Kwigillingok: DOT&PF Emergency Repair Work
Kwigillingok: DOT&PF Emergency Repair Work
DOT&PF is providing updates for each community and has built tools to report damages and request assistance. This page will help you see real-time updates in your community for infrastructure repairs & road access, water & sanitation status, and local recovery progress & resources.
Reporting Damage: If your home, property, or infrastructure was damaged, please report it using our Damage Assessment Hub at: https://damage-assessment-2-akdot.hub.arcgis.com
Need materials or assistance: If your community hasn’t connected with DOT&PF yet, reach out to dot.ask@alaska.gov - we’ll help coordinate approvals and connect you to supplies quickly.
DOT&PF Emergency Response Manager: Amber Shumpert, amber.shumpert@alaska.gov, 907-322-0603.
Water and sewer updates: check Alaska DEC West Coast Storm.
Project Contacts
Construction Manager Jason Baxley 907.545.7361 | Construction Manager Hannah Counter 907.545.2262 | Emergency Response Manager Amber Shumpert 907.322.0603 |
Kwigillingok Operations Summary
5/12/26
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K03: Floor installation.
- #K07: C/O rotten beams; began setting posts and pads.
- #K28: Leveled fuel stands; began T1-11 repair.
- #K39: Built stairs and handrails.
- #K63: Interior sheeting.
- #K65: C/O back beam and re-level; built stairs.
- #K66: Painted trim.
- #K72: Built stairs and handrails.
- #K74: Painted and prepped floor.
- Total of 28 team members onsite.
5/11/26
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K03: Began flooring installation.
- #K07: Raised south end to elevation and began pad placement.
- #K13: Finished post bracing; built guardrail; ramp construction has been completed.
- #K14: Built handrails; raised and supported proch.
- #K39: Installed foam board under house.
- #K63: Completed vapor barrier installation; began roof repair.
- #K66: Painted trim.
- #K74: Completed primer; cross-bracing posts.
- Total of 26 team members onsite.
5/10/26
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K13: Completed post and pad installation with bracing. Raised the deck with temporary support and constructed stairs with handrails and a ramp to the lower level.
- #K39: Installed foam board insulation beneath the structure.
- #K63: Applied primer coat to interior walls.
- #K66: Continued interior trim installation.
- #K74: Completed wall insulation and began vapor barrier installation.
- General: Clean up across job sites.
- Total of 23 team members onsite.
5/09/26
- Cruz: Demobed from site.
- Helical piles to date: 2,486/Linear feet of boardwalk: 8,200.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: Demobed from site.
- Number of helicals installed to date: 602.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K13: Setting posts and pads with bracing.
- #K63: Completed furring out walls and began insulating.
- #K64: Insulated the floor and installed underlayment.
- #K65: Stripped interior walls and flooring.
- #K74: General cleaning in preparation for paint.
- Continuing boardwalk repairs.
- Airport cargo transportation operations.
- Total for 23 team members onsite.
5/08/26
- Cruz: Demobed from site.
- Helical piles to date: 2,486/Linear feet of boardwalk: 8,200.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: Demobed from site.
- Number of helicals installed to date: 602.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K13: Worked on post and pad foundation.
- #K63: Furring out walls; Toyo stove and fuel stand installation.
- #K64: Installed floor joists and underlayment insulation (50% complete).
- #K74: General clean up around the house.
- Continuing boardwalk repairs.
- Airport and cargo transportation operations.
- Total of 26 team members onsite.
5/07/26
- Cruz: Demobed from site.
- Helical piles to date: 2,486/Linear feet of boardwalk: 8,200.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: Demobed from site.
- Number of helicals installed to date: 602.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K03: Began preparing for upcoming floor installation.
- #K13: Completed installation of new pads and ready for final leveling and house placement.
- #K18: Completed floor insulation activities.
- #K66: Finished all interior painting work.
- #K74: Continued installing interior wall sheeting.
- General: Repaired the boardwalk between the school and the airport and maintained ongoing airport cargo transportation.
- Total of 25 team members onsite.
