Kwigillingok Operations Summary

6/01/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice/STG: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.
  • Brice: Repaired contractor lake to water treatment plant existing water line. 

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K25: Installed post and pad foundation. 
  • #K33: Rebuilt damaged deck and installed post and pad foundation. 
  • #K72: Painted interior walls. 
  • #K78: Painted ceiling and arctic entry. 
  • #K79: Installed windows, floor insulation, and underlayment. 
  • Total of 26 team members onsite. 

5/31/26

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K03: Installed plumbing and connected the sewer doghouse. 
  • #K14: Completed interior trim. 
  • #K26: Built stairs, constructed deck, and leveled the porch. 
  • #K33: Installed post and pad insulation. 
  • #K78: Painted bedrooms. 
  • #K79: Installed floor insulation. 
  • Total of 24 team member onsite. 

5/30/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice/STG: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.
  • Brice: Repaired contractor lake to water treatment plant existing water line. 

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K20: Completed interior trim. 
  • #K33: Installed post and pad foundation. 
  • #K72: Installed interior sheeting. 
  • #K78: Painted living room and kitchen. 
  • #K79: Installed wall insulation, vapor barrier, and interior sheeting. 
  • Total of 24 team members onsite. 

5/29/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice/STG: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.
  • Brice: Repaired contractor lake to water treatment plant existing water line. 

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K33: Installed post and pad foundation. 
  • #K38: Worked on interior trim and demolished bathroom for plumbing preparation. 
  • #K72: Installed interior sheeting. 
  • #K78: Painted interior surfaces. 
  • #K79: Removed wet attic insulation, installed wall insulation, vapor barrier placement, and interior sheeting. 
  • Total of 23 team members onsite. 

5/28/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice/STG: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.
  • Brice: Repaired contractor lake to water treatment plant existing water line. 

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K33: Installed post and pad foundation. 
  • #K38: Interior trim work. 
  • #K39: Demolished interior walls, installed wall insulation and placed vapor barrier. 
  • #K72: Installed wall insulation, vapor barrier, and interior sheeting. 
  • #K78: Painted ceiling surfaces. 
  • Total of 23 team members onsite. 

5/27/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice/STG: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.
  • Brice: Repaired contractor lake to water treatment plant existing water line. 

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K33: Post and pad foundation installation. 
  • #K39: Interior demolition and debris removal. 
  • #K72: Vapor barrier installation and interior sheeting. 
  • #K78: Ceiling painting. 
  • #K79: Bathroom demolition and preparation for plumbing work. 
  • Total of 23 team members onsite. 

5/26/26

  • Hog River: Moving/leveling houses. Setting dog houses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 
  • Brice/STG: Continued to monitor critical infrastructure. Electricians assisted linemen in connecting houses to power whenever Hog River deem ready. Also staged materials to repair damaged existing water line from contractor lake to water treatment plant. Repaired boardwalk along runway. 

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K33: Constructed post and pad foundation. 
  • #K38: Completed interior trim installation. 
  • #K39: Performed demo interior activities.
  • #K65: Executing trim interior tasks. 
  • #K78: Applied paint to interior surfaces.
  • #K79: Installed T1-11 siding, setting Z-metal, and dried out interior walls. 
  • Total of 20 team members onsite. 

5/25/26

  • Hog River: Moving/leveling houses. Setting dog houses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 
  • Brice/STG: Continued to monitor critical infrastructure. Electricians assisted linemen in connecting houses to power whenever Hog River deem ready. Also staged materials to repair damaged existing water line from contractor lake to water treatment plant. Repaired boardwalk along runway. 

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K33: Completed post and pad foundation work. 
  • #K39: Performed demolition of the interior. 
  • #K65: Carried out interior trim work and conducted interior painting. 
  • #K78: Applied interior paint. 
  • #K79: Installed roofing and dried out interior walls. 
  • Total of 26 team members onsite. 

5/24/26

  • Hog River: Moving/leveling houses. Setting dog houses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 
  • Brice/STG: Continued to monitor critical infrastructure. Electricians assisted linemen in connecting houses to power whenever Hog River deem ready. Also staged materials to repair damaged existing water line from contractor lake to water treatment plant. Repaired boardwalk along runway. 

