Kwigillingok Operations Summary

3/27/26 

  • Cruz: One excavator drove piles out to sewage lagoon. Continued installation of boardwalk sleepers, support brackets, and decking out to the sewage lagoon. Boardwalk out to freshwater source near completion. 
  • Helical piles to date: 1,554/Linear feet of boardwalk: 2,892. 
  • Brice/STG: Brice continued to monitor critical infrastructure. Two linemen will come in today to begin bringing service to houses Hog River retrieved and relocated. 
  • Delta Backhaul: 24/7 helical installation starting at southeast end of school. They're using one SANY excavator to drive helicals. Began installing sleepers and sway bars with hardware. 
  • Number of helicals installed to date: 185. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K15: Began repairing damaged and missing siding. 
  • #K35: General cleaning, service trash pump and water delivery. 
  • #K41: Removed frozen floor insulation and skirt house for dry out; continued stripping water-damaged walls with insulation. 
  • #K42: Removed flooring insulation and began drying; began stripping interior containing wet insulation.
  • #K46: Began repairing boiler and pressure-testing water lines. 
  • #K62: Got heat operating to test water lines. 
  • #K74: Finished post and pad installation, along with bracing. 
  • Total of 29 team members onsite. 

3/26/26 

  • Cruz: One excavator drove piles out to sewage lagoon. Continued installation of boardwalk sleepers, support brackets, and decking out to the sewage lagoon. Boardwalk out to freshwater source near completion. 
  • Helical piles to date: 1,534/Linear feet of boardwalk: 2,792. 
  • Brice/STG: Brice continued to monitor critical infrastructure. Two linemen will come in today to begin bringing service to houses Hog River retrieved and relocated. 
  • Delta Backhaul: 24/7 helical installation starting at southeast end of school. They're using one SANY excavator to drive helicals. Began installing sleepers and sway bars with hardware. 
  • Number of helicals installed to date: 161. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K02: Completed repairs of damaged and missing siding. 
  • #K15: Began repairing damaged and missing siding. 
  • #K35: General kitchen cleanup; plumbed in second wash bay to make it operational. 
  • #K41: Continued stripping water-damaged walls with insulation.
  • #K42: Removed flooring insulation; began stripping interior with wet insulation; installed Toyo stove and new fuel stand with tank. 
  • #K54: Repaired hot water heater and began boiler troubleshooting. 
  • #K57: Began boiler troubleshooting and performed water line testing for repairs. 
  • #K63: Raised house to remove skid from underneath. 
  • #K74: Post and pad installation (80% complete). 
  • Total of 27 team members onsite. 

3/25/26 

  • Cruz: One excavator drove piles out to sewage lagoon. Continued installation of boardwalk sleepers, support brackets, and decking out to the sewage lagoon. Boardwalk out to freshwater source near completion. 
  • Helical piles to date: 1,504/Linear feet of boardwalk: 2,592. 
  • Brice/STG: Brice continued to monitor critical infrastructure. Two linemen will come in today to begin bringing service to houses Hog River retrieved and relocated. 
  • Delta Backhaul: 24/7 helical installation starting at southeast end of school. They're using one SANY excavator to drive helicals. Began installing sleepers and sway bars with hardware. 
  • Number of helicals installed to date: 121. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K02: Completed sheeting the porch and back wall. 
  • #K35: Installed heat trace and restored water service to operational status. 
  • #K41: General cleaning of the house in prep for interior stripping. 
  • #K42: Began interior stripping, including removal of wet insulation. 
  • #K54: Repaired hot water heater and began troubleshooting the boiler. 
  • #K63: Relocated the house from across the river approximately three miles to the new site. 
  • #K74: Completed remaining post and pad installation. 
  • Total of 27 team members are onsite. 

