Kwigillingok Operations Summary

6/21/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K08: Primed and painted interior walls, ceilings, and trim; completion of interior wall repairs, replaced damaged framing members, installed new wall insulation, vapor barrier, acoustical sealant, and CDX plywood wall sheathing. 
  • #K12: Lifted house to required elevation; installed center support beam; cribbing installed to stabilize structure; debris removed from beneath and around the residence and hauled to landfill. 
  • #K16: Painted interior walls and replaced trim; installed and tested of Toyo oil stove. 
  • #K22: Mobilized lifting equipment and cribbing materials; removed debris and obstacles including an aluminum boat; started house lifting operations; lifted west side of residence and installed cribbing as structure from standing water. 
  • #K39: Installed and test fired Toyo oil stove; removed damaged wall framing; installed replacement framing members, insulation, vapor barrier, acoustical sealant, and CDX plywood wall sheathing.
  • #K41: Painted interior floor. 
  • #K64: Installed new window jambs and trim. 
  • #K79: Installed window case extensions and finish trim; painted interior floor, cleaned up debris beneath the residence and hauled to landfill. 
  • General: Community-wide debris cleanup; hauled construction debris to landfill; repaired boardwalk. 
  • Total of 24 team members onsite. 

6/21/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K08: Priming of interior walls, ceilings, and trim. 
  • #K12: House lifting operations completed to design elevation; structure placed on cribbing; debris removed from beneath the residence and hauled to landfill. 
  • #K16: Painting interior walls and trim. 
  • #K22: Mobilized lifting equipment and tools to site; collected and hauled cribbing materials; started lifting operations on the west side of the residence. 
  • #K31: Pumped septic tank; constructed new septic tank foundation' reset septic tank; installed four-inch sewer pipe between residence and septic tank; constructed new stairs and handrails. 
  • #K41: Installed T1-11 siding in areas damaged by porch failure; interior floor painting.
  • #K64: Installed trim around windows and exterior entry door. 
  • #K79: Interior floor painting. 
  • General: Boardwalk repairs. 
  • Total of 26 team members onsite. 

6/19/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K08: Painted interior walls, ceilings, and trim; hauled and disposed of construction debris and scarp materials to landfill.
  • #K12: Lifted house to raise structure above water level and established elevation for new foundation installation; removed debris from beneath and around the residence; hauled and disposed of debris to landfill.
  • #K16: Painted interior walls and replaced trim. 
  • #K39: Demolished walls damaged by floodwaters; installed indirect-fired heater to dry wall assemblies; hauled and disposed of demolished debris to landfill.
  • #K41: Repaired exterior siding in areas where porch structures were destroyed. Hauled and disposed of construction debris and scrap materials. 
  • #K42: Constructed stairs and handrails; cleaned up debris beneath the residence; hauled and disposed of debris to landfill. 
  • #K63: Final interior and exterior cleanup; hauled and disposed of remaining debris. 
  • #K79: Prepared floors for painting through scraping and cleaning; started painting the floor.  
  • General: Community-wide debris cleanup; hauled construction debris to landfill; repaired boardwalk. 
  • Total of 25 team members onsite. 

6/18/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K08: Completed installing CDX plywood on interior walls; completed interior trim work; hauled and disposed of construction debris; started boardwalk repairs. 
  • #K12: Lifted house to raise structures above water levels and established elevation for new foundation installation. 
  • #K16: Interior wall and trim painting. 
  • #K41: Installed foam board insulation beneath the structure; installed stair handrails; installed foundation cross-bracing. 
  • #K42: Installed foundation cross-bracing; cleaned up beneath and around the residence. 
  • #K65: Installed Toyo stove. 
  • #K79: Interior wall and trim painting. 
  • General: Community-wide debris cleanup; hauled construction debris to landfill; repairing boardwalk. 
  • Total of 25 team members onsite. 

6/17/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K08: Completed interior wall sheathing installation; trim installation; roof repairs; hauled and disposed of construction debris. 
  • #K21: Constructed platforms around the residence; lifted structure above standing water; hauled and disposed debris; retrieved and relocated cribbing materials from completed homes; stored air heated in connex containers. 
  • #K42: Replaced damaged trim; removed remaining flooring materials; prepared surfaces for painting; installed cabinets; hauled and disposed of construction debris. 
  • #K63: Completed bathroom painting; interior and under house cleanup. 
  • #K64: Completed interior painting; completed trim installation; interior cleaning and preparation for inspection. 
  • #K65: Completed exterior siding repairs and exterior trim work; interior and under house cleanup.
  • #K74: Installed exterior door and trim; painted trim, interior cleanup. 
  • #K79: Painted interior walls. 
  • General: Water and sewer service activities; cleaned up around reservoir housing and downtown residences; hauled and disposed of construction debris. 
  • Total of 27 team members onsite. 