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K07: Installed cross-bracing for the foundation and installed Toyo stove. 
  • #K26 and #K33: Constructed post and pad foundation. 
  • #K38: Furred out walls and installed insulation, vapor barrier, and interior sheathing. 
  • #K39: Installed cross-bracing for the foundation. 
  • #K65: Painted interior walls. 
  • #K72: Installed interior insulation and vapor barrier. 
  • #K78: Installed interior sheathing and vapor barrier. 
  • #K79: Conducted interior demolition and furred out walls. 
  • Total of 26 team members onsite. 

5/23/26

  • Hog River: Moving/leveling houses. Setting dog houses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 
  • Brice/STG: Continued to monitor critical infrastructure. Electricians assisted linemen in connecting houses to power whenever Hog River deem ready. Also staging materials to repair damaged existing water line from contractor lake to water treatment plant. Repaired boardwalk along runway. 
  • LKSD school cleaned and returned to district. 

Facilities Daily Report 

  • Work performed by Hog River Construction. 
  • #K07: Cross-bracing foundation components. 
  • #K26: Constructed post and pad foundation. 
  • #K38: Furring out walls. 
  • #K72: Cross-bracing foundation components. 
  • #K78: Installed interior sheeting and vapor barrier. 
  • #K79: Cleaned debris from floor surfaces. 
  • Total of 26 team members onsite. 

5/22/26 

  • Hog River: Moving/leveling houses. Setting dog houses for installation. Drying/thawing houses. Removing wet/damaged material in houses. Installing new material as needed. 
  • Brice/STG: Continued to monitor critical infrastructure. Electricians assisted linemen in connecting houses to power whenever Hog River deem ready. Also staging materials to repair damaged existing water line from contractor lake to water treatment plant. Repaired boardwalk along runway. 
  • LKSD school inspection following Brice personnel use and clean-up. LKSD personnel accepted facilities return. 

5/21/26

Facilities Daily Report 

  • Work performed by Hog River Construction 
  • #K26: Post and pad material work in progress. 
  • #K64: Cleaned the interior, demolished flooring, and dried the subfloor. 
  • #K65: Insulated, vapor barrier installation, and T1-11 work. 
  • #K66: Interior sheeting and plumbing work. 
  • #K78: Interior sheeting and vapor barrier installation is in progress. 
  • Total of 26 team members onsite. 

5/20/26

Facilities Daily Report 

  • #K25, #K26, #K33: Transporting post and pad materials 
  • #K63: Conducting interior cleaning
  • #K65: Performing cross-bracing, insulation work, vapor-barrier installation, and T1-11 application 
  • #K78: Performing interior sheeting and installing the vapor-barrier
  • Total of 26 team members are currently on site. 

5/19/26

Facilities Daily Report 

  • #K65: Conducting interior sheeting
  • #K66: Performing interior and exterior cleanup
  • #K78: Conducting interior sheeting
  • #K79: Repairing floor joists
  • General Tasks: Hauling plane-load materials 
  • Total of 26 team members are currently on-site

5/18/26

Facilities Daily Report 

  • #K03: Performing flooring installation activities
  • #K07: Conducting post-and-pad foundation work
  • #K08: Carrying out exterior finish tasks, insulation removal, and general cleanup
  • #K63: Painting interior walls 
  • #K65: Installing stair rails and foam board, reframing the exterior door, insulating walls, and applying sheeting
  • #K66: Applying stained finish trim
  • #K78: Continuing installation of vapor barrier and insulation 
  • Total of 16 team members are currently on-site 

5/17/26

Facilities Daily Report

  • #K07: Continued post and pad installation and replaced rotten beams
  • #K08: Removed remaining wet insulation, demolished interior walls, and repaired T1-11 siding
  • #K41: Continued floor painting
  • #K63: Painted interior walls 
  • #K65: Completed plywood installation, house wrap, and wall insulation
  • #K66: Stained trim
  • #K74: Completed outside corner trim and floor painting
  • #K78: Installed vapor barrier and sheathing
  • Total of 24 team members are currently on-site

5/15/26

Facilities Daily Report 

  • #K07: Replace rim joist and support beams; set posts and pads
  • #K66: Strip bathroom for re-installation; complete exterior corner work
  • #K74: General bathroom cleanup in preparation for plumbing work; close in exterior corners; install Z-metal and siding; paint floor
  • #K41: Paint floor
  • #K63: Complete interior trim
  • #K65: Close separation in center of house structure; insulate floor and portions of walls
  • Total of 24 team members are currently on-site