3/24/26 

  • Cruz: One excavator drove piles out to sewage lagoon. Continued installation of boardwalk sleepers, support brackets, and decking out to the sewage lagoon. Boardwalk out to freshwater source near completion. 
  • Helical piles to date: 1,479/Linear feet of boardwalk: 2,452. 
  • Brice/STG: Brice continued to monitor critical infrastructure. Two linemen will come in today to begin bringing service to houses Hog River retrieved and relocated. 
  • Delta Backhaul: 24/7 helical installation starting at southeast end of school. They're using one SANY excavator to drive helicals and using the MT100 to remove snow in the helical installation path. 
  • Number of helicals installed to date: 66. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K02: Sheeted the porch with siding. 
  • #K35: General cleaning. 
  • #K41: Removed and disposed of debris. 
  • #K42: General cleaning and preparation for interior stripping. 
  • #K48: Repaired the hot water heater and completed plumbing connections. 
  • #K63: Positioned house on a skid and ready to be moved. 
  • #K66: Completed post and pad foundation installation. 
  • #K74: Began post and pad foundation installation. 
  • #K35: Plumbed in the septic tank and restored water flow. 
  • Total of 28 team members onsite. 

3/23/26 

  • Cruz: One excavator drove piles out to sewage lagoon. Continued installation of boardwalk sleepers, support brackets, and decking out to the sewage lagoon. Boardwalk out to freshwater source near completion. 
  • Helical piles to date: 1,455/Linear feet of boardwalk: 2,352. 
  • Brice/STG: Brice currently has one mechanical worker with the purpose of monitoring critical infrastructure. They are working on houses that they have parts for on-hand. They will continue to fix houses that they already have parts for and were planned to do. They are also waiting for parts to finalize repairs to washeteria that were ordered back in December. 
  • Delta Backhaul: 24/7 helical installation starting at southeast end of school. They're using one SANY excavator to drive helicals and using the MT100 to remove snow in the helical installation path. 
  • Number of helicals installed to date: 64. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K35: General cleaning. 
  • #K48: Troubleshoot heater and repaired water lines. 
  • #K63: Lifted house in preparation for moving. 
  • #K66: Constructed foundation posts and pads. 
  • Janlynn's house: Working on insulation. 
  • Total of 23 team members onsite. 

3/22/26 

  • Cruz: One excavator drove piles out to sewage lagoon. Continued installation of boardwalk sleepers, support brackets, and decking out to the sewage lagoon. Boardwalk out to freshwater source near completion. 
  • Helical piles to date: 1,450/Linear feet of boardwalk: 2,152. 
  • Brice/STG: Brice currently has one mechanical worker with the purpose of monitoring critical infrastructure. They are working on houses that they have parts for on-hand. They will continue to fix houses that they already have parts for and were planned to do. They are also waiting for parts to finalize repairs to washeteria that were ordered back in December. 
  • Delta Backhaul: 24/7 helical installation starting at southeast end of school. They're using one SANY excavator to drive helicals and using the MT100 to remove snow in the helical installation path. 
  • Number of helicals installed to date: 60. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K32: General cleaning. 
  • #K66: Installed foundation post and pads. 
  • Teacher housing: Transported the building across the river, positioned it by the school, and removed the skid from underneath. 
  • Janlynn's House: Installed insulation and vapor barrier. 
  • Total of 24 team members onsite. 

3/21/26 

  • Cruz: One excavator drove piles out to sewage lagoon. Continued installation of boardwalk sleepers, support brackets, and decking out to the sewage lagoon. Boardwalk out to freshwater source near completion. 
  • Helical piles to date: 1,450/Linear feet of boardwalk: 2,152. 
  • Brice/STG: Brice currently has one mechanical worker with the purpose of monitoring critical infrastructure. 
  • Delta Backhaul: 24/7 helical installation starting at southeast end of the school. They're using one SANY excavator to drive helicals. Delta was having mechanical issues with various equipment. Due to weather, boardwalk progress has been minimal.
  • Number of helicals installed to date: 58. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

3/20/26 

  • Cruz: One excavator drove piles out to sewage lagoon. Continued installation of boardwalk sleepers, support brackets, and decking out to the sewage lagoon. Boardwalk out to freshwater source near completion. 
  • Helical piles to date: 1,450/Linear feet of boardwalk: 2,152. 
  • Brice/STG: Brice currently has one mechanical worker with the purpose of monitoring critical infrastructure. 
  • Delta Backhaul: 24/7 helical installation starting at southeast end of the school. They're using one SANY excavator to drive helicals. SANY mechanics repaired one of two downed excavators. The remaining downed SANY excavator needs a new motor.
  • Number of helicals installed to date: 58. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