5/05/26
- Cruz: Demobing from site.
- Helical piles to date: 2,486/Linear feet of boardwalk: 8,200.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: Demobed from site.
- Number of helicals installed to date: 602.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K13: Cribs were staged, the structure was lifted, and ramp repair work began.
- #K18: Stair and railing construction progressed, re-insulation was completed, and sheeting commenced.
- #K20: Interior and exterior cleanup was completed.
- #K41: Priming was finalized and finish-coat application began.
- #K42: Painting completed.
- #K64: Insulation and skirting were removed, dry-out activities began, the Toyo stove was installed, re-insulation was completed, and sheeting commenced.
- #K65: Re-insulation completed and began sheeting.
- #K66: Floor insulation and vapor barrier installation were completed, and interior sheeting began.
- #K68: Roofing and T1-11 exterior sheathing were installed.
- #K68: Roofing and T1-11 exterior sheeting were installed.
- Total of 24 team members onsite.
5/04/26
- Cruz: Demobed from site.
- Helical piles to date: 2,486/Linear feet of boardwalk: 8,200.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: Demobing from site.
- Number of helicals installed to date: 602.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K17: Staged cribs to raise the house.
- #K39: Installed wall sheeting and applied house wrap.
- #K41 and #K42: Interior painting work.
- #K64: Finished post and pad foundation with bracing.
- #K68: Installed roofing and T1-11 exterior sheeting.
- #K77: Built stairs and installed handrails.
- General: Cleared snow at the lagoon to establish an access path for sewer transfer and hauled tundra mats from the lake to the gravel road.
- Total of 23 team members onsite.
5/03/26
- Cruz: Demobing from site.
- Helical piles to date: 2,486/Linear feet of boardwalk: 8,200.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: Demobing from site.
- Number of helicals installed to date: 602.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
5/02/26
- Cruz: Demobing from site.
- Helical piles to date: 2,486/Linear feet of boardwalk: 8,200.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: Demobing from site.
- Number of helicals installed to date: 602.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K17: Completed installation of foam board.
- #K18: Installed interior trim.
- #K41: Completed interior painting.
- #K42: Completed interior painting.
- #K64: Set post and pad foundation.
- #K68: Installed wall insulation and applied vapor barrier.
- #K75: Installed house wrap and began placing foam board beneath the structure.
- #K77: Completed house wrap and foam installation under the building; finalized bracing and cleaned the work area.
- General: Continued transporting airport cargo.
- Total of 24 team members onsite.
5/01/26
- Cruz: Finished boardwalk at village store. Assisted/supported other contractors. Transitioned into demob; gathered tools, equipment, and supplies. Demobing over the weekend.
- Helical piles to date: 2,486/Linear feet of boardwalk: 8,200.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: Working on punch list items. Planned demob for Saturday.
- Number of helicals installed to date: 602.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K18: Skirted the house to allow structure to dry out.
- #K39: Insulated the floor.
- #K40: Insulated and sheeted flooring beneath the house.
- #K41 and #K42: Painted interior walls.
- #K64: Continued lifting and replacing damaged beam.
- #K77: Set final post and pad foundation with bracing.
- General: Continued transporting airport cargo and hauled cribs from the water reservoir.
- Total of 25 team members onsite.
4/29/26
- Cruz: Finished boardwalk at village store. Assisted/supported other contractors. Transitioned into demob; gathered tools, equipment, and supplies.
- Helical piles to date: 2,486/Linear feet of boardwalk: 8,157.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: Handrail from bridge to subdivision complete. Worked on punch list items. Planned demobilization for Saturday.
- Number of helicals installed to date: 602.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K03: Finished stripping the wet floor.
- #K16: Installed insulation and sheeting; work is 50% complete.
- #K41: Began painting interior walls and continued installing interior trim.
- #K42: Completed interior trim installation and prepared surfaces for paint.
- #K65: Continued post and pad foundation work; progress at 75%.
- #K79: Completed the post and pad installation on the south end.
- General: Transported cargo from airport and staged materials.
