: Completing interior sheathing; skid steer storage structure work continued. 
        • #K15: House lifted, placed on skid, and ready for relocation. 
        • #K35: Performing interior finish painting. 
        • Water Plant: Intake line thawed; leak in water treatment plant currently being addressed. 
        • Total of 23 team members currently on-site. 

        2/02/26

        • Cruz: staging material at the run from the bridge out to the raw water supply, Cruz is actively trying to find an auger bit to drill through the frost layer, they found a softer spot today but are still only getting about one per hour, also unloading planes when they come in and will be unloading piston bullies when they arrive. 
        • Brice: the sewer line leak was repaired and numerous leaks in the water system were identified and Brice got authorization to go in and fix the damage. Housing maintenance and repair is ongoing, servicing heaters, restoring heat, doghouse repair, heat trace, and fixing plumbing issues. The washateria was down for a bit and an airlock in the pump was identified and fixed. The water treatment plant has resumed water production. Brice is fabricating a tank on a trailer with a 1" pump to assist in fuel logistics. 
        • Delta Backhaul: Incinerator is down until they get a bracket for the fuel filter, removing damaged boardwalk and taking to the burn pile. 
        • Hog River: Moving/leveling houses. Setting dog houses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 

        Facilities Daily Report

          • #K14: Framing completed for interior. 
          • #K15: Structure lifted 2.5 feet and preparation underway for relocation. Constructure 30 house pads. 
          • #K35: Interior finish painting continued. 
          • Water plant: Intake line thawed; leak in water treatment plant currently being addressed. 
          • Total of 18 team members are currently on-site. 

          2/01/26

          • Cruz: staging material at the run from the bridge out to the raw water supply, Cruz is actively trying to find an auger bit to drill through the frost layer, there may be one in Akiachak. 
          • Brice: Clinic water is on but cannot test until the sewer line is clear, sewer line leak has been repaired, but a fitting busted when it was water jetted, but flow is going to the lagoon. Plumbers and electricians are working on getting the fuel dispenser at the marina running, working on stairs and landing at the stand-alone teacher housing, finished insulating and installed a new thermostat there, working on insulating and heat tracing other houses/doghouses. 
          • Delta Backhaul: Getting the appliance crusher up and running, removing tundra mats in front of Cruz for helicals, hauling debris to the incinerator, DBC needs more debris before they start up the incinerator. 
          • Hog River: Moving/leveling houses. Setting dog houses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 

           

           

          3/03/26


          3/02/26


          3/01/26


          2/28/26


          2/27/26


          2/26/26


          2/25/26


          2/24/26


          2/23/26


          2/22/26


          2/21/26


          2/20/26


          2/19/26


           

          2/18/26


          2/17/26


          2/16/26


          2/15/26


          2/14/26


          2/13/26


          2/12/26


          2/11/26


          2/10/26


          2/08/26


          2/07/26


          2/05/26


          2/03/26


          2/02/26


          2/01/26