3/17/26 

  • Cruz: Continued installing helical piles. Continuing boardwalk construction. 
  • 25 helical piles installed yesterday; one excavator pre-drilling with auger built past the frozen layer. 
  • Helical Piles to date: 1,450/Linear feet of boardwalk: 1,892. 
  • Brice/STG: Critical infrastructure checks. 
  • Delta Backhaul: Continued installing helical piles, removed snow and set up/repaired equipment. Five helical piles installed yesterday. The temporary boardwalk was removed mostly intact and stacked for cribbing use. Waiting on quick-connects for the second power head. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K32: Paneled the interior and installed vapor barrier. 
  • #K35: Prepared the exterior to connect the doghouse; installed T-fitting for fuel supply to the hot-water heater; constructed doghouse base. 
  • #K41: Post and pad foundation installation (one row completed with cross-bracing). 
  • #K79: Prepared site for lifting; cribbing delivered; placed both I-beams under the building; continued lifting operations; relocated structure over two miles to across from the 20-unit housing. 
  • Water Plant: Thawed lift-pump. 
  • Total of 24 team members onsite. 

3/16/26 

  • Cruz: Continued installing helical piles. Continuing boardwalk construction. 
  • 25 helical piles installed yesterday; one excavator pre-drilling with auger built past the frozen layer, ~100 linear feet of boardwalk constructed. 
  • Helical Piles to date: 1,425/Linear feet of boardwalk: 1,892. 
  • Brice/STG: Critical infrastructure checks. 
  • Delta Backhaul: Continued installing helical piles, removed snow and set up/repaired equipment. Five helical piles installed yesterday. The temporary boardwalk was removed mostly intact and stacked for cribbing use. Waiting on quick-connects for the second power head. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K16: Finished vapor barrier. 
  • #K35: Installed dishwasher and plumbed in the water tank. 
  • #K42: Set post and pad foundation.
  • #K74: Continued lifting the building.
  • #K79: Prepared for lifting and brought cribbing onto site. 
  • Water Plant: Produced water, thawed the washateria dump line, and repaired the washateria lift pump.
  • Total of 27 team members onsite. 

3/15/26 

  • Cruz: Continued installing helicals and constructing boardwalk. 
  • 25 helical piles installed yesterday; one excavator pre-drilling with auger bit past the frozen layer. ~100 linear feet of boardwalk constructed. About 10 piles installed today. 
  • Helical Piles to date: 1,398/Linear feet of boardwalk: 1,792. 
  • Brice/STG: Continuing critical infrastructure checks. Two plumbers flew to Kipnuk to work on frozen/damaged sewer system. 
  • Delta Backhaul: Continued installing helical piles, removing snow, and equipment set up/repair. Four helical piles installed yesterday. Temporary boardwalk removed mostly intact and stacked for cribbing. Still waiting on quick-connects for the second power head. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

3/14/26 

  • Cruz: Continued installing helicals and constructing boardwalk. 
  • 15 helical piles installed yesterday; one excavator pre-drilling with auger bit past the frozen layer. ~100 linear feet of boardwalk constructed. About 10 piles installed today. 
  • Helical Piles to date: 1,373/Linear feet of boardwalk: 1,692. 
  • Brice/STG: Continuing critical infrastructure checks. Two plumbers flew to Kipnuk to work on frozen/damaged sewer system. 
  • Delta Backhaul: Continued installing helical piles, removing snow, and equipment set up/repair. Four helical piles installed yesterday. Temporary boardwalk removed mostly intact and stacked for cribbing. Still waiting on quick-connects for the second power head. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

 3/13/26 

  • Cruz: Continued installing helicals and constructing boardwalk. 
  • 10 helical piles installed yesterday; one excavator pre-drilling with auger bit past the frozen layer. ~100 linear feet of boardwalk constructed. About five piles installed today. 
  • Helical Piles to date: 1,348/Linear feet of boardwalk: 1,592. 
  • Brice/STG: Continuing critical infrastructure checks. Two plumbers flew to Kipnuk to work on frozen/damaged sewer system. 
  • Delta Backhaul: Continued installing helical piles, removing snow, and equipment set up/repair. Four helical piles installed yesterday. Temporary boardwalk removed mostly intact and stacked for cribbing. Still waiting on quick-connects for the second power head. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed. 