- Total of 25 team members onsite.
4/28/26
- Cruz: Finished boardwalk at village store. Assisted/supported other contractors. Transitioned into demob; gathered tools, equipment, and supplies.
- Helical piles to date: 2,486/Linear feet of boardwalk: 8,117.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: Handrail from bridge to subdivision complete. Worked on punch list items. Planned demobilization for Saturday.
- Number of helicals installed to date: 602.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K03: Removed flooring and cleaned out interior.
- #K39: Demolition of existing floor insulation.
- #K41: Completed installing AVC plywood on interior walls.
- #K42: Installed interior trim.
- #K65: Set post and pad.
- #K68: Worked on roof repairs.
- #K79: Set the south side post and pad.
- General: Transported cargo from the airport.
- Total of 26 team members onsite.
4/27/26
- Cruz: Working on boardwalk sections throughout the village. Installed saddles, sleepers, and deck throughout (village store parking, near Bill's store, etc..).
- Helical piles to date: 2,486/Linear feet of boardwalk: 7,847.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: All curbs installed. All approach ramps installed near marina. Worked on installing handrail from bridge to subdivision. Still screwing down deck; some of the areas needing 5" screws was temporarily screwed down with shorter screws. Still putting through-colts on curb/rail.
- Number of helicals installed to date: 602.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K03: Built and installed stairs.
- #K38: Finished sheeting beneath the house with CDX.
- #K39: Demo interior wall sheeting and removed wet insulation.
- #K40: Demo the floor.
- #K41: Installed ACX plywood on the interior.
- #K65: Installed post and pad foundation.
- #K72: Built and installed stairs.
- #K77: Rim-joist repairs and began elevation lifting.
- #K79: Installed post and pad foundation.
- General: Conducted water-plant operations, cleaned work areas, and hauled trash.
- Total of 22 team members onsite.
4/26/26
- Cruz: Working on boardwalk sections throughout the village. Installed saddles, sleepers, and deck throughout (village store parking, near Bill's store, etc..).
- Helical piles to date: 2,486/Linear feet of boardwalk: 7,500.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: Continued to install boardwalk deck. Continued ramp installation. Continued installing curbs and rails; started Monday. Debris disposal.
- Number of helicals installed to date: 602.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
4/25/26
- Cruz: Working on boardwalk sections throughout the village. Installed saddles, sleepers, and deck throughout (village store parking, near Bill's store, etc..).
- Helical piles to date: 2,486/Linear feet of boardwalk: 7,467.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: Continued to install boardwalk deck. Continued ramp installation. Continued installing curbs and rails; started Monday. Debris disposal.
- Number of helicals installed to date: 602.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K03: Continued work on the post and pad structural support.
- #K38: Installed insulated floor with modalized MCDX plywood for the house.
- #K64: Removed interior finishes and extract saturated insulation.
- General: Hauled debris and garbage to the dump.
- Total of 21 team members onsite.
4/24/26
- Cruz: Working on boardwalk sections throughout the village. Installed saddles, sleepers, and deck throughout (village store parking, near Bill's store, etc..).
- Helical piles to date: 2,486/Linear feet of boardwalk: 7,437.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: Continued to install boardwalk deck. Continued ramp installation. Continued installing curbs and rails; started Monday.
- Number of helicals installed to date: 602.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K03 & #K39: Worked on post and pad structural support.
- #K38 & #K64: Demo of interior sheeting and saturated insulation.
- #K72: Completed installation of sheeting, house wrap, and foam board under the structure.
- Total of 23 team members onsite.
4/23/26
- Cruz: Finished boardwalk near 10-unit housing; now working at several small locations throughout village (village store parking, near Bill's store, etc..).
- Helical piles to date: 2,495/Linear feet of boardwalk: 7,267.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: Continued to install boardwalk deck. Continued ramp installation. Continued installing curbs and rails; started Monday. Disposing debris.
- Number of helicals installed to date: 602.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K39: Demolished interior and removed insulation.
- #K41: Installed sheeting beneath the floor.
- #K42: CDX plywood installed.
