Kwigillingok Operations Summary

4/07/26 

  • Cruz: One excavator drove piles out to sewage lagoon. Continued installing boardwalk sleepers and support brackets out to sewage lagoon. Continued cutting piles and installing saddles out near community church; ~1/3 complete. Boardwalk out to fresh water source is near completion.
  • Helical piles to date: 1,800/Linear feet of boardwalk: 3,900. 
  • Brice/STG: Brice continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
  • Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation. 
  • Number of helicals installed to date: 385. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

 

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K03: Removed the skid from underneath the house. 
  • #K38: Hauled material for post and pad. 
  • #K41: Began re-installing floor insulation. 
  • #K42: Began re-installing floor insulation; removed insulation from walls three feet up. 
  • #K46: Plumbed in the hot water heater. 
  • #K57: Repaired water service lines and continued work to restore running water in the house. 
  • #K63: Finished stripping insulation from the floor and skirted the area for drying; continued dry-out operations. 
  • #K66: Completed T1-11 installation and repairs. 
  • #K74: Began T1-11 repairs; began cleaning around the house. 
  • #K77: Stripped insulation and skirting and began dry-out. 
  • #K79: Began repairs to floor joists and rim joists; fabricated pads for the foundation. 
  • General: Cargo transportation from the airport. 
  • Total of 31 team members are onsite. 

4/06/26 

  • Cruz: One excavator drove piles out to sewage lagoon. Continued installing boardwalk sleepers and support brackets out to sewage lagoon. Continued cutting piles and installing saddles out near community church; ~1/3 complete. Boardwalk out to fresh water source is near completion.
  • Helical piles to date: 1,772/Linear feet of boardwalk: 3,812. 
  • Brice/STG: Brice continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
  • Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation. 
  • Number of helicals installed to date: 377. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

4/05/26 

  • Cruz: One excavator drove piles out to sewage lagoon. Continued installing boardwalk sleepers and support brackets out to sewage lagoon. Continued cutting piles and installing saddles out near community church; ~1/3 complete. Boardwalk out to fresh water source is near completion.
  • Helical piles to date: 1,748/Linear feet of boardwalk: 3,545. 
  • Brice/STG: Brice continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
  • Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation. 
  • Number of helicals installed to date: 367. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K03: Moved house to new location. 
  • #K42: Completed drying out and stripping walls. 
  • #K46: Plumbed in hot water heater. 
  • #K57: Repaired water service line and continued working on restoring running water to the house. 
  • #K63: Finished stripping insulation from the floor and skirted the area for drying. 
    #K64: Removed the skid from underneath the house. 
  • #K66: Continued installation of repair of T1-11. 
  • #K74: Dried out the floor and began cleaning debris. 
  • #K77: Completed bracing. 
  • #K79: Making pads for the foundation. 
  • Total of 30 team member onsite. 

4/04/26 

  • Cruz: One excavator drove piles out to sewage lagoon. Continued installing boardwalk sleepers and support brackets out to sewage lagoon. Continued helical installation out new community church. Cleared and laid out helical installations near village council building. Boardwalk out to fresh water source is near completion.
  • Helical piles to date: 1,738/Linear feet of boardwalk: 3,392. 
  • Brice/STG: Brice continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
  • Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation. 
  • Number of helicals installed to date: 357. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

​​​Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K42: Finished stripping interior and continued drying out the floor joists. 
  • #K46: Plumbed in hot water heater. 
  • #K57: Repaired water service lines and continued work to restore running water. 
  • #K64: Moved structure into its new position. 
  • #K66: Completed dry-out, replaced soggy attic insulation, installed T1-11, and built stairs. 
  • #K74: Continued drying out floor and began interior debris cleanup. 
  • #K77: Completed post and pad work and reached 50 % completion on bracing. 
  • #K79: Constructed pads for foundation. 
  • Total of 30 team members onsite. 

4/03/26 

  • Cruz: One excavator drove piles out to sewage lagoon. Continued installing boardwalk sleepers and support brackets out to sewage lagoon. Continued helical installation out new community church. Cleared and laid out helical installations near village council building. Boardwalk out to fresh water source is near completion.
  • Helical piles to date: 1,732/Linear feet of boardwalk: 3,131. 
  • Brice/STG: Brice continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
  • Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation. 
  • Number of helicals installed to date: 354. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

​​​Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K42: Stripped interior, removed wet insulation, and continued drying out the structure. 
  • #K46: Began installation of the Toyo unit. 
  • #K57: Repaired water service lines and continued working to restore running water. 
  • #K64: Relocated house from across the river. 
  • #K66: Continued drying out the structure, removed saturated attic insulation, and repaired siding. 
  • #K77: Post and pad foundation work (50% complete). 
  • #K79: Fabricated and installed foundation pads.
  • #K74: Continued drying out. 
  • Total of 28 team members onsite. 

4/02/26 

  • Cruz: One excavator drove piles out to sewage lagoon. Continued installing boardwalk sleepers and support brackets out to sewage lagoon. Continued helical installation out new community church. Cleared and laid out helical installations near village council building. Boardwalk out to fresh water source is near completion.
  • Helical piles to date: 1,719/Linear feet of boardwalk: 3,132. 
  • Brice/STG: Brice continued to monitor critical infrastructure. Electricians will assist linemen in connecting houses to power whenever Hog River is ready.
  • Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Continued boardwalk installation. 
  • Number of helicals installed to date: 341. 
  • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

​​​Facilities Daily Report

  • Work performed by Hog River Construction.
  • #K41: Stripped interior, removed wet insulation, dried out. 
  • #K46: Began installation of Toyo. 
  • #K57: Repaired water service lines; worked toward restoring running water. 
  • #K63: Finished post and pad foundation; made pads for foundation. 
  • #K64: Lifted house two feet on south end. 
  • #K66: Continued drying out; removed soggy attic insulation. 
  • #K74: Wrapped house with reinforced poly; began drying out. 
  • #K77: Began working on post and pad foundation. 
  • Total of 28 team members onsite. 

    4/01/26 

    • Cruz: One excavator drove piles out to church. 
    • Helical piles to date: 1,689/Linear feet of boardwalk: 2,932. 
    • Brice/STG: Brice continued to monitor critical infrastructure. Two linemen will come in today to begin bringing service to houses Hog River retrieved and relocated. 
    • Delta Backhaul: 24/7 helical installation; there is one SANY excavator driving helicals. Continuing to install sleepers and sway bars with hardware. Removed snow and temporary boardwalk in path of helical installation.  
    • Number of helicals installed to date: 328. 
    • Hog River: Moved/leveled houses. Set dog houses for installation. Dried/thawed houses. Removed wet/damaged material in houses. Installed new material as needed.

    Facilities Daily Report

    • Work performed by Hog River Construction.
    • #K41: Stripped interior, removed wet insulation, dried out. 
    • #K57: Repaired water service lines, worked on getting running water into house. 
    • #K63: Continued post and pad installation (90% completed); make pads for foundation. 
    • #K66: Lifting storage shed to return next to house; stripped floor insulation, skirted house, and began drying out. 
    • #K72: Moved house into new position from across river, removed winter skid from underneath; moved shed from across the river. 
    • #K74: Stripped floor insulation, skirted house with plywood. 
    • Total of 25 team members onsite. 