3/12/26 

  • Cruz: Continued installing piles from the sewer lagoon; three installed last night, eight so far today. Using pilot auger to get through the hard layer which is three to four feet down. Boardwalk crew continued with boardwalk construction behind them. 
  • Helical piles to date: 1,335/Linear feet of boardwalk: 1,400. 
  • Brice/STG: Critical infrastructure checks still being performed. Two plumbers flew to Kipnuk to work on frozen/damaged sewer system. 
  • Delta Backhaul: Began installing piles today. One fully installed and working on the second. Removed snow towards the school. Sany techs onsite trying to get excavators running. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K08: Stripped interior and cleaned debris. 
  • #K18: Continued to remove wet insulation. 
  • #K20: Finished painting. 
  • #K32: Installed new wall sheeting and fix vapor barrier. 
  • #K35: Fixed up house for catering; started demolition, furred out wall, and began running water pipe. 
  • #K42: Setting post and pad foundation. 
  • #K44: Prefabricated parts for boiler. 
  • #K48: Continued thawing doghouse.
  • #K66: Moved house into new position, lifted building off skid, and set on cribbing.
  • #K74: Continued lifting the house. 
  • Water Plant: Thawing dump line from washateria.
  • Total of 30 team members onsite. 

3/11/26 

  • Weather is improving. Water is able to make it to the village water treatment plant, but the line to the storage tank is frozen. Brice is assisting. 
  • Cruz: Continued with pile installation and boardwalk construction from the sewer lagoon. 10 piles installed today. Removed snow and berming from boardwalk area to prevent drifting. Still down to one excavator/drive head. 
  • Helical piles to date: 1,160/Linear feet of boardwalk: 1,150. 
  • Brice/STG: Critical infrastructure checks still being performed. Two plumbers flew to Kipnuk to work on frozen/damaged sewer system. 
  • Delta Backhaul: Service technician's onsite to repair the two Sany 80 excavators that have been down. Mechanic worked on installing drive head on Cat 35 excavator for pile installation. Removed snow for boardwalk work. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K13: Finished insulating and completing underlayment installation. 
  • #K20: Painted interior walls; continued interior stripping and debris removal. 
  • #K35: Pre-fabricated plumbing components. 
  • #K63: Repaired boiler. 
  • #K65: Raised the structure, removed I-beams, and leveled the building onto cribbing. 
  • #K66: Set the house onto the skid and moved ~50 yard to reposition.
  • General: Plumbed new fuel tanks with pumps; repaired sewer line servicing rental units. 
  • Water Plant: Attempted to thaw lines between the treatment system and the washateria. 
  • Total of 28 team members onsite. 

3/10/26 

  • Weather is improving. Water is able to make it to the village water treatment plant, but the line to the storage tank is frozen. Brice is assisting. 
  • Cruz: Continued with pile installation from the sewer lagoon towards the village. They are about to the culvert crossing which puts them 1,500 to 1,800 ft from the tie-in point. Boardwalk continued to be built behind them; about 200 ft has been completed. They have over 1,500 ft of pilings to catch up on.
  • Helical piles to date: 1,150/Linear feet of boardwalk: 1,150. 
  • Brice/STG: Critical infrastructure checks still being performed. Two plumbers flew to Kipnuk to work on frozen/damaged sewer system. 
  • Delta Backhaul: Received their drive heads and Sany excavator with drive head installed. Snow removal continues at the tie-in to the existing boardwalk behind the school. Layout continues as well. The rest of the crew is managing debris removed during snow removal and prepping for boardwalk work and pile installation, which should proceed tomorrow. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed. 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K08: Stripped interior and cleaned debris. 
  • #K16: Completed ~95% of post and pad installation. 
  • #K18: Continued removing damaged walls containing wet insulation. 
  • #K20: Painted walls and floors; surfaces are prepared for the final coat. 
  • #K48: Serviced the boiler and restored it to operational condition. 
  • #K66: Repositioned the skid and pulled the house across the river. 
  • Total of 29 team members onsite. 