- #K72: Floor insulated and CDX plywood installation started.
- 21 team members onsite.
4/22/26
- Cruz: Installing boardwalk deck out near church; ~1/4 complete. Installing helicals at 10-unit housing. Moving layout yard to more suitable area to stage material during warmer temperature. Assisted Hog River moving/rotating a house.
- Helical piles to date: 2,495/Linear feet of boardwalk: 6,808.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation.
- Number of helicals installed to date: 594.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K07: Set the house onto the skid, plowed an access trail to the new location, towed the structure to the new site, and removed the skid.
- #K38: Began demolishing interior wall sheeting and removed wet insulation.
- #K39: Installed post and pad foundation with cross-bracing.
- #K42: Installed floor insulation and began sheeting.
- #K66: Installed interior insulation.
- #K72: Demolished interior wall sheeting and removed water-damaged insulation.
- #K74: Installed vapor barrier.
- #K77: Installed insulated flooring, placed CDX plywood, added foam board, and completed foam-board installation beneath the house.
- Other: Moved three steam houses back to owners' lots.
- Total of 20 team members onsite.
4/21/26
- Cruz: Installing boardwalk deck out near church; ~1/4 complete. Installing helicals at 10-unit housing. Moving layout yard to more suitable area to stage material during warmer temperature. Assisted Hog River moving/rotating a house.
- Helical piles to date: 2,495/Linear feet of boardwalk: 6,528.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation.
- Number of helicals installed to date: 581.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
4/20/26
- Cruz: Installing boardwalk deck out near church; ~1/4 complete. Installing helicals at 10-unit housing. Moving layout yard to more suitable area to stage material during warmer temperature. Assisted Hog River moving/rotating a house.
- Helical piles to date: 2,495/Linear feet of boardwalk: 5,979.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation.
- Number of helicals installed to date: 565.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K07: Setting unit on the skid.
- #K42: Installed interior sheeting.
- #K63: Continued stripping interior.
- #K66: Furring out walls.
- #K74: Installed insulation and vapor barrier.
- Total of 19 team members onsite.
4/19/26
- Cruz: Installing boardwalk deck out near church; ~1/4 complete. Installing helicals at 10-unit housing. Moving layout yard to more suitable area to stage material during warmer temperature. Assisted Hog River moving/rotating a house.
- Helical piles to date: 2,495/Linear feet of boardwalk: 5,979.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation.
- Number of helicals installed to date: 565.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
4/18/26
- Cruz: Installing boardwalk deck out near church; ~1/4 complete. Installing helicals at 10-unit housing. Moving layout yard to more suitable area to stage material during warmer temperature. Assisted Hog River moving/rotating a house.
- Helical piles to date: 2,565/Linear feet of boardwalk: 5,900.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation.
- Number of helicals installed to date: 570.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K07: Prepared for setting the structure onto the sled.
- #K63: Dried the structure and repaired roof damage.
- #K66: Completed the demolition of the interior walls and relocated heater into the house.
- #K74: Demolished walls and repaired roof damage.
- General Tasks: Lifted and returned shed to its proper position, hauled materials from the airport, and repaired the skid.
- Total of 21 team members are onsite.
4/17/26
- Cruz: Installing boardwalk deck out near church; ~1/4 complete. Installing helicals at 10-unit housing. Moving layout yard to more suitable area to stage material during warmer temperature. Assisted Hog River moving/rotating a house.
- Helical piles to date: 2,545/Linear feet of boardwalk: 5,800.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation.
- Number of helicals installed to date: 560.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K07: Continued lifting the structure.
- #K08: Lifted the structure to the required height.
- #K63: Demolished exterior walls.
- #K66: Removed interior wall sheathing and wet insulation; completed demolition of exterior walls and the bathroom.
- #K74: Installed plywood and foam insulation beneath the structure.
- General Tasks: Extended the skid.
- Total of 21 team members are onsite.
