Chevak Operations Summary

Completed 11/9 until further notice. 


11/09/2025

  • No Change: Horizontal work complete.

11/08/2025

  • Storm response complete; roads reinforced and riprap installed.
  • Cruz Construction demobilized after walkthrough with city officials.
  • Community shifting to maintenance/monitoring; no near-term construction expected.

11/06/2025

  • Work complete, Cruz is demobilizing from community.

11/05/2025

  • Cruz repairing road in front of clinic.

11/04/2025

  • No change - Cruz is working on grading and embankment at barge landing.

11/03/2025

  • Cruz working on grading and embankment at barge landing.

11/01/2025

  • Cruz has material stockpiled at this site from a pervious project.
  • Crews onsite begin working on filling the potholes and blading the road with their material on hand.
  • Breaking up material in stockpile.

10/28/2025

 

  • Cruz has material stockpiled at this site from a previous project.
  • Plan to have a crew mobilize from Shishmaref to Chevak tomorrow to begin working on filling the potholes and blading the road with their material on hand.

10/21/2025 - Infrastructure Damage Assessment.


10/20/2025 - Infrastructure Damage Assessment.


10/15/2025 - Infrastructure Damage Assessment.

11/3/2025

Cruz working on grading and embankment at barge landing.