5/14/26

  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.
  • Brice / STG: Continued to monitor critical infrastructure. Electricians assist linemen in connecting houses to power whenever Hog River deem ready

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K03: Install flooring and complete cross-bracing
  • #K07: Cut out rotten beams; begin post-and-pad foundation on the east side
  • #K08: Build stairs; install 2" foam board underlayment; prepare for T1-11 installation
  • #K13: Build ramp to the boardwalk
  • #K41: Demolish porch and close in area to allow electricians to relocate the meter box
  • #K42: Begin painting the floor
  • #K63: Complete interior trim, cabinets, and ro
  • #K65: Install cross-bracing; demolish interior insulation; clean exterior debris 
  • #K74: Prepare floor for paint and complete painting
  • General Tasks: Repair sewer tank trailer; remove debris from beneath houses; perform water and sewer service; operate water plant to make water
  • Total of 30 team members are currently on site. 

5/13/26 

  • Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K03: Cross bracing foundation. 
  • #K07: Carried out beam change-out and continued post and pad installation. 
  • #K13: Built ramp to the boardwalk. 
  • #K28: Cut foam board to one inch and completed T1-11 repairs. 
  • #K35: Installed interior doors and built stairs and handrails. 
  • #K63: Completed interior sheeting, exterior siding, cross-bracing of the foundation, and painted the kitchen wall. 
  • #K65: Stripped interior walls, disposed of wet insulation, and repaired the support beam. 
  • #K74: Completed floor preparation for painting. 
  • Total of 28 team members onsite. 

5/12/26 

  • Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K03: Floor installation. 
  • #K07: C/O rotten beams; began setting posts and pads. 
  • #K28: Leveled fuel stands; began T1-11 repair. 
  • #K39: Built stairs and handrails. 
  • #K63: Interior sheeting. 
  • #K65: C/O back beam and re-level; built stairs. 
  • #K66: Painted trim. 
  • #K72: Built stairs and handrails. 
  • #K74: Painted and prepped floor. 
  • Total of 28 team members onsite. 

5/11/26 

  • Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K03: Began flooring installation. 
  • #K07: Raised south end to elevation and began pad placement. 
  • #K13: Finished post bracing; built guardrail; ramp construction has been completed. 
  • #K14: Built handrails; raised and supported proch. 
  • #K39: Installed foam board under house. 
  • #K63: Completed vapor barrier installation; began roof repair. 
  • #K66: Painted trim. 
  • #K74: Completed primer; cross-bracing posts. 
  • Total of 26 team members onsite. 

5/10/26 

  • Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K13: Completed post and pad installation with bracing. Raised the deck with temporary support and constructed stairs with handrails and a ramp to the lower level. 
  • #K39: Installed foam board insulation beneath the structure. 
  • #K63: Applied primer coat to interior walls. 
  • #K66: Continued interior trim installation. 
  • #K74: Completed wall insulation and began vapor barrier installation. 
  • General: Clean up across job sites. 
  • Total of 23 team members onsite. 

5/09/26 

  • Cruz: Demobed from site. 
  • Helical piles to date: 2,486/Linear feet of boardwalk: 8,200.  
  • Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
  • Delta Backhaul: Demobed from site. 
  • Number of helicals installed to date: 602.
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K13: Setting posts and pads with bracing. 
  • #K63: Completed furring out walls and began insulating. 
  • #K64: Insulated the floor and installed underlayment. 
  • #K65: Stripped interior walls and flooring. 
  • #K74: General cleaning in preparation for paint.
  • Continuing boardwalk repairs. 
  • Airport cargo transportation operations. 
  • Total for 23 team members onsite. 

5/08/26 

  • Cruz: Demobed from site. 
  • Helical piles to date: 2,486/Linear feet of boardwalk: 8,200.  
  • Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
  • Delta Backhaul: Demobed from site. 
  • Number of helicals installed to date: 602.
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K13: Worked on post and pad foundation. 
  • #K63: Furring out walls; Toyo stove and fuel stand installation. 
  • #K64: Installed floor joists and underlayment insulation (50% complete). 
  • #K74: General clean up around the house. 
  • Continuing boardwalk repairs. 
  • Airport and cargo transportation operations. 
  • Total of 26 team members onsite. 