4/16/26
- Cruz: Installing boardwalk deck out near church; ~1/4 complete. Installing helicals at 10-unit housing. Moving layout yard to more suitable area to stage material during warmer temperature. Assisted Hog River moving/rotating a house.
- Helical piles to date: 2,495/Linear feet of boardwalk: 5,739.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation.
- Number of helicals installed to date: 548.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K07: Raised the house, installed I-beams underneath, and completed sled preparation.
- #K41: Continued vapor barrier work; assisted with kitchen tasks.
- #K66: Demolished exterior walls.
- #K74: Insulated the floor and began sheeting under the house.
- General Tasks: Welded extension onto sled; pulled water from the reservoir to the water plant.
- Total of 23 team members onsite.
4/15/26
- Cruz: Installing boardwalk deck out near church; ~1/4 complete. Installing helicals at 10-unit housing. Moving layout yard to more suitable area to stage material during warmer temperature. Assisted Hog River moving/rotating a house.
- Helical piles to date: 2,476/Linear feet of boardwalk: 5,172.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation.
- Number of helicals installed to date: 526.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K07: Continued elevating the house to position the sled underneath and removed the porch.
- #K41: Continued installing vapor barrier and exterior sheeting.
- #K63: Installed plywood and foam board insulation beneath the house.
- #K74: Stripped interior walls and flooring.
- General tasks: Added 23 feet to the winter skid.
- Total of 20 team members onsite.
4/14/26
- Cruz: Installing boardwalk deck out near church; ~1/4 complete. Installing helicals at 10-unit housing. Moving layout yard to more suitable area to stage material during warmer temperature. Assisted Hog River moving/rotating a house.
- Helical piles to date: 2,406/Linear feet of boardwalk: 4,932.
- Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation.
- Number of helicals installed to date: 505.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K07: Began lifting on west side of house.
- #K15: Finished post, pad and bracing.
- #K35: C/O lift pump.
- #K39: Post and pad installation; built pads and installed beams.
- #K42: Tyvek under floor joists; continued sheeting installation.
- #K44: Fix Toyo heater; demobilized boiler and installed fuel tank.
- #K52: Finished how water indirect.
- #K63: Repaired roof, prepped, and installed new foam; cleaned out and prepped for stripping; insulated floor and sheeted 40% under house; continued stripping walls and inside flooring.
- #K66: Cleaned up trash and loose insulation.
- #K72: Continued stripping walls and inside flooring.
- #K74: Skirting around house with reinforced poly.
- Additional task: Moved five doghouses and one boat from across the river.
- Additional general tasks: Conducted boat/steam bath retrieval from across the river.
- Total of 20 team members onsite.
4/13/26
- Cruz: Installing boardwalk deck out near church; ~1/4 complete. Installing helicals at 10-unit housing. Moving layout yard to more suitable area to stage material during warmer temperature. Assisted Hog River moving/rotating a house.
- Helical piles to date: 2,399/Linear feet of boardwalk: 4,712.
- Brice/STG: Brice continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation.
- Number of helicals installed to date: 505.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K15: Post and pad installation is ~50% complete.
- #K39: Relocated operations to the new location and removed the skid.
- #K41: Interior wall sheeting in progress.
- #K52: Completed plumbing repairs for the toilet.
- #K58: Pressure-tested lines, repaired faucet, and installed the hot water heater.
- #K63: Performed roof repairs and completed installation of the stair handrails.
- #K66: Installed R-Tek underlayment.
- #K72: Began interior cleaning and surface stripping.
- #K77: Initiated drying of joists.
- Additional general tasks: Boat/steam bath retrieval from across the river.
- Total of 29 team members onsite.
4/12/26
- Cruz: Continued installation of boardwalk decking out to sewage lagoon. Installed sleepers out near church; ~1/3 complete. Cleared snow and debris at 10-unit housing. Completed layouts at village store and Bill's house. Moved layout yard to more suitable area to stage material during warmer temperature.
- Helical piles to date: 2,256/Linear feet of boardwalk: 4,622.
- Brice/STG: Brice continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation.