    3/09/26 

    • Cruz: Continued with pile installation, anticipating intersecting with the "roadway: to the sewer lagoon by tomorrow. 
    • Helical piles to date: 1,085/Linear feet of boardwalk: 1,080. 
    • Brice/STG: Critical infrastructure checks still being performed. Two plumbers flew to Kipnuk to work on frozen/damaged sewer system. 
    • Delta Backhaul: Continued removing snow along the boardwalk section towards the fuel farm from school. They are also gathering debris as they go and taking it to the incinerator. They should be receiving their driving equipment later today on the pisten bully train. 
    • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

    Facilities Daily Report

    • Work performed by Hog River Construction.
    • #K08: Stripped interior and removed debris. 
    • #K13: Finished insulation and underlayment work. 
    • #K20: Painted walls. 
    • #K48: Serviced boiler to restore it to operational status. 
    • #K49: Fixed boiler and performed service. 
    • #K65: Removed I-beams and leveled house on cribbing. 
    • #K66: Lifted house onto skid and moved 50 yards to reposition skid. 
    • Installation of new fuel storage tanks, and new Toyo stove drum. 
    • Total of 28 team members onsite. 

      3/08/26 

      • Weather is improving. Water is able to make it to the village water treatment plant, but the line to the storage tank is frozen. Brice is assisting. 
      • Cruz: Continued with mini ex installation piles from the sewage lagoon and continued with boardwalk construction. 
      • Helical piles to date: 1,052/Linear feet of boardwalk: 1,150. 
      • Brice/STG: Critical infrastructure checks still being performed. Two plumbers flew to Kipnuk to work on frozen/damaged sewer system. 
      • Delta Backhaul: Hauled debris to the burner. Still expecting a drive head by the end of the week. 
      • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

      Facilities Daily Report

      • Work performed by Hog River Construction.
      • #K13: Insulated the structure and installed underlayment (80% complete). 
      • #K20: Sheeted interior walls with ACX, painted interior wall, and interior strip-out with debris removal. 
      • #K65: Raised the house and removed the skid from underneath. 
      • #K66: Lifted the house ~3 ft on the west side. 
      • Rental Units: Repaired hot water heater. 
      • Total of 28 team members onsite. 

      3/07/26 

      • Water and sewer have been restored to the gym section of the school, doubling the number of bathrooms to two. The operator for the village water has returned but the water treatment facility is frozen. Work is proceeding on getting it thawed and functional. 
      • Cruz: Continued with one mini ex installing piles from sewage lagoon and continuing boardwalk construction. 
      • Helical Piles to date: 1,035/Linear feet of boardwalk: 1,080. 
      • Brice/STG: Critical infrastructure checks still being performed. Two plumbers flew to Kipnuk to work on frozen/damaged sewer system. 
      • Delta Backhaul: Hauled debris to the burner. Still expecting a drive head by the end of the week. 
      • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

      Facilities Daily Report

      • Work performed by Hog River Construction.
      • #K08: General cleanup and preparation for stripping. 
      • #K13: Stripped remaining insulation, continued drying out, and began reinsulating and installing underlayment. 
      • #K20: Sheeted walls with ACX. 
      • #K32: General cleanup; began sheeting walls. 
      • #K66: Dug lifting points for airbags; removed snow along the building. 
      • Thawed raw water line supplying the water treatment plant. 
      • Total of 23 team members onsite. 

      3/06/26 

      • Cruz: Continued with one mini ex installing piles from the sewage lagoon and continued boardwalk construction. 
      • Helical Piles to date: 1,025/Linear feet of boardwalk: 1,080. 
      • Brice/STG: Critical infrastructure checks still being performed. Two plumbers flew to Kipnuk to work on frozen/damaged sewer system. 
      • Delta Backhaul: Hauled debris to the burner. Still expecting a drive head by the end of the week. 
      • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

      Facilities Daily Report

      • Work performed by Hog River Construction.
      • #K13: Removed existing insulation, continued drying the structure, and began insulating. 
      • #K14: Completed interior painting. 
      • #K20: Set the house onto the skid and installed ACX wall sheathing. 
      • Continued daily checks on the water plant, serviced dog houses. 
      • Total of 23 team members onsite. 