5/07/26 

  • Cruz: Demobed from site. 
  • Helical piles to date: 2,486/Linear feet of boardwalk: 8,200.  
  • Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
  • Delta Backhaul: Demobed from site. 
  • Number of helicals installed to date: 602.
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K03: Began preparing for upcoming floor installation. 
  • #K13: Completed installation of new pads and ready for final leveling and house placement. 
  • #K18: Completed floor insulation activities. 
  • #K66: Finished all interior painting work. 
  • #K74: Continued installing interior wall sheeting. 
  • General: Repaired the boardwalk between the school and the airport and maintained ongoing airport cargo transportation. 
  • Total of 25 team members onsite. 

5/05/26 

  • Cruz: Demobing from site. 
  • Helical piles to date: 2,486/Linear feet of boardwalk: 8,200.  
  • Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
  • Delta Backhaul: Demobed from site. 
  • Number of helicals installed to date: 602.
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K13: Cribs were staged, the structure was lifted, and ramp repair work began. 
  • #K18: Stair and railing construction progressed, re-insulation was completed, and sheeting commenced. 
  • #K20: Interior and exterior cleanup was completed. 
  • #K41: Priming was finalized and finish-coat application began. 
  • #K42: Painting completed. 
  • #K64: Insulation and skirting were removed, dry-out activities began, the Toyo stove was installed, re-insulation was completed, and sheeting commenced. 
  • #K65: Re-insulation completed and began sheeting. 
  • #K66: Floor insulation and vapor barrier installation were completed, and interior sheeting began. 
  • #K68: Roofing and T1-11 exterior sheathing were installed. 
  • #K68: Roofing and T1-11 exterior sheeting were installed. 
  • Total of 24 team members onsite. 

5/04/26 

  • Cruz: Demobed from site. 
  • Helical piles to date: 2,486/Linear feet of boardwalk: 8,200.  
  • Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
  • Delta Backhaul: Demobing from site. 
  • Number of helicals installed to date: 602.
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K17: Staged cribs to raise the house. 
  • #K39: Installed wall sheeting and applied house wrap. 
  • #K41 and #K42: Interior painting work. 
  • #K64: Finished post and pad foundation with bracing. 
  • #K68: Installed roofing and T1-11 exterior sheeting. 
  • #K77: Built stairs and installed handrails. 
  • General: Cleared snow at the lagoon to establish an access path for sewer transfer and hauled tundra mats from the lake to the gravel road. 
  • Total of 23 team members onsite. 

5/03/26 

  • Cruz: Demobing from site. 
  • Helical piles to date: 2,486/Linear feet of boardwalk: 8,200.  
  • Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
  • Delta Backhaul: Demobing from site. 
  • Number of helicals installed to date: 602.
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

5/02/26 

  • Cruz: Demobing from site. 
  • Helical piles to date: 2,486/Linear feet of boardwalk: 8,200.  
  • Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
  • Delta Backhaul: Demobing from site. 
  • Number of helicals installed to date: 602.
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K17: Completed installation of foam board. 
  • #K18: Installed interior trim. 
  • #K41: Completed interior painting. 
  • #K42: Completed interior painting. 
  • #K64: Set post and pad foundation. 
  • #K68: Installed wall insulation and applied vapor barrier. 
  • #K75: Installed house wrap and began placing foam board beneath the structure. 
  • #K77: Completed house wrap and foam installation under the building; finalized bracing and cleaned the work area.
  • General: Continued transporting airport cargo. 
  • Total of 24 team members onsite. 

5/01/26 

  • Cruz: Finished boardwalk at village store. Assisted/supported other contractors. Transitioned into demob; gathered tools, equipment, and supplies. Demobing over the weekend.
  • Helical piles to date: 2,486/Linear feet of boardwalk: 8,200.  
  • Brice/STG: Continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
  • Delta Backhaul: Working on punch list items. Planned demob for Saturday. 
  • Number of helicals installed to date: 602.
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K18: Skirted the house to allow structure to dry out. 
  • #K39: Insulated the floor. 
  • #K40: Insulated and sheeted flooring beneath the house. 
  • #K41 and #K42: Painted interior walls. 
  • #K64: Continued lifting and replacing damaged beam. 
  • #K77: Set final post and pad foundation with bracing. 
  • General: Continued transporting airport cargo and hauled cribs from the water reservoir. 
  • Total of 25 team members onsite. 

5/26/26


5/24/26


5/13/26


5/08/26


5/02/26


5/01/26