- Number of helicals installed to date: 456.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
4/11/26
- Cruz: Helical pile out near church is complete. Continued installing boardwalk decking out to sewage lagoon. Installed sleepers out near church (~1/3 complete). Clearing snow debris at 10-unit housing. Completed layouts at village store and Bill's house. Moving layout yard to more suitable area to stage material during warmer temperatures.
- Helical piles to date: 2,256/Linear feet of boardwalk: 4,622.
- Brice/STG: Brice continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation.
- Number of helicals installed to date: 456.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K39: Moved house to new location: two miles.
- #K42: Continued sheeting.
- #K58: Installed new toilet, added glycol to boiler system, replaced shower valve.
- #K62: Fixed water line leak and serviced boiler.
- #K63: Finished stairs, added roof repair, repaired wall on bathroom addition.
- #K64: Insulated wall and began vapor barrier.
- #K66: Finished installing Tyvek and underlayment; began foam board installation.
- #K72: Finished post and pad with bracing; cleaned out and prepped for stripping.
- #K74: Built and installed fuel stand.
- #K77: Continued drying out floor.
- General: Pre-fabricated parts for septic repair.
- Total of 30 team members onsite.
4/10/26
- Cruz: Helical pile out near church is complete. Continued installing boardwalk decking out to sewage lagoon. Installed sleepers out near church (~1/3 complete). Clearing snow debris at 10-unit housing. Completed layouts at village store and Bill's house. Moving layout yard to more suitable area to stage material during warmer temperatures.
- Helical piles to date: 2,903/Linear feet of boardwalk: 4,204.
- Brice/STG: Brice continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation.
- Number of helicals installed to date: 447.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K38: Completed post and pad work with full structural bracing.
- #K39: House set on skid and prepared for relocation.
- #K42: Installed wall insulation, completed vapor barrier, and initiated exterior sheeting.
- #K52: Completed boiler repairs.
- #K57: Installed new fuel tank and filter system.
- #K62: Repaired shower valve, adjusted toilet flange, and completed boiler repairs.
- #K63: Installed stair handrails and removed saturated attic insulation.
- #K64: Cleaned and prepared for interior wall stripping.
- #K65: Relocated structure and placed in the designated new location.
- #K66: Installed floor insulation and Tyvek, initiated sheeting, installed stair handrails, and removed snow from attic space.
- #K72: Raised house and initiated post and pad work (50% complete).
- #K74: Installed stair handrails, fascia repairs, siding repairs, porch demo, stair construction, and initiated roof repairs.
- #K77: Continued drying flooring system.
- Additional general tasks: Pre-fabricated parts for upcoming house repairs and continued cargo transportation from the airport.
- Total of 32 team members onsite.
4/09/26
- Cruz: Helical pile out near church is complete. Continued installing boardwalk decking out to sewage lagoon. Installed sleepers out near church (~1/3 complete). Clearing snow debris at 10-unit housing. Completed layouts at village store and Bill's house. Moving layout yard to more suitable area to stage material during warmer temperatures.
- Helical piles to date: 2,903/Linear feet of boardwalk: 4,204.
- Brice/STG: Brice continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation.
- Number of helicals installed to date: 422.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K38: 75% complete with post and pad work.
- #K39: Began lifting preparation to move; repairing beams.
- #K41: Installed second Toyo stove; reinstalled floor insulation.
- #K42: Installed second Toyo stove; reinstalled floor insulation; removed insulation from walls three feet up.
- #K57: Installed new fuel tank and filter.
- #K62: Repaired boiler and prepared for water; air-tested lines.
- #K63: Installed Toyo stove; continued drying out.
- #K64: Cleaned out and prepared for interior wall stripping.
- #K65: Moved to new location; constructed ramp at new site.
- #K66: Installed Toyo stove; prepped floor and began insulation installation.
- #K74: Continued T1-11 repairs; finished stairs; began cleaning around house.
- #K77: Continued drying out.
- Additional General Tasks: Continued cargo transportation from the airport.
- Total of 32 team members onsite.