6/16/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K03: Finial interior and exterior cleaning and site cleanup. 
  • #K08: Completed installing insulation, vapor barrier, and wall sheathing; started interior trim installation. 
  • #K21: Staged construction materials and cribbing in preparation for house lifting and rehabilitation work. 
  • #K39: Demolished interior wall finsihes and subflooring; removed and cleaned up interior debris. 
  • #K63: Installed bathroom wall insulation; installed vapor barrier and CDX plywood sheathing; installed trim, painted and finishing work. 
  • #K64: Completed interior wall painting; installed trim; cleaned debris beneath and around the residence; prepared additional trim materials.
  • #K66: Finishing up site, interior and exterior clean up. 
  • #K78: Completed post, pad, and bracing foundation system; site cleanup; removed and relocated cribbing materials to the next residence. 
  • General: Water and sewer service activities; transferred sewage waste to treatment pit; hauled and stored frost fighters and project equipment; community cleanup and debris disposal. 
  • Total of 26 team members onsite. 

6/15/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K08: Installed insulation and vapor barrier; started ceiling and wall sheathing with CDX plywood; roof repairs; staged construction materials. 
  • #K19: Completed handrails; repairs to floor underlayment. 
  • #K42: Started foam board underlayment installation. 
  • #K63: Installed insulation and vapor barrier; installed plywood wall sheathing; installed living room and window trim. 
  • #K65: Painted trim and floors; site cleanup. 
  • #K74: Final site cleanup and close out activities.
  • #K78: Completed house leveling; adjusted and replaced foundation pads; completed post and pad foundation work. 
  • #K79: Completed two-inch foam board underlayment; competed subfloor and trim installation; interior and exterior cleanup around the residence.
  • General: Community cleanup activities; hauled debris and trash to disposal sites; transferred sewage waste from lagoon to treatment pit; servicing water and sewer operations.
  • Total of 27 team members onsite. 

6/14/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K08: Installed insulation and started vapor barrier installation. 
  • #K16: Final interior cleanup; completed interior finish work; cleaned up around the residence. 
  • #K17: Constructed handrails; exterior siding repairs; cleaned up around the residence. 
  • #K18: Repaired stairs, constructed handrails; installed foundation cross-bracing; cleaned up site around the residence.
  • #K20: Cleaned out interior; cleaned up around the residence, repaired boardwalk. 
  • #K63: Completed exterior siding repairs; repaired roof damage.
  • #K74: Completed bathroom trim work; painted bathroom; cleaned up interior and under the house. 
  • General: Water and sewer service activities; transferred sewage waste for lagoon to treatment pit; hauled and disposed of trash from project sites; repaired boardwalk access areas. 
  • Total of 27 team members onsite. 

6/13/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K16: Completed interior trim work; installed stair handrails; site cleanup; demobilized and relocated tools and equipment. 
  • #K19: Installed new exterior door; constructed handrails; site cleanup around the residence. 
  • #K20: Constructed handrails; stair repairs; interior and exterior site cleanup. 
  • #K65: Completed interior and exterior trim painting. 
  • #K78: Constructed and staged foundation pads; collected and staged cribbing materials. 
  • #K79: Installed 1/2-inch CDX subflooring; installed house wrap; installed two-inch foam board underlayment; hauled and disposed constructure debris. 
  • General: Water and sewer service activities; repaired boardwalk ramps and missed boardwalk sections; repairs to boardwalk access at the 20-unit housing complex; hauled and disposed of construction debris. 
  • Total of 27 team members onsite. 

6/12/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K07: Completed exterior siding repairs; prepared interior walls for vapor barrier installation; cleaned interior; framed roof overhang supports; prepared for insulation, vapor barrier, and interior wall sheathing installation. 
  • #K16: Installed foam board insulation beneath the structure; installed foundation cross-bracing; installed CDX wall sheathing; commencement of interior trim work; installed window trim, base trim, and crown trim; site cleanup and stair resetting. 
  • #K27: Continued lifting structure; resetting and adding cribbing for safety; removed water-damaged floor insulation. 
  • #K38: Completed exterior siding repairs; completed foundation cross-bracing; completed interior wall and trim painting; floor painting; replaced deteriorated floor sections. 
  • #K41: Installed exterior door. 
  • General: Water and sewer service activities; hauled and disposed of construction debris and site cleanup. 
  • Total of 26 team members onsite. 

6/11/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K07: Demolished and removed interior flooring; removed a small porch section; framed and enclosed opened areas; releveled structure and cleaned up beneath the building. 
  • #K16: Site cleanup and preparation; installed foam board underlayment. 
  • #K27: Initiated lifting structure on the east side in preparation for foundation stabilization work. 
  • #K38: Installed two-inch foam board underlayment; installed interior insulation and vapor barrier; continued installing interior wall sheeting. 
  • #K64: Installed 1/2 inch of CDX sheathing on interior walls; repaired and replaced missing T1-11 siding. 
  • General: Continued removing debris and transported waste materials to the designated disposal site. 
  • Total of 29 team members onsite. 

6/10/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.

