Alakanuk Operations Summary

11/07/2025

  • Bundled into regional contract package; likely scheduled after Kotlik/Emmonak.
  • Local cleanup and temporary road patches complete; staging area designated.
  • Expect redeployment of regional crew for road/berm repairs next operational cycle.

11/05/2025

  • Work proposal for community forwarded for review and approval.


11/04/2025

  • Site visit with QAP took place on 11/3.
  • Work proposals for each community forwarded for review and approval.

11/03/2025

  • Planning site assessment with QAP and construction in progress.


10/30/2025

  • Planning site assessment with QAP scheduled for Nov. 3 this week to define scope and estimate prior to freeze up.


10/26/2025

  • Temporary Work Authorization for QAP, site work plans received by construction, working with contractor on scope and schedule.


10/21/2025 - Infrastructure Damage Assessment.


10/15/2025 - Infrastructure Damage Assessment.