4/08/26
- Cruz: Helical pile out near church is complete. Continued installing boardwalk decking out to sewage lagoon. Installed sleepers out near church (~1/3 complete). Clearing snow debris at 10-unit housing. Completed layouts at village store and Bill's house. Moving layout yard to more suitable area to stage material during warmer temperatures.
- Helical piles to date: 1,908/Linear feet of boardwalk: 4,204.
- Brice/STG: Brice continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation.
- Number of helicals installed to date: 398.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K03: Removed I-beams and set the house on cribs.
- #K38: Began post and pad installation.
- #K41: Installed Toyo stove; reinstalled floor insulation.
- #K42: Installed Toyo stove; reinstalled floor insulation; removed insulation from walls three feet up.
- #K57: Restored running water; general support: hauled 16 boats from walls three feet up.
- #K62: Repaired boiler and fixed thermostat.
- #K63: Continued drying out the structure.
- #K65: Began lifting structure for relocation to new site.
- #K66: Completed roof repairs.
- #K74: Began T1-11 repairs; built stairs; began cleaning around the house.
- #K77: Continued structural dry out.
- #K79: Built foundation pads.
- Additional general tasks: Hauled seven doghouses from across the river; installed fuel pump at marina; transported cargo from the airport.
- Total of 32 team members onsite.
4/07/26
- Cruz: One excavator drove piles out to sewage lagoon. Continued installing boardwalk sleepers and support brackets out to sewage lagoon. Continued cutting piles and installing saddles out near community church; ~1/3 complete. Boardwalk out to fresh water source is near completion.
- Helical piles to date: 1,800/Linear feet of boardwalk: 3,900.
- Brice/STG: Brice continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation.
- Number of helicals installed to date: 385.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K03: Removed the skid from underneath the house.
- #K38: Hauled material for post and pad.
- #K41: Began re-installing floor insulation.
- #K42: Began re-installing floor insulation; removed insulation from walls three feet up.
- #K46: Plumbed in the hot water heater.
- #K57: Repaired water service lines and continued work to restore running water in the house.
- #K63: Finished stripping insulation from the floor and skirted the area for drying; continued dry-out operations.
- #K66: Completed T1-11 installation and repairs.
- #K74: Began T1-11 repairs; began cleaning around the house.
- #K77: Stripped insulation and skirting and began dry-out.
- #K79: Began repairs to floor joists and rim joists; fabricated pads for the foundation.
- General: Cargo transportation from the airport.
- Total of 31 team members are onsite.
4/06/26
- Cruz: One excavator drove piles out to sewage lagoon. Continued installing boardwalk sleepers and support brackets out to sewage lagoon. Continued cutting piles and installing saddles out near community church; ~1/3 complete. Boardwalk out to fresh water source is near completion.
- Helical piles to date: 1,772/Linear feet of boardwalk: 3,812.
- Brice/STG: Brice continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation.
- Number of helicals installed to date: 377.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
4/05/26
- Cruz: One excavator drove piles out to sewage lagoon. Continued installing boardwalk sleepers and support brackets out to sewage lagoon. Continued cutting piles and installing saddles out near community church; ~1/3 complete. Boardwalk out to fresh water source is near completion.
- Helical piles to date: 1,748/Linear feet of boardwalk: 3,545.
- Brice/STG: Brice continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation.
- Number of helicals installed to date: 367.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K03: Moved house to new location.
- #K42: Completed drying out and stripping walls.
- #K46: Plumbed in hot water heater.
- #K57: Repaired water service line and continued working on restoring running water to the house.
- #K63: Finished stripping insulation from the floor and skirted the area for drying.
#K64: Removed the skid from underneath the house. - #K66: Continued installation of repair of T1-11.
- #K74: Dried out the floor and began cleaning debris.
- #K77: Completed bracing.
- #K79: Making pads for the foundation.
- Total of 30 team member onsite.
4/04/26
- Cruz: One excavator drove piles out to sewage lagoon. Continued installing boardwalk sleepers and support brackets out to sewage lagoon. Continued helical installation out new community church. Cleared and laid out helical installations near village council building. Boardwalk out to fresh water source is near completion.