6/09/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K07: Began reinsulating the floor and installed 1/2" CDX underlayment. 
  • #K16: Lifted and reset the middle post. Completed furring out and insulated walls, leveled the house, repaired siding around the entire house, hauled trash, and moved cribbing materials for the lifting crew.
  • #K27: Lifted the house two feet around the entire perimeter and completed site cleanup around the structure. 
  • #K38: Replaced missing foam board and completed T1-11 siding repairs. Finished foam board underlayment installation and installed a handrail for the stairs. 
  • #K64: Completed cleanup and finished siding repairs. 
  • #K65: Installed missing siding and completed cleaning inside and underneath the house. 
  • General: Water and sewer hauling. Moved materials to designated staging areas. 
  • Total of 21 team members onsite. 

6/08/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice/STG: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.
  • Brice: Repaired contractor lake to water treatment plant existing water line. 

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K07: Continued demolishing and removing interior subflooring and laminate flooring; repositioned and realigned exterior wall framing. 
  • #K16: Removed remaining interior insulation; installed furring on exterior walls in preparation for insulation and finishing work. 
  • #K27: Continued lifting the east end of the residence in preparation for foundation stabilization work. 
  • #K38: Completed foam board underlayment installation; completed foundation cross-bracing; commencement of exterior siding repairs. 
  • #K64: Painted and installed Toyo stove; completed interior wall sheathing; exterior siding repairs; demobilized tools and equipment. 
  • #K65: Exterior siding repairs and surface preparation for painting. 
  • Total of 29 team members onsite. 

6/07/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice/STG: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.
  • Brice: Repaired contractor lake to water treatment plant existing water line. 

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K07: Demolished and removed interior flooring removed a small porch section; framed and enclosed opened areas; releveled structure and cleaned up beneath the building.
  • #K16: Site cleanup and preparation; installed foam board underlayment. 
  • #K27: Initial lifting of structure on the east side in preparation for foundation stabilization work. 
  • #K38: Installed two-inch foam board underlayment installed interior insulation and vapor barrier; continued installation of interior wall sheeting. 
  • #K64: Installed 1/2-inch CDX sheathing on interior walls; repaired and replaced missing T1-11 siding. 
  • General: Continued removing debris and transported waste materials to the designated disposal site. 
  • Total of 29 team members onsite. 

6/06/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice/STG: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.
  • Brice: Repaired contractor lake to water treatment plant existing water line. 

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K07: Demolished and removed interior flooring; hauled and disposed of interior debris. 
  • #K38: Installed interior wall sheeting; assisted electrician in preparing areas for surface-mounted electrical installation. 
  • #K64: Installed foam board insulation; enclosed damaged window opening; installed foundation cross-bracing. 
  • #K80: Installed post and pad foundation system.
  • General: Constructed boardwalk access ramp to septic tanks. 
  • Total of 31 team members onsite. 

6/05/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice/STG: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.
  • Brice: Repaired contractor lake to water treatment plant existing water line. 

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K07: Demolished interior and hauled debris from the exterior. 
  • #K38: Demolished bathroom and kitchen walls; furred out exterior walls. 
  • #K64: Installed foam board beneath flooring and completed interior vapor barrier; waiting on ACX to continue work.
  • General: Boardwalk repairs and tundra mat assembly at the water reservoir homes.
  • Total of 29 team members onsite. 

6/04/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice/STG: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.
  • Brice: Repaired contractor lake to water treatment plant existing water line. 

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K07: Demolished interior walls and flooring; interior clean-up. 
  • #K64: Furring out walls; installed wall insulation and vapor barrier. 
  • #K79: General site work; hauled and disposed of debris to landfill. 
  • #K80: Installed post and pad foundation system. 
  • Total of 29 team members onsite. 

6/03/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice/STG: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.
  • Brice: Repaired contractor lake to water treatment plant existing water line. 

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K07: Built stairs, demoed interior walls, and removed wet insulation. 
  • #K33: Finished handrails on stairs and deck. 
  • #K38: Began handrails on stairs; painting. 
  • #K64: Demoed interior, removed insulation in walls, hauled material onsite for cross bracing and insulation, and began furring out walls. 
  • #K79: Cleaned up and hauled tools/materials offsite; painting. 
  • Total of 29 team members onsite. 

6/02/26

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K25: Installed post and pad foundation. 
  • #K33: Constructed stairs and handrails. 
  • #K38: Began interior painting activities. 
  • #K72: Completed interior painting activities. 
  • #K79: Installed interior sheeting and completed floor insulation. 
  • Total of 29 team members onsite. 

6/01/26

  • Hog River: Moving/leveling houses. Drying home's interior and removing interior home wet/damaged material and replaced with new material. Setting dog houses for installation. 
  • Brice/STG: Continued to monitor critical infrastructure. Electricians and linemen connected service drops to homes following home relocation/foundation installation.
  • Brice: Repaired contractor lake to water treatment plant existing water line. 

Facilities Daily Report 

  • Work performed by Hog River Construction.
  • #K25: Installed post and pad foundation. 
  • #K33: Rebuilt damaged deck and installed post and pad foundation. 
  • #K72: Painted interior walls. 
  • #K78: Painted ceiling and arctic entry. 
  • #K79: Installed windows, floor insulation, and underlayment. 
  • Total of 26 team members onsite. 

6/04/26