      3/05/26

      • Water and sewer system is down at school. Community water treatment plant is also out of water. 
      • Cruz: Continued with one mini ex installing piles from the sewage lagoon and continued boardwalk construction. 
      • Helical Piles to date: 1,019/Linear feet of boardwalk: 1,080. 
      • Brice/STG: Critical infrastructure checks still being performed. Two plumbers flew to Kipnuk to work on frozen/damaged sewer system. 
      • Delta Backhaul: Hauled debris to the burner. Still expecting a drive head by the end of the week. 
      • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

      Facilities Daily Report

      • Work performed by Hog River Construction.
      • #K13: Stripped insulation and continued drying out. 
      • #K14: Finished painting walls and began painting the floor. 
      • #K20: Sheeted walls with ACX. 
      • #K43: Fixed hot water heater and prefabbed parts for heaters.
      • #K46/#K49: Got boiler running and operational. 
      • #K65: Lifted house. General: Installed hot water heater in rental unit, prefabricated components for heater installations. 
      • Restored shower in rental units. 
      • Total of 24 team members onsite. 

      3/03/26

      • Cruz: Continued support for other contractors. Continued boardwalk installation: one excavator drove piles; 2nd drive unit is broken down with plans in the works to get the other helical head driver operational. Continued installation of boardwalk deck and support brackets. Removed snow. Installed boardwalk deck out to freshwater source. Installed piles out to sewage lagoon. 
      • Helical Piles to date: 1,016/ Linear feet of boardwalk: 1,080. 
      • Brice/STG: Local and non-local hires on. Critical infrastructure checks still being performed. Two plumbers currently troubleshooting and monitoring school's sewer line. 
      • Delta Backhaul: Removed and hauled debris. Assisted with snow removal. Supported other contractors. 
      • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

      Facilities Daily Report

      • Work performed by Hog River Construction.
      • #K13: Stripped insulation, removed skirting, and began drying out. 
      • #K14: Began interior wall painting. 
      • #K20: Repaired damaged wall, removed deteriorated plywood, and completed floor repairs. 
      • #K33: Stripped insulation, removed skirting, and began drying out.
      • #K43: Attempted to thaw sewer tank.
      • #K46: Serviced boiler. 
      • General: Installed hot water heater in rental unit, prefabricated components for heater installations. 
      • Total of 24 team members onsite. 

      3/02/26

      • Cruz: Continued support for other contractors. Continued boardwalk installation. Day shift installed 12 helicals/night shift installed 12 helicals. Continued installation of boardwalk deck and support brackets. Removed snow. Installed boardwalk deck out to freshwater source. Installed piles out to sewage lagoon. 
      • Helical Piles to date: 837/ Linear feet of boardwalk: 1,080. 
      • Brice/STG: Local and non-local hires on. Critical infrastructure checks still being performed. Two plumbers currently troubleshooting and monitoring school's sewer line. 
      • Delta Backhaul: Removed and hauled debris. Assisted with snow removal. Supported other contractors. 
      • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

      Facilities Daily Report

      • Work performed by Hog River Construction.
      • #K13: Cleared snow around the house and gathered cribbing. 
      • #K14: Completed interior wall sheeting with AC plywood and began painting.
      • #K16: Installed new beams, raised the house to elevation, and set posts and pads on the south side of the house. 
      • #K20: Finished interior insulation and began interior sheeting. 
      • #K65: Performed lift operations on the structure. 
      • Total of 25 team members onsite. 

      3/01/26

      • Cruz: Continued support for other contractors. Continued boardwalk installation. Day shift installed 12 helicals/night shift installed 10 helicals. Continued installation of boardwalk deck and support brackets. Removed snow. Installed boardwalk deck out to freshwater source. Installed piles out to sewage lagoon. 
      • Helical Piles to date: 813/Linear feet of boardwalk: 990. 
      • Brice/STG: Local and non-local hires on standby including three electricians, two wiremen, and one plumber. Critical infrastructure checks still being performed. 
      • Delta Backhaul: Removed/hauled debris. Assisted with snow removal and supported other contractors. 
      • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

      3/27/26


      3/26/26


      3/25/26


      3/24/26


      3/23/26


      3/22/26


      3/21/26


      3/20/26


      3/17/26


      3/16/26


      3/15/26


      3/14/26


      3/13/26


      3/12/26


      3/11/26


      3/10/26


      3/06/26


      3/05/26


      3/03/26


      3/02/26