- Helical piles to date: 1,738/Linear feet of boardwalk: 3,392.
- Brice/STG: Brice continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation.
- Number of helicals installed to date: 357.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K42: Finished stripping interior and continued drying out the floor joists.
- #K46: Plumbed in hot water heater.
- #K57: Repaired water service lines and continued work to restore running water.
- #K64: Moved structure into its new position.
- #K66: Completed dry-out, replaced soggy attic insulation, installed T1-11, and built stairs.
- #K74: Continued drying out floor and began interior debris cleanup.
- #K77: Completed post and pad work and reached 50 % completion on bracing.
- #K79: Constructed pads for foundation.
- Total of 30 team members onsite.
4/03/26
- Cruz: One excavator drove piles out to sewage lagoon. Continued installing boardwalk sleepers and support brackets out to sewage lagoon. Continued helical installation out new community church. Cleared and laid out helical installations near village council building. Boardwalk out to fresh water source is near completion.
- Helical piles to date: 1,732/Linear feet of boardwalk: 3,131.
- Brice/STG: Brice continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation.
- Number of helicals installed to date: 354.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K42: Stripped interior, removed wet insulation, and continued drying out the structure.
- #K46: Began installation of the Toyo unit.
- #K57: Repaired water service lines and continued working to restore running water.
- #K64: Relocated house from across the river.
- #K66: Continued drying out the structure, removed saturated attic insulation, and repaired siding.
- #K77: Post and pad foundation work (50% complete).
- #K79: Fabricated and installed foundation pads.
- #K74: Continued drying out.
- Total of 28 team members onsite.
4/02/26
- Cruz: One excavator drove piles out to sewage lagoon. Continued installing boardwalk sleepers and support brackets out to sewage lagoon. Continued helical installation out new community church. Cleared and laid out helical installations near village council building. Boardwalk out to fresh water source is near completion.
- Helical piles to date: 1,719/Linear feet of boardwalk: 3,132.
- Brice/STG: Brice continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation.
- Number of helicals installed to date: 341.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K41: Stripped interior, removed wet insulation, dried out.
- #K46: Began installation of Toyo.
- #K57: Repaired water service lines; worked toward restoring running water.
- #K63: Finished post and pad foundation; made pads for foundation.
- #K64: Lifted house two feet on south end.
- #K66: Continued drying out; removed soggy attic insulation.
- #K74: Wrapped house with reinforced poly; began drying out.
- #K77: Began working on post and pad foundation.
- Total of 28 team members onsite.
4/01/26
- Cruz: One excavator drove piles out to church.
- Helical piles to date: 1,689/Linear feet of boardwalk: 2,932.
- Brice/STG: Brice continued to monitor critical infrastructure. Two linemen will come in today to begin bringing service to houses Hog River retrieved and relocated.
- Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Removed snow and temporary boardwalk in path of helical installation.
- Number of helicals installed to date: 328.
- Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
Facilities Daily Report
- Work performed by Hog River Construction.
- #K41: Stripped interior, removed wet insulation, dried out.
- #K57: Repaired water service lines, worked on getting running water into house.
- #K63: Continued post and pad installation (90% completed); make pads for foundation.
- #K66: Lifting storage shed to return next to house; stripped floor insulation, skirted house, and began drying out.
- #K72: Moved house into new position from across river, removed winter skid from underneath; moved shed from across the river.
- #K74: Stripped floor insulation, skirted house with plywood.
- Total of 25 team members onsite.
5/08/26
5/02/26
5/01/26
4/29/26
4/28/26
4/27/26
4/26/26
4/25/26
4/24/26
4/23/26
4/22/26
4/21/26
4/20/26
4/19/26
4/18/26
4/17/26
4/16/26
4/15/26
4/14/26
4/13/26
4/12/26
4/11/26
4/10/26
4/09/26
4/08/26
4/07/26
4/06/26
4/05/26
4/04/26
4/03/26
4/02/26
4/01/26